I want to search for...
Permit #2005080703
Permit Details
Status: COED
| Parcel Id: 07-11-31-7032-00190-0010 |
| CONDITIONED SPACE: 2163 sqft |
| GARAGE: 660 sqft |
| OPENED PORCH (WITH ROOF) : 318 sqft |
| OPENED PORCH (WITH ROOF) : 67 sqft |
| Total Square Footage: 3208 sqft |
| Block: 0019 |
| Subdivision: - |
| Job Phone: (386) 445-2222 |
| Location Address: 57 ROYAL OAK DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 10/10/2005 |
| NOC: RECORDED |
| Applicant name: MICHAEL STEPHAN MULLEN |
| Owner: RALPH AND CHRISTINE MEROLA |
|
Address 6 CALENDER RD MANORVILLE, NY 11949 |
| Lot: 010 |
| Contracted Stated Job Value: ¤150,000.00 |
| Job Description: RESIDENTIAL SINGLE FAMILY HOME |
| Type: CN |
Contractor
TOWN & COUNTRY HOMES
| Status | Location Address | State License Number | Phone |
| ACTIVE |
1 Enterprise Drive Bunnell, FL 32110 |
CGC049972 (Exp: 08/31/2026) | (386) 445-2222 |
Inspection History
| Type | Request Date | Result | Inspector |
| FINAL COMPLETE BUILDING INSPECTION | 05/10/2006 | FINAL APPROVED | PGALLMANN |
| Note: THIS IS A REINSPECTION | |||
| FINAL COMPLETE BUILDING INSPECTION | 05/04/2006 | Disapproved -FEE REQUIRED | JGIBSON |
| Note: No energy calcs, no insulation cer., no numbers on house, light fixture in main room missing, land scaping not completed, front entry not completed, not ready, missing access panel for master tub. | |||
| STORMWATER FINAL INSPECTION | 05/02/2006 | APPROVED - AS NOTED | GLALIMA |
| Note: 30 FEET ROAD DAMAGE , | |||
| UTILITY COMPANY FINAL | 04/28/2006 | APPROVED | RANDRADE |
| RESIDENTIAL EARLY POWER | 04/27/2006 | APPROVED | JHINDMAN |
| PRE DRIVEWAY | 04/19/2006 | APPROVED | GLALIMA |
| INSULATION INSPECTION | 03/15/2006 | APPROVED | PGALLMANN |
| LATH /BRICK FLASHING | 03/10/2006 | APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION | |||
| LATH /BRICK FLASHING | 03/08/2006 | Disapproved -FEE REQUIRED | JGIBSON |
| Note: Not ready @ 10:05 am, window seel not in on left side of house. | |||
| ALL ROUGH | 03/07/2006 | APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION | |||
| ALL ROUGH | 03/03/2006 | Disapproved -FEE REQUIRED | JHINDMAN |
| Note: THIS IS A REINSPECTION need letter on rear porch beam per previous notice | |||
| FRAMING | 02/28/2006 | Disapproved -FEE REQUIRED | PGALLMANN |
| Note: NOT READY. 5 ITEM LIST IN BOX. | |||
| ALL ROUGH | 02/28/2006 | Disapproved -FEE REQUIRED | PGALLMANN |
| Note: WAITING TO PASS FRAMING. | |||
| EXTERIOR WALL SHEATHING/SHEAR WALL | 02/24/2006 | APPROVED | JGIBSON |
| ROOF SHEATHING/BRACES/TIES/ DOWN CELL | 02/24/2006 | APPROVED | JGIBSON |
| Note: THIS IS A REINSPECTION | |||
| TEMPORARY POLE | 02/15/2006 | APPROVED | PGALLMANN |
| Note: called fpl on 2/15/06 at 4:50 | |||
| ROOF SHEATHING/BRACES/TIES/ DOWN CELL | 02/13/2006 | Disapproved -FEE REQUIRED | JGIBSON |
| Note: See previous notice. | |||
| ROOF SHEATHING/BRACES/TIES/ DOWN CELL | 02/08/2006 | Disapproved -FEE REQUIRED | JGIBSON |
| Note: Previous items not addressed, T-13, & T-14 not straped @ header @ arch, letter from engineer on the use of SP4, insted of SP2,SP1, LETTER ON HEADER ON BACK LANI | |||
| EXTERIOR WALL SHEATHING/SHEAR WALL | 02/08/2006 | APPROVED | JGIBSON |
| Note: THIS IS A REINSPECTION | |||
| ROOF SHEATHING/BRACES/TIES/ DOWN CELL | 01/09/2006 | Disapproved -FEE REQUIRED | JGIBSON |
| Note: 1. strap & vapor barrier missing on truss gdr04 2. grout is missing under trusses throughout 3. right end of truss h05 has been cut 6" @ king. no repair noted. provide truss repairapproval 4. bolt missing on wood to cmv connection in garage 5. 2-ply truss hg01 not nailed, large gaps noted. 6. physical condition of truss engineering package & plans is unacepptable 7. cell under right side of garage door lintel is not filled | |||
| EXTERIOR WALL SHEATHING/SHEAR WALL | 01/09/2006 | Disapproved -FEE REQUIRED | JGIBSON |
| Note: too many deficiencies around the sheathed walls. partial list follows: 1) no crete slab under 3+ inches of sole plate at living room slider ( major bearing point) 2) bolts not installed on sole plate @ bow window 3) tripple header @! porch modified. Replace per plan note: Flitch is also incorrect. Page #2 | |||
| ROOF SHEATHING/BRACES/TIES/ DOWN CELL | 01/04/2006 | Disapproved - NO FEE | ARAYMOND |
| Note: MISSED FILLED CELLS/ MISSED NAILING /MISSING TRUSS ENGINEERING & LAYOUT | |||
| EXTERIOR WALL SHEATHING/SHEAR WALL | 01/04/2006 | Disapproved -FEE REQUIRED | ARAYMOND |
| Note: MISSED FILLED CELLS/ MISSED NAILING /MISSING TRUSS ENGINEERING & LAYOUT | |||
| TEMPORARY POLE | 12/15/2005 | APPROVED | TOUTLAND |
| Note: called susan at fpl on 12/16/05 at 11/ | |||
| LINTEL | 12/05/2005 | APPROVED | TOUTLAND |
| MONOLITHIC SLAB INSPECTION/SLAB | 11/15/2005 | APPROVED | JHINDMAN |
| FIRST ROUGH PLUMBING INSPECTION | 11/07/2005 | APPROVED | TOUTLAND |
Review History
| Department | Status | Date In | Date Out |
| BLD | COMPLETE | 03/01/2006 | 03/02/2006 |
| Note: Released By: LWOODROME Revision: Beam @ covered porch | |||
| BLD | COMPLETE | 02/20/2006 | 02/22/2006 |
| Note: Released By: LWOODROME Revision: Connectors @ bearing wall | |||
| BLD | COMPLETE | 10/03/2005 | 10/04/2005 |
| Note: Released By: CCOTE Approved for Release per plan cover sheet. | |||
| BLD | HOLD | 09/12/2005 | 09/13/2005 |
| Note: Held By: CCOTE The City received your revised drawings per the previous , however the following items must be submitted in order to complete the Building Permit Application plan review. 1. Please provide a detail showing how the gable end wall at the rear gable will be constructed to comply with FBC 2117.1. This wall must be structurally continuous from the slab to the ceiling plane or roof plane. | |||
| BLD | HOLD | 08/25/2005 | 08/29/2005 |
| Note: Held By: CCOTE The following items must be submitted in order to complete the Building Permit Application plan review. 1. Please provide a detail showing how the gable end wall at the rear gable will be constructed to comply with FBC 2117.1. The gable end bracing detail will not work at this location. | |||
| SWMD | COMPLETE | 08/19/2005 | 08/30/2005 |
| Note: Released By: LAPTEKAR | |||
| ZON | COMPLETE | 08/19/2005 | 08/25/2005 |
| Note: Released By: BWRY |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ENGINEERING ROAD DAMAGE | ¤340.00 | 05/15/2006 |
| EARLY POWER INSPECTION | ¤40.00 | 05/15/2006 |
| REINSPECTION FEE | ¤40.00 | 05/15/2006 |
| REINSPECTION FEE | ¤40.00 | 05/15/2006 |
| REINSPECTION FEE | ¤40.00 | 05/15/2006 |
| REINSPECTION FEE | ¤40.00 | 05/15/2006 |
| REINSPECTION FEE | ¤40.00 | 05/15/2006 |
| REINSPECTION FEE | ¤40.00 | 05/15/2006 |
| REINSPECTION FEE | ¤40.00 | 05/15/2006 |
| REINSPECTION FEE | ¤40.00 | 05/15/2006 |
| REINSPECTION FEE | ¤40.00 | 05/15/2006 |
| REINSPECTION FEE | ¤40.00 | 05/15/2006 |
| REVISION | ¤40.00 | 05/15/2006 |
| REVISION | ¤40.00 | 05/15/2006 |
| SCHOOL BOARD IMPACT FEE RES | ¤3,600.00 | 10/10/2005 |
| STORM WATER PERMIT FEES | ¤80.00 | 10/10/2005 |
| TRANSPORTATION IMPACT FEE3/RES | ¤2,885.00 | 10/10/2005 |
| FIRE RES IMPACT FEE 4-1-05 | ¤173.47 | 10/10/2005 |
| MECHANICAL FEE | ¤137.40 | 10/10/2005 |
| PERMIT FEE | ¤698.10 | 10/10/2005 |
| PARKS IMPACT FEE 11-2-04 | ¤1,120.91 | 10/10/2005 |
| PLAN CHECK FEE | ¤71.60 | 10/10/2005 |
| PLUMBING FEE | ¤137.40 | 10/10/2005 |
| RADON FEE | ¤16.04 | 10/10/2005 |
| ADMIN FEE | ¤20.00 | 10/10/2005 |
| ARC HOUSE REVIEW | ¤125.00 | 10/10/2005 |
| BUILDING CODE ADMIN FUND | ¤16.04 | 10/10/2005 |
| ELECTRIC FEE | ¤137.40 | 10/10/2005 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤10,078.36 |