Status: COED

Parcel Id: 07-11-31-7035-00230-0310
CONDITIONED SPACE: 2821 sqft
GARAGE: 574 sqft
OPENED PORCH (WITH ROOF) : 159 sqft
OPENED PORCH (WITH ROOF) : 104 sqft
Total Square Footage: 3658 sqft
Block: 0023
Subdivision: -
Job Phone: (904)363-7626
Location Address: 27 BURNABY LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 12/28/2005
NOC: RECORDED
Owner: WEEKLEY HOMES
Lot: 310
Contracted Stated Job Value: ¤180,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

WEEKLEY HOMES,L.P.
Status Location Address State License Number Phone Fax
CANCEL

448 VICTORIA HILLS DRIVE

DELAND, FL 32724

CBC053082 (Exp: 08/31/2012) (386)775-7206 (386)775-1709

Inspection History

Type Request Date Result Inspector
FINAL COMPLETE BUILDING INSPECTION 06/16/2006 FINAL APPROVED MMOORE
UTILITY COMPANY FINAL 06/13/2006 APPROVED TSCHWEERS
Note: THIS IS A REINSPECTION
UTILITY COMPANY FINAL 06/09/2006 Disapproved - NO FEE CBOEHME
Note: THIS IS A REINSPECTION
UTILITY COMPANY FINAL 06/06/2006 Disapproved - NO FEE TSCHWEERS
Note: FAILED NO POWER FROM HOUSE TO PEP PANEL THIS IS A REINSPECTION
STORMWATER FINAL INSPECTION 06/06/2006 APPROVED - AS NOTED BFCHAMBERLAIN
Note: Remove dumpster and sod swale across street. 36 sf road damage, $388.
UTILITY COMPANY FINAL 06/02/2006 Disapproved - NO FEE TSCHWEERS
Note: FAILED CANT LOCATE BALL VALVE COULDN'T SIGN PERMIT BOX FULL OF WATER ALL PAPERS WERE WET THIS IS A REINSPECTION
UTILITY COMPANY FINAL 05/19/2006 Disapproved - NO FEE TSCHWEERS
Note: FAILED NO SOD DOWN YET
RESIDENTIAL EARLY POWER 05/19/2006 APPROVED RMARVEL
Note: THIS IS A REINSPECTION
RESIDENTIAL EARLY POWER 05/15/2006 Disapproved -FEE REQUIRED RMARVEL
Note: THIS IS A REINSPECTION need to see connection to the UFER ground where available.
RESIDENTIAL EARLY POWER 05/08/2006 Disapproved -FEE REQUIRED JLEVRAULT
Note: THIS IS A REINSPECTION NOT READY.
DRIVEWAY 05/04/2006 APPROVED BFCHAMBERLAIN
INSULATION INSPECTION 04/04/2006 APPROVED ARITTER
ALL ROUGH 03/31/2006 APPROVED MMOORE
Note: THIS IS A REINSPECTION
ALL ROUGH 03/17/2006 Disapproved -FEE REQUIRED JLEVRAULT
Note: THIS IS A REINSPECTION
ALL ROUGH 03/13/2006 Disapproved -FEE REQUIRED ARITTER
Note: trusse braces missing on t 13 through t 25,, need test pressure on plumbing
LATH /BRICK FLASHING 03/13/2006 APPROVED ARITTER
ROOF SHEATHING/BRACES/TIES/ DOWN CELL 03/08/2006 APPROVED - AS NOTED JLEVRAULT
Note: STILL NO WASHERS AND NUTS AT FRONT ENTRANCE LEDGER. ALL ROUGH WILL NOT PASS UNTIL THIS ITEM IS COMPLETED. SECOND REQUEST.
RESIDENTIAL EARLY POWER 03/08/2006 Disapproved -FEE REQUIRED JLEVRAULT
Note: GROUND RODS TOO CLOSE. GROUND WIRE RUNNING UP WALL NOT PROTECTED WITH NMT OR SIMILAR PROTECTOR, NOR IS IT EFFECTIVELY CLAMPED TO THE MASONRY. BOXES NOT SAFE FOR EARLY POWER.
ROOF SHEATHING/BRACES/TIES/ DOWN CELL 02/28/2006 CANCELLED BY APPLICANT AIRS WEB
Note: THIS IS A REINSPECTION
ROOF SHEATHING/BRACES/TIES/ DOWN CELL 02/24/2006 Disapproved -FEE REQUIRED JLEVRAULT
Note: FILL TWO CELLS. ALL THREAD ROD IN GARAGE CAME LOOSE WITH MINIMAL FORCE. STRAPS CAN ONLY BE PACKED OUT 1 1/2". NO NUTS AND WASHERS AT FRONT ENTRANCE LEDGER. CANNOT INSPECT FRONT ENTRANCE ROUND ARCH WOOD TO BLOCK CONNECTIONS - NEED INSPECTION HOLES. INSTALL ALL WINDOW AND DOOR BUCKS AND TAPCON SAME FOR ROOF SHEATHING INSPECTION.
LINTEL 02/10/2006 APPROVED JLEVRAULT
FOUNDATION SURVEY APPROVED BY STORMWATER 02/09/2006 APPROVED WKINELL
MONOLITHIC SLAB INSPECTION/SLAB 01/30/2006 APPROVED MMOORE
FIRST ROUGH PLUMBING INSPECTION 01/26/2006 APPROVED MMOORE

Review History

Department Status Date In Date Out
BLD COMPLETE 03/02/2006 03/07/2006
Note: Released By: CCOTE Approved for Release. Revision: Truss T20a repair.
BLD COMPLETE 12/14/2005 12/16/2005
Note: Released By: CCOTE Approved for Release per plan cover sheet.
ZON COMPLETE 12/14/2005 12/14/2005
Note: Released By: HHERKERT
ZON HOLD 10/06/2005 12/12/2005
Note: Held By: HHERKERT corrected site plan needed
ZON HOLD 09/29/2005 10/06/2005
Note: Held By: BWRY NEED SQ/FT TABULATIONS ON PLANS
SW1 COMPLETE 09/29/2005 10/03/2005
Note: Released By: LAPTEKAR

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ENGINEERING ROAD DAMAGE ¤388.00 06/22/2006
EARLY POWER INSPECTION ¤40.00 06/22/2006
EARLY POWER INSPECTION ¤40.00 06/22/2006
EARLY POWER INSPECTION ¤40.00 06/22/2006
EARLY POWER INSPECTION ¤40.00 06/22/2006
REINSPECTION FEE ¤40.00 06/22/2006
REINSPECTION FEE ¤40.00 06/22/2006
REINSPECTION FEE ¤40.00 06/22/2006
REINSPECTION FEE ¤40.00 06/22/2006
REINSPECTION FEE ¤40.00 06/22/2006
REINSPECTION FEE ¤40.00 06/22/2006
REVISION ¤40.00 06/22/2006
SCHOOL BOARD IMPACT FEE RES ¤3,600.00 12/28/2005
STORM WATER PERMIT FEES ¤80.00 12/28/2005
TRANSPORTATION IMPACT FEE3/RES ¤2,885.00 12/28/2005
FIRE RES IMPACT FEE 4-1-05 ¤173.47 12/28/2005
MECHANICAL FEE ¤160.80 12/28/2005
PERMIT FEE ¤850.20 12/28/2005
PARKS IMPACT FEE 11-2-04 ¤1,120.91 12/28/2005
PLAN CHECK FEE ¤87.20 12/28/2005
PLUMBING FEE ¤160.80 12/28/2005
RADON FEE ¤18.29 12/28/2005
ADMIN FEE ¤20.00 12/28/2005
ARC HOUSE REVIEW ¤125.00 12/28/2005
BUILDING CODE ADMIN FUND ¤18.29 12/28/2005
ELECTRIC FEE ¤160.80 12/28/2005
Fees Total Due: ¤0.00 Total Paid: ¤10,288.76