I want to search for...
Permit #2025050872
Permit Details
Status: INSPECT
| Parcel Id: 07-11-31-7023-00630-0190 |
| CONDITIONED SPACE: 2901 sqft |
| Total Square Footage: 2901 sqft |
| Block: 00630 |
| Subdivision: - |
| Job Phone: 904-888-6443 |
| Location Address: 3 WHELAN PL |
| Type: DU - DUPLEX |
| Issue Date: 10/02/2025 |
| NOC: RECORDED |
| Applicant name: AMIR BENTOV |
| Owner: ADBT 51 LLC |
|
Address 3225 MCLEOD DRIVE LAS VEGAS, NV 89121 |
|
Address SUITE 777 LAS VEGAS, NV 89121 |
| Lot: 0190 |
| Contracted Stated Job Value: ¤350,000.00 |
| Job Description: Duplex |
| Type: CN |
Contractor
MAVEN HOMES LLC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
2800 N 6TH ST UNIT 790 , |
CRC1333741 (Exp: 08/31/2026) | 904-667-4330 |
Sub Contractors
GLEN WILLIAM KEHLE
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
P. O. Box 353511 BUNNELL, FL 32110 |
CFC057241 (Exp: 08/31/2026) | (386) 447-4249 | (386) 437-8488 |
JOSEPH HORATIO STRADA JR
| Status | Location Address | State License Number | Phone |
| ACTIVE |
3400 ST JOHNS PARKWAY SANFORD, FL 32771 |
EC13003715 (Exp: 08/31/2026) | 877-906-1113 |
JOSEPH H STRADA JR
| Status | Location Address | State License Number | Phone |
| ACTIVE |
3400 ST JOHNS PKWY SANFORD, FL 32771 |
CAC043953 (Exp: 08/31/2026) | 877-906-1113 |
Inspection History
| Type | Request Date | Result | Inspector |
| ELECTRIC - EARLY POWER | 05/26/2026 | Approval - Private Provider | PPROVIDER |
| ROW- PRE-APRON (PRE-POUR) | 05/21/2026 | APPROVED - AS NOTED | TPOLACEK |
| Note: 05-21-26 TPOLACEK**** MADE A FEW ADJUSTMENTS WITH CONTRACTOR ON RIGHT SIDE APRON FLARE. AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS MAKE SURE TO USE 3000 PSI CONCRETE REINFORCED WITH WWF 6X6.W1.4 MESH OR FIBERGLASS REINFORCED CONCRETE (FRC) DRAWING 300,E RESIDENTIAL CULVERT DETAIL BEFORE POURING. TICKET OF CONCRETE MIX DESIGN SHALL BE UPLOADED INTO PERMIT PORTAL. 8.a. IF FIBERGLASS OPTION IS USED, DOCUMENTATION OF THE ( FRC) CONTAINING THE FIBERGLASS MUST BE ATTACHED TO THE PERMIT PRIOR TO REQUESTING AN AFTER-POUR INSPECTION. 8.b. IF MESH OPTION IS USED, IT SHALL BE IN PLACE AT THE TIME OF THE PRE-POUR. WOOD CONTROL JOINTS ARE PROHIBITED IN THE RIGHT-OF-WAY. SAWCUT SHALL BE PROVIDED AT THE EDGE OF ROW AND EVERY 12' THEREAFTER, OR A MINIMUM OF 2 SAWCUTS WHICHEVER IS GREATER" 5/14/2026 - PREVIOUS INSPECTION NOTES READY TO POUR UPPER PART OF DRIVEWAY ALL CONCRETE NEEDS TO BE A MINIMUM OF 3000PSI WITH FIBER OR WITH METAL MESH IN THE CONCRETE TO MEET ALL CITY'S STANDARDS. At the time of the inspection all minimum city requirements were met. It is the builders and the homowners responsibility to ensure that nothing changes after this Inspection is approved. It will not be on the city if any changes after this inspection. ------------------------------------------------------------------------------- 5/12/2026 - PREVIOUS INSPECTION NOTES 05-12-26 TPOLACEK*** LEFT TEXT MESSAGE FOR BUILDER TO PLEASE CALL REGARDING PARTIAL POUR. THE SITE WAS WASHED OUT TODAY DUE TO HEAVY RAIN ( SEE PHOTO) 5/11/2026 - PREVIOUS INSPECTION NOTES 5/11/26 CM CALLED AND ASKED TO HAVE THIS PREPOUR CANCELLED FOR TODAY. CANCELLING AS A COURTESY. | |||
| ROW- PRE-APRON (PRE-POUR) | 05/14/2026 | PARTIALLY APPROVED | PFLANAGAN |
| Note: READY TO POUR UPPER PART OF DRIVEWAY ALL CONCRETE NEEDS TO BE A MINIMUM OF 3000PSI WITH FIBER OR WITH METAL MESH IN THE CONCRETE TO MEET ALL CITY'S STANDARDS. At the time of the inspection all minimum city requirements were met. It is the builders and the homowners responsibility to ensure that nothing changes after this Inspection is approved. It will not be on the city if any changes after this inspection. ------------------------------------------------------------------------------- 5/12/2026 - PREVIOUS INSPECTION NOTES 05-12-26 TPOLACEK*** LEFT TEXT MESSAGE FOR BUILDER TO PLEASE CALL REGARDING PARTIAL POUR. THE SITE WAS WASHED OUT TODAY DUE TO HEAVY RAIN ( SEE PHOTO) 5/11/2026 - PREVIOUS INSPECTION NOTES 5/11/26 CM CALLED AND ASKED TO HAVE THIS PREPOUR CANCELLED FOR TODAY. CANCELLING AS A COURTESY. | |||
| ROW- PRE-APRON (PRE-POUR) | 05/12/2026 | Disapproved - NO FEE | TPOLACEK |
| Note: 05-12-26 TPOLACEK*** LEFT TEXT MESSAGE FOR BUILDER TO PLEASE CALL REGARDING PARTIAL POUR. THE SITE WAS WASHED OUT TODAY DUE TO HEAVY RAIN ( SEE PHOTO) 5/11/2026 - PREVIOUS INSPECTION NOTES 5/11/26 CM CALLED AND ASKED TO HAVE THIS PREPOUR CANCELLED FOR TODAY. CANCELLING AS A COURTESY. | |||
| ROW- PRE-APRON (PRE-POUR) | 05/11/2026 | CANCELLED BY APPLICANT | FSLADISH |
| Note: 5/11/26 CM CALLED AND ASKED TO HAVE THIS PREPOUR CANCELLED FOR TODAY. CANCELLING AS A COURTESY. | |||
| ROW- PROJECT STATUS | 04/15/2026 | Status Check | PFLANAGAN |
| Note: Met with contractor for grading in the back. Back right corner there are trees on the back property line so drainage will flow around those trees. Any question call Parren | |||
| GRAVITY SEWER TEST | 03/25/2026 | APPROVED | HCAMACHO |
| SEWER TIE IN | 03/25/2026 | APPROVED | HCAMACHO |
| PEP TANK INSTALLATION REQUEST | 02/24/2026 | APPROVED | ISANDERSON |
| Note: 2/18/2026 11:16:19 AM- PREVIOUS INSPECTION NOTES Dumpster in the way. | |||
| PEP TANK INSTALLATION REQUEST | 02/18/2026 | Disapproved - NO FEE | ISANDERSON |
| Note: Dumpster in the way. | |||
| INSULATION | 01/21/2026 | Approval - Private Provider | PPROVIDER |
| LATH/BRICK/ WATER BARRIER | 01/16/2026 | Approval - Private Provider | PPROVIDER |
| ELECTRIC-TUG | 01/13/2026 | Approval - Private Provider | PPROVIDER |
| FIREWALL FINAL | 01/13/2026 | Approval - Private Provider | PPROVIDER |
| ALL ROUGH | 01/12/2026 | Approval - Private Provider | PPROVIDER |
| FIREWALL DRYWALL NAILING | 01/08/2026 | Approval - Private Provider | PPROVIDER |
| FIREWALL FRAMING | 01/07/2026 | Approval - Private Provider | PPROVIDER |
| WALL SHEATHING | 12/18/2025 | Approval - Private Provider | PPROVIDER |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 12/18/2025 | Approval - Private Provider | PPROVIDER |
| ROOF VALLEY & METAL | 12/18/2025 | Approval - Private Provider | PPROVIDER |
| TIE BEAM / LINTEL | 11/17/2025 | Approval - Private Provider | PPROVIDER |
| MONOLITHIC SLAB | 10/28/2025 | Approval - Private Provider | PPROVIDER |
| FORMBOARD SURVEY (OFFICE USE ONLY) | 10/28/2025 | APPROVED | RRICKS |
| PLUMBING 1ST ROUGH UNDERGROUND | 10/22/2025 | Approval - Private Provider | PPROVIDER |
| GEOTECHNICAL REPORT APPROVAL (OFFICE USE) | 10/16/2025 | APPROVED | JMUNSON |
| WATER METER INSTALLATION REQUEST | 10/10/2025 | APPROVED | CBOWERMASTER |
| BLD - BUILDING FINAL | |||
| U-CROSS CONNECTION | |||
| ROW - FINAL APRON (AFTER POUR) | |||
| ROW- FINAL SURVEY/GRADING CERTIFICATION | |||
| Note: 4/15/26 Note to inspector : Met with contractor for grading in the back. Back right corner there are trees on the back property line so drainage will flow around those trees. Any question call Parren | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | |||
| ROW - FINAL INSPECTION | |||
| U -UTILITY RESIDENTIAL FINAL |
Review History
| Department | Status | Date In | Date Out |
| MECH | HOLD | 12/15/2025 | 12/15/2025 |
| Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Plans show 3/4 inch foam board (R5) on CMU walls. Energy Calcs say R7 on CMU walls. Revise calcs | |||
| SW1 | COMPLETE | 10/28/2025 | 10/28/2025 |
| Note: Released By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 10/28/2025 | 10/28/2025 |
| Note: Released By: SCOTT THOMAS - (386)986-3780 - STHOMAS@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 10/16/2025 | 10/16/2025 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 10/07/2025 | 10/07/2025 |
| Note: Released By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 10/07/2025 | 10/07/2025 |
| Note: Released By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 08/21/2025 | 08/21/2025 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 08/21/2025 | 08/25/2025 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ZON | HOLD | 08/14/2025 | 08/14/2025 |
| Note: Held By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM Elevation side plan: Missing banding around the corner of the home for at least two feet | |||
| BLD | HOLD | 08/14/2025 | 08/19/2025 |
| Note: Held By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM 1. ok 2. Provide detail for both UL337 and UL U914. 3. ok 4.ok 5. Plans need to be digitally verifiable. 3rd Request | |||
| ELEC | COMPLETE | 08/14/2025 | 08/18/2025 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ZON | HOLD | 08/08/2025 | 08/08/2025 |
| Note: Held By: MICHELLE RAMOS - (386)986-3780 - MRAMOS@PALMCOASTGOV.COM 1. Landscape plan missing. 2. Site plan can't have any drainage information on it. Drainage information should be on separate form. 3. Elevation missing roof pitch and another form of articulation. 4. Floor plan missing sqaure footage information. | |||
| ELEC | HOLD | 08/08/2025 | 08/12/2025 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Need orrect outlet spacing in all bed rooms on side A. NEC 2020 210.52 2. Need to show correct outlet spacing in kitchen. NEC 2020 210.52 3. Washer, dryer, range, bathroom, and outside outlets need to be GFCI protected. NEC 2020 210.8 4. bathrooms need to have correct outlets by sink. NEC 2020 210.52 (D) 5. Submit Electrical load calculations 6. Submit a duplex riser diagram that includes all wire sizes and breaker sizes. Also must include the surge protectors and outside disconnects. NEC 2020 230.67, 230.85 7. Need correct outlet spacing in dining room side A. NEC 2020 210.52 8. Need service outlet by the A/C unit NEC 2020 210.63 | |||
| BLD | HOLD | 08/08/2025 | 08/11/2025 |
| Note: Held By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM 1. ok 2. Provide detail for both UL337 and UL U914. 3. ok 4.ok 5. Plans need to be digitally verifiable. 2nd Request | |||
| SW1 | COMPLETE | 08/08/2025 | 08/08/2025 |
| Note: Released By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM | |||
| BADMIN | INFORMATION | 08/08/2025 | 08/08/2025 |
| Note: Marked INFORMATION By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM NO plans submitted | |||
| SWALE | COMPLETE | 05/21/2025 | 06/17/2025 |
| Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM | |||
| BADMIN | COMPLETE | 05/20/2025 | 05/28/2025 |
| Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM | |||
| BLD | HOLD | 05/20/2025 | 05/28/2025 |
| Note: Held By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM 1. Truss layout and package is not for this address. 2. Provide detail for both UL337 and UL U914. 3. Roofing worksheet FL# 30310.1-R1 out of cycle. We are in the 2023 code cycle. FL# 10626.1-R21 out of cycle. 4.Product Approval FL# 5675-R4 not valid FL# 101922-R10 not valid FL# 13223.2-R5 out of cycle. FL# 13265.1-R6 out of cycle. FL# 30310-R2 out of cycle. FL# 18449-R3 not valid. FL# 10626.1-R19 out of cycle. FL# 10456.4-R6 out of cycle. FL# 16230-R8 out of cycle. FL# 1999.2-R7 out of cycle. FL# 18389.1-R2 out of cycle. 5. Plans need to be digitally verifiable. | |||
| CUSVC | COMPLETE | 05/20/2025 | 05/28/2025 |
| Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM | |||
| ELEC | HOLD | 05/20/2025 | 05/23/2025 |
| Note: Held By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM 1. Need orrect outlet spacing in all bed rooms on side A. NEC 2020 210.52 2. Need to show correct outlet spacing in kitchen. NEC 2020 210.52 3. Washer, dryer, range, bathroom, and outside outlets need to be GFCI protected. NEC 2020 210.8 4. bathrooms need to have correct outlets by sink. NEC 2020 210.52 (D) 5. Submit Electrical load calculations 6. Submit a duplex riser diagram that includes all wire sizes and breaker sizes. Also must include the surge protectors and outside disconnects. NEC 2020 230.67, 230.85 7. Need correct outlet spacing in dining room side A. NEC 2020 210.52 8. Need service outlet by the A/C unit NEC 2020 210.63 | |||
| ENGIN1 | COMPLETE | 05/20/2025 | 05/21/2025 |
| Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM | |||
| GAS | CANCEL | 05/20/2025 | 05/22/2025 |
| LOCATE | COMPLETE | 05/20/2025 | 05/21/2025 |
| Note: Released By: CANDACE BOWERMASTER - - CBOWERMASTER@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 05/20/2025 | 05/23/2025 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 05/20/2025 | 05/27/2025 |
| Note: Released By: RODNEY RICKS - (386)986-2001 - RRICKS@PALMCOASTGOV.COM | |||
| ZON | HOLD | 05/20/2025 | 05/21/2025 |
| Note: Held By: SCOTT THOMAS - (386)986-3780 - STHOMAS@PALMCOASTGOV.COM 1. Sec. 13.03. - Single-Family and Duplex Residential Architectural Requirements. This section shall apply to all single-family and duplex residential dwelling units. 13.03.01. Architectural styles. A.Duplex residential dwelling units shall have the same architectural design, materials, and colors for both sides 2. DUPLEX DOES NOT MEET SAME ARCHITECTURLA DESIGN 3. INDICATE OUTSIDE MATERIAL ON COLOR MATERIAL SHEET (STUCCO, SIDING,...) 4. INDICATE DRIVEWAY WIDTH FOR BOTH GARAGES 5. LRV INCORRECT. MUST BE ABOVE 80 6. TOTAL SQ FT INCORRECT ON FLOOR PLAN. 2900, NOT 2901 7. FLOOR PLAN MISSING TOTAL FOR GARAGE, PATIO, FRONT ENTRANCE 8. ELEVATIONS MISSING ROOF PITCH, ARTICULATION, MASSING TREATMENT 9. INDICATE BANDING AROUND WINDOWS ON ELEVATION 10. SETBACKS NOT MET FOR DUPLEX LOT. (25') | |||
| MECH | PENDING |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| WATER- TURN ON | ¤100.00 | 10/02/2025 |
| ADJUSTMENT 10% | (¤40.91) | 10/02/2025 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 10/02/2025 |
| ADMINISTRATIVE - RESID PP | ¤225.00 | 10/02/2025 |
| PLAN REVIEW - RESIDENTIAL | ¤379.08 | 10/02/2025 |
| FC IMPACT FEE EMS | ¤124.00 | 10/02/2025 |
| IMPACT FEE FIRE | ¤869.02 | 10/02/2025 |
| FC IMPACT FEE LAW ENFORCEMENT | ¤436.00 | 10/02/2025 |
| FC IMPACT FEE LIBRARY | ¤536.00 | 10/02/2025 |
| IMPACT FEE PARKS | ¤3,656.02 | 10/02/2025 |
| IMPACT FEE SCHOOL | ¤10,900.00 | 10/02/2025 |
| IMPACT FEE TRANSPORTATION | ¤2,974.00 | 10/02/2025 |
| PEP TANK INSTALL | ¤1,513.48 | 10/02/2025 |
| WASTEWATER MAIN EXTENSION IMPA | ¤4,770.00 | 10/02/2025 |
| SURCHARGE FS 533.721 | ¤5.93 | 10/02/2025 |
| SURCHARGE - FS 468.631 | ¤8.90 | 10/02/2025 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 10/02/2025 |
| SW ENG INSPECTION 80 | ¤80.00 | 10/02/2025 |
| SW ENG PRE APRON | ¤30.00 | 10/02/2025 |
| SW ENG - REVIEW 20 | ¤20.00 | 10/02/2025 |
| SW ENG RES REVIEW 200 | ¤200.00 | 10/02/2025 |
| WASTEWATER PERM INSPECTION | ¤80.00 | 10/02/2025 |
| WASTEWATER PERM REVIEW | ¤100.00 | 10/02/2025 |
| SEWER CAPITAL FACILITY | ¤8,830.00 | 10/02/2025 |
| WATER CAPITAL FACILITY FEE | ¤7,580.98 | 10/02/2025 |
| WATER PERMIT INSPECTION | ¤80.00 | 10/02/2025 |
| WATER MAIN EXTENSION IMPACT | ¤1,834.54 | 10/02/2025 |
| SITE PLAN 30 | ¤30.00 | 10/02/2025 |
| WASTEWATER MAIN EXTENSION IMPA | (¤4,770.00) | 09/26/2025 |
| SITE PLAN 30 | ¤30.00 | 09/26/2025 |
| SITE PLAN 30 | (¤30.00) | 09/26/2025 |
| WATER MAIN EXTENSION IMPACT | ¤1,834.54 | 09/26/2025 |
| WATER MAIN EXTENSION IMPACT | (¤1,834.54) | 09/26/2025 |
| WATER PERMIT INSPECTION | ¤80.00 | 09/26/2025 |
| WATER PERMIT INSPECTION | (¤80.00) | 09/26/2025 |
| WATER CAPITAL FACILITY FEE | (¤7,580.98) | 09/26/2025 |
| WATER CAPITAL FACILITY FEE | ¤7,580.98 | 09/26/2025 |
| SEWER CAPITAL FACILITY | ¤8,830.00 | 09/26/2025 |
| SEWER CAPITAL FACILITY | (¤8,830.00) | 09/26/2025 |
| WASTEWATER PERM REVIEW | ¤100.00 | 09/26/2025 |
| WASTEWATER PERM REVIEW | (¤100.00) | 09/26/2025 |
| WASTEWATER PERM INSPECTION | ¤80.00 | 09/26/2025 |
| WASTEWATER PERM INSPECTION | (¤80.00) | 09/26/2025 |
| SW ENG RES REVIEW 200 | ¤200.00 | 09/26/2025 |
| SW ENG RES REVIEW 200 | (¤200.00) | 09/26/2025 |
| SW ENG - REVIEW 20 | (¤20.00) | 09/26/2025 |
| SW ENG PRE APRON | ¤30.00 | 09/26/2025 |
| SW ENG PRE APRON | (¤30.00) | 09/26/2025 |
| SW ENG - REVIEW 20 | ¤20.00 | 09/26/2025 |
| SW ENG INSPECTION 80 | ¤80.00 | 09/26/2025 |
| SW ENG INSPECTION 80 | (¤80.00) | 09/26/2025 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 09/26/2025 |
| SW ENG - FOUNDATION SURVEY | (¤20.00) | 09/26/2025 |
| SURCHARGE - FS 468.631 | ¤8.90 | 09/26/2025 |
| SURCHARGE - FS 468.631 | (¤8.90) | 09/26/2025 |
| SURCHARGE FS 533.721 | ¤5.93 | 09/26/2025 |
| SURCHARGE FS 533.721 | (¤5.93) | 09/26/2025 |
| WASTEWATER MAIN EXTENSION IMPA | ¤4,770.00 | 09/26/2025 |
| PEP TANK INSTALL | ¤1,513.48 | 09/26/2025 |
| PEP TANK INSTALL | (¤1,513.48) | 09/26/2025 |
| IMPACT FEE TRANSPORTATION | ¤2,974.00 | 09/26/2025 |
| IMPACT FEE TRANSPORTATION | (¤2,974.00) | 09/26/2025 |
| IMPACT FEE SCHOOL | ¤10,900.00 | 09/26/2025 |
| IMPACT FEE SCHOOL | (¤10,900.00) | 09/26/2025 |
| IMPACT FEE PARKS | ¤3,656.02 | 09/26/2025 |
| IMPACT FEE PARKS | (¤3,656.02) | 09/26/2025 |
| FC IMPACT FEE LIBRARY | ¤536.00 | 09/26/2025 |
| FC IMPACT FEE LIBRARY | (¤536.00) | 09/26/2025 |
| FC IMPACT FEE EMS | (¤124.00) | 09/26/2025 |
| FC IMPACT FEE LAW ENFORCEMENT | (¤436.00) | 09/26/2025 |
| FC IMPACT FEE LAW ENFORCEMENT | ¤436.00 | 09/26/2025 |
| FC IMPACT FEE EMS | ¤124.00 | 09/26/2025 |
| PLAN REVIEW - RESIDENTIAL | ¤379.08 | 09/26/2025 |
| PLAN REVIEW - RESIDENTIAL | (¤379.08) | 09/26/2025 |
| IMPACT FEE FIRE | ¤869.02 | 09/26/2025 |
| IMPACT FEE FIRE | (¤869.02) | 09/26/2025 |
| ADMINISTRATIVE - RESID PP | (¤225.00) | 09/26/2025 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 09/26/2025 |
| ADMINISTRATIVE RESIDENTIAL | (¤30.00) | 09/26/2025 |
| ADMINISTRATIVE - RESID PP | ¤225.00 | 09/26/2025 |
| ADJUSTMENT 10% | (¤40.91) | 09/26/2025 |
| ADJUSTMENT 10% | ¤40.91 | 09/26/2025 |
| WATER- TURN ON | ¤100.00 | 09/26/2025 |
| WATER- TURN ON | (¤100.00) | 09/26/2025 |
| WATER- TURN ON | ¤100.00 | 09/24/2025 |
| WATER- TURN ON | (¤100.00) | 09/24/2025 |
| ADJUSTMENT 10% | ¤40.91 | 09/24/2025 |
| ADJUSTMENT 10% | (¤40.91) | 09/24/2025 |
| PLAN REVIEW - RESIDENTIAL | ¤379.08 | 09/24/2025 |
| PLAN REVIEW - RESIDENTIAL | (¤379.08) | 09/24/2025 |
| ADMINISTRATIVE - RESID PP | ¤225.00 | 09/24/2025 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 09/24/2025 |
| ADMINISTRATIVE RESIDENTIAL | (¤30.00) | 09/24/2025 |
| ADMINISTRATIVE - RESID PP | (¤225.00) | 09/24/2025 |
| IMPACT FEE FIRE | ¤869.02 | 09/24/2025 |
| IMPACT FEE FIRE | (¤869.02) | 09/24/2025 |
| FC IMPACT FEE EMS | ¤124.00 | 09/24/2025 |
| FC IMPACT FEE EMS | (¤124.00) | 09/24/2025 |
| FC IMPACT FEE LAW ENFORCEMENT | ¤436.00 | 09/24/2025 |
| FC IMPACT FEE LAW ENFORCEMENT | (¤436.00) | 09/24/2025 |
| FC IMPACT FEE LIBRARY | (¤536.00) | 09/24/2025 |
| FC IMPACT FEE LIBRARY | ¤536.00 | 09/24/2025 |
| IMPACT FEE PARKS | (¤3,656.02) | 09/24/2025 |
| IMPACT FEE PARKS | ¤3,656.02 | 09/24/2025 |
| IMPACT FEE SCHOOL | ¤10,900.00 | 09/24/2025 |
| IMPACT FEE SCHOOL | (¤10,900.00) | 09/24/2025 |
| IMPACT FEE TRANSPORTATION | (¤2,974.00) | 09/24/2025 |
| PEP TANK INSTALL | ¤1,513.48 | 09/24/2025 |
| PEP TANK INSTALL | (¤1,513.48) | 09/24/2025 |
| IMPACT FEE TRANSPORTATION | ¤2,974.00 | 09/24/2025 |
| WASTEWATER MAIN EXTENSION IMPA | (¤4,770.00) | 09/24/2025 |
| SURCHARGE FS 533.721 | ¤5.93 | 09/24/2025 |
| SURCHARGE FS 533.721 | (¤5.93) | 09/24/2025 |
| WASTEWATER MAIN EXTENSION IMPA | ¤4,770.00 | 09/24/2025 |
| SURCHARGE - FS 468.631 | (¤8.90) | 09/24/2025 |
| SURCHARGE - FS 468.631 | ¤8.90 | 09/24/2025 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 09/24/2025 |
| SW ENG - FOUNDATION SURVEY | (¤20.00) | 09/24/2025 |
| SW ENG INSPECTION 80 | (¤80.00) | 09/24/2025 |
| SW ENG INSPECTION 80 | ¤80.00 | 09/24/2025 |
| SW ENG RES REVIEW 200 | ¤200.00 | 09/24/2025 |
| SW ENG RES REVIEW 200 | (¤200.00) | 09/24/2025 |
| SW ENG - REVIEW 20 | ¤20.00 | 09/24/2025 |
| SW ENG PRE APRON | ¤30.00 | 09/24/2025 |
| SW ENG PRE APRON | (¤30.00) | 09/24/2025 |
| SW ENG - REVIEW 20 | (¤20.00) | 09/24/2025 |
| WASTEWATER PERM INSPECTION | ¤80.00 | 09/24/2025 |
| WASTEWATER PERM INSPECTION | (¤80.00) | 09/24/2025 |
| WASTEWATER PERM REVIEW | (¤100.00) | 09/24/2025 |
| SEWER CAPITAL FACILITY | ¤8,830.00 | 09/24/2025 |
| SEWER CAPITAL FACILITY | (¤8,830.00) | 09/24/2025 |
| WASTEWATER PERM REVIEW | ¤100.00 | 09/24/2025 |
| WATER CAPITAL FACILITY FEE | ¤7,580.98 | 09/24/2025 |
| WATER CAPITAL FACILITY FEE | (¤7,580.98) | 09/24/2025 |
| WATER PERMIT INSPECTION | ¤80.00 | 09/24/2025 |
| WATER PERMIT INSPECTION | (¤80.00) | 09/24/2025 |
| WATER MAIN EXTENSION IMPACT | (¤1,834.54) | 09/24/2025 |
| SITE PLAN 30 | ¤30.00 | 09/24/2025 |
| SITE PLAN 30 | (¤30.00) | 09/24/2025 |
| WATER MAIN EXTENSION IMPACT | ¤1,834.54 | 09/24/2025 |
| SITE PLAN 30 | ¤30.00 | 09/22/2025 |
| SITE PLAN 30 | (¤30.00) | 09/22/2025 |
| WATER MAIN EXTENSION IMPACT | ¤1,834.54 | 09/22/2025 |
| WATER MAIN EXTENSION IMPACT | (¤1,834.54) | 09/22/2025 |
| WATER PERMIT INSPECTION | ¤80.00 | 09/22/2025 |
| WATER PERMIT INSPECTION | (¤80.00) | 09/22/2025 |
| WATER CAPITAL FACILITY FEE | ¤7,580.98 | 09/22/2025 |
| WATER CAPITAL FACILITY FEE | (¤7,580.98) | 09/22/2025 |
| WASTEWATER PERM REVIEW | ¤100.00 | 09/22/2025 |
| SEWER CAPITAL FACILITY | ¤8,830.00 | 09/22/2025 |
| SEWER CAPITAL FACILITY | (¤8,830.00) | 09/22/2025 |
| WASTEWATER PERM REVIEW | (¤100.00) | 09/22/2025 |
| WATER METER W/ TAP | ¤4,653.86 | 09/22/2025 |
| WASTEWATER PERM INSPECTION | ¤80.00 | 09/22/2025 |
| WASTEWATER PERM INSPECTION | (¤80.00) | 09/22/2025 |
| SW ENG - REVIEW 20 | ¤20.00 | 09/22/2025 |
| SW ENG RES REVIEW 200 | ¤200.00 | 09/22/2025 |
| SW ENG RES REVIEW 200 | (¤200.00) | 09/22/2025 |
| SW ENG - REVIEW 20 | (¤20.00) | 09/22/2025 |
| SW ENG INSPECTION 80 | ¤80.00 | 09/22/2025 |
| SW ENG PRE APRON | ¤30.00 | 09/22/2025 |
| SW ENG PRE APRON | (¤30.00) | 09/22/2025 |
| SW ENG INSPECTION 80 | (¤80.00) | 09/22/2025 |
| SURCHARGE - FS 468.631 | (¤8.90) | 09/22/2025 |
| SURCHARGE - FS 468.631 | ¤8.90 | 09/22/2025 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 09/22/2025 |
| SW ENG - FOUNDATION SURVEY | (¤20.00) | 09/22/2025 |
| WASTEWATER MAIN EXTENSION IMPA | ¤4,770.00 | 09/22/2025 |
| SURCHARGE FS 533.721 | ¤5.93 | 09/22/2025 |
| SURCHARGE FS 533.721 | (¤5.93) | 09/22/2025 |
| WASTEWATER MAIN EXTENSION IMPA | (¤4,770.00) | 09/22/2025 |
| IMPACT FEE TRANSPORTATION | ¤2,974.00 | 09/22/2025 |
| PEP TANK INSTALL | ¤1,513.48 | 09/22/2025 |
| PEP TANK INSTALL | (¤1,513.48) | 09/22/2025 |
| IMPACT FEE TRANSPORTATION | (¤2,974.00) | 09/22/2025 |
| IMPACT FEE PARKS | ¤3,656.02 | 09/22/2025 |
| IMPACT FEE SCHOOL | ¤10,900.00 | 09/22/2025 |
| IMPACT FEE SCHOOL | (¤10,900.00) | 09/22/2025 |
| IMPACT FEE PARKS | (¤3,656.02) | 09/22/2025 |
| FC IMPACT FEE LIBRARY | ¤536.00 | 09/22/2025 |
| FC IMPACT FEE LIBRARY | (¤536.00) | 09/22/2025 |
| FC IMPACT FEE LAW ENFORCEMENT | ¤436.00 | 09/22/2025 |
| FC IMPACT FEE LAW ENFORCEMENT | (¤436.00) | 09/22/2025 |
| FC IMPACT FEE EMS | (¤124.00) | 09/22/2025 |
| FC IMPACT FEE EMS | ¤124.00 | 09/22/2025 |
| IMPACT FEE FIRE | ¤869.02 | 09/22/2025 |
| IMPACT FEE FIRE | (¤869.02) | 09/22/2025 |
| ADMINISTRATIVE - RESID PP | ¤225.00 | 09/22/2025 |
| PLAN REVIEW - RESIDENTIAL | ¤379.08 | 09/22/2025 |
| PLAN REVIEW - RESIDENTIAL | (¤379.08) | 09/22/2025 |
| ADMINISTRATIVE - RESID PP | (¤225.00) | 09/22/2025 |
| ADJUSTMENT 10% | (¤40.91) | 09/22/2025 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 09/22/2025 |
| ADMINISTRATIVE RESIDENTIAL | (¤30.00) | 09/22/2025 |
| ADJUSTMENT 10% | ¤40.91 | 09/22/2025 |
| WATER- TURN ON | ¤100.00 | 09/22/2025 |
| WATER- TURN ON | (¤100.00) | 09/22/2025 |
| CONTRACTOR CHANGE | ¤20.00 | |
| CONTRACTOR CHANGE | ¤20.00 | |
| RSI GENERAL INSPECTION 32.50 | ¤32.50 | |
| Fees | Total Due: ¤72.50 | Total Paid: ¤50,025.90 |