I want to search for...
Permit #2021100257
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7028-00030-0270 |
| CONDITIONED SPACE: 1815 sqft |
| GARAGE: 396 sqft |
| OPENED PORCH (WITH ROOF) : 352 sqft |
| OPENED PORCH (WITH ROOF) : 63 sqft |
| Total Square Footage: 2626 sqft |
| Block: 00030 |
| Subdivision: 2199 - SECTION 28-WYNNFIELD |
| Job Phone: (386) 672-8285 |
| Location Address: 24 PHILMONT LN |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 10/21/2021 |
| NOC: RECORDED |
| Applicant name: JOSEPH TODD VANACORE |
| Owner: BAYCORA, ALEXANDER & ADAM, CO-TRUSTEES |
|
Address OF THE GREGORY FAMILY IRREVOCABLE TRUST HOPEWELL JUNCTION, NY 12533 |
|
Address 103 LAMALA LANE HOPEWELL JUNCTION, NY 12533 |
| Lot: 0270 |
| Contracted Stated Job Value: ¤179,999.00 |
| Job Description: BUILDING A SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
VANACORE CONSTRUCTION INC.
| Status | Location Address | Mailing Address | State License Number | Phone |
| INACTIVE |
1451 N US HIGHWAY 1 Ormond Beach, FL 32174 |
SUITE 13 Ormond Beach, FL 32174 |
CBC058991 (Exp: 08/31/2024) | (386) 672-8285 |
Sub Contractors
JEFFREY DALE KNIGHT
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
923 ASHMEADE CT PORT ORANGE, FL 32127 |
CFC057351 (Exp: 08/31/2026) | 386-345-3857 | 386-345-4443 |
SHAWN MICHAEL HISS
| Status | Location Address | State License Number | Phone |
| ACTIVE |
1315 LPGA BLVD HOLLY HILL, FL 32117 |
CAC1813585 (Exp: 08/31/2026) | (386)672-8688 |
VERNON JACK SMITH III
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
224 KIRKLAND ROAD NEW SMYRNA BEACH, FL 32169 |
EC13004432 (Exp: 08/31/2026) | 386-409-3616 | 386-409-3616 |
ALFRED N FYOCK JR
| Status | Location Address | Mailing Address | State License Number | Phone | Fax |
| ACTIVE |
387 SAULS ORMOND BEACH, FL 32174 |
ST ORMOND BEACH, FL 32174 |
CCC1329075 (Exp: 08/31/2026) | 386-566-6112 | 386-673-4299 |
Inspection History
| Type | Request Date | Result | Inspector |
| ROW- PROJECT STATUS | 03/22/2023 | APPROVED | GBERTOLA |
| U -UTILITY RESIDENTIAL FINAL | 01/25/2023 | FINAL APPROVED | LFITZGERALD |
| Note: 1/24/2023 - PREVIOUS INSPECTION NOTES need accress to garage to inspect pep circuit breaker | |||
| U -UTILITY RESIDENTIAL FINAL | 01/24/2023 | Disapproved -FEE REQUIRED | LFITZGERALD |
| Note: need accress to garage to inspect pep circuit breaker | |||
| ROW - FINAL APRON (AFTER POUR) | 01/24/2023 | APPROVED | PFLANAGAN |
| Note: Inspector Notes from Inspection 9471 01/19/23= NEED TO ADD SOD BY THE PEP TANK TO MOVE THE WATER AWAY. IN THE BACK YARD BY THE END OF THE PROPERTY LINE (SLOPE) NEED TO SODDED ALL THE WAY DOWN TO PREVENT WASH OUT. ON THE LEFT SIDE BY THE VYNNIL FENCE NEED TO REMOVE THE MULCH. Flat work, i.e., slabs, walkways, hardscaping, patios, decking or AC pads are not allowed in any utility easements. Additionally, decorative objects, columns, light poles, mulch, stones, plantings or landscaping of any kind, is not allowed in the Right of Way (the swale area, between the edge of pavement and the property line). SEC 300.03 C.F | |||
| ROW- PROJECT STATUS | 01/19/2023 | APPROVED - AS NOTED | GBERTOLA |
| Note: 01/19/23= I did contact CM Jack Daniels ONLY CONTACT I HAVE FOR THIS COMPANY. PLEASE CONTACT THE INSPECTOR AT 386-986-7660 GBERTOLA . OR PROVIDE A CONTACT PHONE NUMBER FOR THE CM IN THIS AREA THAN YOU . +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ NOTE TO INSPECTOR: Builder requested a meeting with an inspector to go over an issue. Per email said in part: "The superintendent needs to go over the ROW elevation and the centerline of the road elevation, per our inspection results". Please contact Super for Maronda Homes and give him a rough ETA. | |||
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 01/19/2023 | APPROVED | GBERTOLA |
| Note: 01/19/23= CORRECTION WERE MADE THE PROPERTY LINE IS HIGHER THEN THE CROWN OF THE ROAD. | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 01/19/2023 | APPROVED | GBERTOLA |
| ROW - STORMWATER FINAL | 01/19/2023 | APPROVED - AS NOTED | GBERTOLA |
| Note: 01/19/23= NEED TO ADD SOD BY THE PEP TANK TO MOVE THE WATER AWAY. IN THE BACK YARD BY THE END OF THE PROPERTY LINE (SLOPE) NEED TO SODDED ALL THE WAY DOWN TO PREVENT WASH OUT. ON THE LEFT SIDE BY THE VYNNIL FENCE NEED TO REMOVE THE MULCH. Flat work, i.e., slabs, walkways, hardscaping, patios, decking or AC pads are not allowed in any utility easements. Additionally, decorative objects, columns, light poles, mulch, stones, plantings or landscaping of any kind, is not allowed in the Right of Way (the swale area, between the edge of pavement and the property line). SEC 300.03 C.F | |||
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 01/11/2023 | CANCELLED BY APPLICANT | WEB |
| Note: 1/10/2023 - PREVIOUS INSPECTION NOTES The front property line/right away elevation are to be equal to or greater than the centerline of the road elevation. (I) cHECK THE FIANL SURVEY REMARKS | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 01/11/2023 | CANCELLED BY APPLICANT | WEB |
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 01/10/2023 | Disapproved - NO FEE | GBERTOLA |
| Note: The front property line/right away elevation are to be equal to or greater than the centerline of the road elevation. (I) CHECK THE FIANL SURVEY REMARKS | |||
| U-CROSS CONNECTION | 01/04/2023 | APPROVED - AS NOTED | LFITZGERALD |
| Note: well irrigation-no cross connection | |||
| BLD - BUILDING FINAL | 12/29/2022 | Approval - Private Provider | PPROVIDER |
| ROW- PRE-APRON (PRE-POUR) | 10/17/2022 | APPROVED | GBERTOLA |
| Note: AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS BEFORE POURING. MAKE SURE IS 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL | |||
| ELECTRIC - EARLY POWER | 09/25/2022 | Approval - Private Provider | PPROVIDER |
| GRAVITY SEWER TEST | 09/06/2022 | Approval - Private Provider | PPROVIDER |
| U - SEWER TIE IN | 09/01/2022 | APPROVED | MGIBSON |
| PEP TANK INSTALLATION REQUEST | 08/19/2022 | APPROVED | CSTONE |
| Note: THIS IS A REINSPECTION ADDED ON 7/14/2022 2:40:55 PM dumpster | |||
| PEP TANK INSTALLATION REQUEST | 07/14/2022 | Disapproved - NO FEE | CSTONE |
| Note: dumpster | |||
| LATH/BRICK/ WATER BARRIER | 06/27/2022 | Approval - Private Provider | PPROVIDER |
| INSULATION | 06/17/2022 | Approval - Private Provider | PPROVIDER |
| ALL ROUGH | 06/06/2022 | Approval - Private Provider | PPROVIDER |
| ROOF VALLEY & METAL | 04/27/2022 | Approval - Private Provider | PPROVIDER |
| WALL SHEATHING | 04/15/2022 | Approval - Private Provider | PPROVIDER |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 04/15/2022 | Approval - Private Provider | PPROVIDER |
| TIE BEAM / LINTEL | 03/10/2022 | Approval - Private Provider | PPROVIDER |
| FOUND SURVEY APPROVED (OFFICE) | 03/03/2022 | APPROVED | TBAKER |
| PLUMBING 1ST ROUGH UNDERGROUND | 02/23/2022 | Approval - Private Provider | PPROVIDER |
| MONOLITHIC SLAB | 02/23/2022 | Approval - Private Provider | PPROVIDER |
| WATER METER INSTALLATION REQUEST | 01/05/2022 | APPROVED | TCHURCHILL |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 03/03/2022 | 03/03/2022 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 03/03/2022 | 03/03/2022 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 03/03/2022 | 03/03/2022 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 03/03/2022 | 03/03/2022 |
| Note: Released By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 10/13/2021 | 10/13/2021 |
| Note: Released By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 10/13/2021 | 10/13/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 10/13/2021 | 10/20/2021 |
| Note: Released By: GABRIEL BERTOLA - (386)225-3840 - GBERTOLA@PALMCOASTGOV.COM | |||
| CUSVC | COMPLETE | 10/06/2021 | 10/07/2021 |
| Note: Released By: HALEIGH HAND - - | |||
| ENGIN1 | COMPLETE | 10/06/2021 | 10/06/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| LOCATE | COMPLETE | 10/06/2021 | 10/11/2021 |
| Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 10/06/2021 | 10/12/2021 |
| Note: Released By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM | |||
| ZON | HOLD | 10/06/2021 | 10/08/2021 |
| Note: Held By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM Please provide the correct Flood Panel Number on survey and site plan. | |||
| SWALE | COMPLETE | 10/06/2021 | 12/09/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| SW ENG REINSPECTION 20 | ¤20.00 | 01/25/2023 |
| REINSPECTION FEE | ¤40.00 | 01/25/2023 |
| SURCHARGE FS 533.721 | ¤11.12 | 10/21/2021 |
| SURCHARGE - FS 468.631 | ¤16.69 | 10/21/2021 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 10/21/2021 |
| SW ENG INSPECTION 80 | ¤80.00 | 10/21/2021 |
| SW ENG PRE APRON | ¤30.00 | 10/21/2021 |
| SW ENG - REVIEW 20 | ¤20.00 | 10/21/2021 |
| SW ENG RES REVIEW 200 | ¤200.00 | 10/21/2021 |
| 3% TRANS IMPACT FEE CREDIT | (¤51.54) | 10/21/2021 |
| SEWER CREDIT | (¤650.00) | 10/21/2021 |
| SEWER INSPECTION | ¤25.00 | 10/21/2021 |
| SEWER CAPITAL FACILITY | ¤4,664.55 | 10/21/2021 |
| WATER CAPITAL FACILITY FEE | ¤3,424.45 | 10/21/2021 |
| SITE PLAN 30 | ¤30.00 | 10/21/2021 |
| METER - DEPOSIT | ¤60.00 | 10/21/2021 |
| WATER- TURN ON | ¤25.00 | 10/21/2021 |
| ADMINISTRATIVE - RESID PP | ¤225.00 | 10/21/2021 |
| INSPECTION - RESIDENTIAL | ¤646.25 | 10/21/2021 |
| PLAN REVIEW - RESIDENTIAL | ¤183.30 | 10/21/2021 |
| CONNECTION FEES | ¤1,017.83 | 10/21/2021 |
| 3% FIRE IMPACT FEE CREDIT | (¤11.01) | 10/21/2021 |
| IMPACT FEE FIRE | ¤367.00 | 10/21/2021 |
| IMPACT FEE PARKS | ¤1,199.12 | 10/21/2021 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 10/21/2021 |
| IMPACT FEE TRANSPORTATION | ¤1,718.00 | 10/21/2021 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 10/21/2021 |
| 3% PARKS IMPACT FEE CREDIT | (¤35.97) | 10/21/2021 |
| SW ENG REINSPECTION 20 | ¤20.00 | |
| Fees | Total Due: ¤20.00 | Total Paid: ¤16,899.79 |