Permit #2005080609
Permit Details
Status: COED
| Parcel Id: 07-11-31-7037-00960-0130 |
| CONDITIONED SPACE: 2057 sqft |
| GARAGE: 610 sqft |
| OPENED PORCH (WITH ROOF) : 158 sqft |
| OPENED PORCH (WITH ROOF) : 50 sqft |
| Total Square Footage: 2875 sqft |
| Block: 0096 |
| Subdivision: - |
| Job Phone: (386) 672-8285 |
| Location Address: 9 LAKE PLACID PL |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 09/14/2005 |
| NOC: RECORDED |
| Applicant name: JOSEPH TODD VANACORE |
| Owner: JAMES AND LORIE WILCOX |
|
Address 10 BRIAN LANE PALM COAST, FL 32137 |
| Lot: 130 |
| Contracted Stated Job Value: ¤180,000.00 |
| Job Description: RESIDENTIAL SINGLE FAMILY HOME |
| Type: CN |
Contractor
VANACORE CONSTRUCTION INC.
| Status | Location Address | Mailing Address | State License Number | Phone |
| INACTIVE |
1451 N US HIGHWAY 1 Ormond Beach, FL 32174 |
SUITE 13 Ormond Beach, FL 32174 |
CBC058991 (Exp: 08/31/2024) | (386) 672-8285 |
Sub Contractors
DANIEL R SHEFFIELD
| Status | Location Address | State License Number | Phone |
| INACTIVE |
1100 Old Haw Creek Road Bunnell, FL 32110 |
EC0003100 (Exp: 08/31/2024) | 386-931-4729 |
Inspection History
| Type | Request Date | Result | Inspector |
| FINAL COMPLETE BUILDING INSPECTION | 05/15/2006 | CANCELLED BY INSPECTOR | JLEVRAULT |
| FINAL COMPLETE BUILDING INSPECTION | 05/12/2006 | FINAL APPROVED | JLEVRAULT |
| STORMWATER FINAL INSPECTION | 05/10/2006 | APPROVED - AS NOTED | BFCHAMBERLAIN |
| Note: THIS IS A REINSPECTION 28 s.f. road damages $324 | |||
| UTILITY COMPANY FINAL | 05/09/2006 | APPROVED | RANDRADE |
| STORMWATER FINAL INSPECTION | 05/08/2006 | Disapproved -FEE REQUIRED | BFCHAMBERLAIN |
| Note: Place sod on exposed earth on right adj property D.M. needed from #9 to ditch, and Vactron needed for #11,s culvert | |||
| RESIDENTIAL EARLY POWER | 04/17/2006 | APPROVED | MMOORE |
| PRE DRIVEWAY | 03/29/2006 | APPROVED | BFCHAMBERLAIN |
| LATH /BRICK FLASHING | 02/14/2006 | APPROVED | MMOORE |
| INSULATION INSPECTION | 02/03/2006 | APPROVED | MMOORE |
| ALL ROUGH | 01/31/2006 | APPROVED | MMOORE |
| ROOF SHEATHING/BRACES/TIES/ DOWN CELL | 01/18/2006 | APPROVED - AS NOTED | MMOORE |
| Note: 1. htt-22/ bottom at study finish nailing 2. 2-ply m. bath, m.b. room nail tight together 3. inspection #354 passes 4. complete above items by all-rough insp. | |||
| ROOF SHEATHING/BRACES/TIES/ DOWN CELL | 01/13/2006 | CANCELLED BY INSPECTOR | MMOORE |
| Note: PACK-OUT JACK CJ03 ON RIGHT 2. GROUT UNDER TRUSSES WITH STONELESS GROUT 3. CANCELLED BY INSPECTOR/ NO CHARGE/ CALL-IN NEXT WEEK FOR RE-INSPECTION/ WE ARE CLOSED ON MONDAY/ MARTIN LUTHER KING DAY | |||
| LINTEL | 12/01/2005 | APPROVED | MMOORE |
| MONOLITHIC SLAB INSPECTION/SLAB | 11/17/2005 | APPROVED | MMOORE |
| FIRST ROUGH PLUMBING INSPECTION | 11/16/2005 | APPROVED | JLEVRAULT |
| Note: THIS IS A REINSPECTION | |||
| FIRST ROUGH PLUMBING INSPECTION | 11/15/2005 | Disapproved -FEE REQUIRED | JLEVRAULT |
| Note: THIS IS A REINSPECTION NO HEAD PREASSURE ON DWV. | |||
| FIRST ROUGH PLUMBING INSPECTION | 11/14/2005 | Disapproved -FEE REQUIRED | JLEVRAULT |
| Note: No pressure on DWV. |
Review History
| Department | Status | Date In | Date Out |
| BLD | COMPLETE | 12/22/2005 | 12/22/2005 |
| Note: Released By: LWOODROME Revision: Window and door buck attachment | |||
| BLD | COMPLETE | 09/09/2005 | 09/09/2005 |
| Note: Released By: CCOTE Approved for Release per plan cover sheet. | |||
| BLD | HOLD | 08/23/2005 | 08/25/2005 |
| Note: Held By: CCOTE The following items must be submitted in order to complete the Building Permit Application plan review. 1. Sheet 7 appears to be missing. Please provide if there is indeed a sheet 7. 2. Provide a truss layout and connector schedule. 3. Provide a bond beam transition detail. 4. The floor plan references details A/5 & B/5 however these details could not be found on sheet 5. Please provide these details. 5. Clarify lintels to be used. The schedule lists 8x8 and the diagram below shows a 16" deep lintel that is filled and reinforced. The description, diagram and wall sections shall all match. | |||
| SWMD | COMPLETE | 08/17/2005 | 08/18/2005 |
| Note: Released By: LAPTEKAR | |||
| ZON | COMPLETE | 08/17/2005 | 08/23/2005 |
| Note: Released By: HHERKERT |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ENGINEERING ROAD DAMAGE | ¤324.00 | 05/15/2006 |
| EARLY POWER INSPECTION | ¤40.00 | 05/15/2006 |
| REINSPECTION FEE | ¤40.00 | 05/15/2006 |
| REINSPECTION FEE | ¤40.00 | 05/15/2006 |
| REVISION | ¤40.00 | 05/15/2006 |
| STORMWATER REINSPECTION FEE | ¤35.00 | 05/15/2006 |
| TRANSPORTATION IMPACT FEE3/RES | ¤2,885.00 | 09/14/2005 |
| SCHOOL BOARD IMPACT FEE RES | ¤3,600.00 | 09/14/2005 |
| STORM WATER PERMIT FEES | ¤80.00 | 09/14/2005 |
| ADMIN FEE | ¤20.00 | 09/14/2005 |
| ARC HOUSE REVIEW | ¤125.00 | 09/14/2005 |
| BUILDING CODE ADMIN FUND | ¤14.38 | 09/14/2005 |
| ELECTRIC FEE | ¤138.00 | 09/14/2005 |
| FIRE RES IMPACT FEE 4-1-05 | ¤173.47 | 09/14/2005 |
| MECHANICAL FEE | ¤138.00 | 09/14/2005 |
| PERMIT FEE | ¤702.00 | 09/14/2005 |
| PARKS IMPACT FEE 11-2-04 | ¤1,120.91 | 09/14/2005 |
| PLAN CHECK FEE | ¤72.00 | 09/14/2005 |
| PLUMBING FEE | ¤138.00 | 09/14/2005 |
| RADON FEE | ¤14.38 | 09/14/2005 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤9,740.14 |