Permit #2006040774
Permit Details
Status: COED
| CONDITIONED SPACE: 16449 sqft |
| GARAGE: 2535 sqft |
| OPENED PORCH (WITH ROOF) : 1158 sqft |
| Total Square Footage: 20142 sqft |
| Subdivision: 2085 - Tidelands at the Village Phase II |
| Job Phone: (407)838-1486 |
| Location Address: 95 RIVERVIEW BEND S |
| Type: BCR - BUILDING COMMERCIAL RESIDENTIAL -CONDO |
| Issue Date: 06/12/2006 |
| NOC: RECORDED |
| Applicant name: JAMES NICHOLSON BOYCE IV |
| Owner: CENTEX DESTINATION PROPERTIES |
|
Address 1064 GREENWOOD BLVD LAKE MARY, FL 32746 |
|
Address SUITE 200 LAKE MARY, FL 32746 |
| Contracted Stated Job Value: ¤1,672,110.00 |
| Job Description: BUILDING # 14, 12-PLEX CONDOMINIUM |
| Type: CN |
Contractor
CENTEX DESTINATION PROPERTIES
| Status | Location Address | Mailing Address | State License Number | Phone |
| CANCEL |
1064 GREENWOOD BLVD LAKE MARY, FL 32746 |
STE. 200 LAKE MARY, FL 32746 |
CGC1508651 (Exp: 08/31/2010) | (407)838-1486 |
Sub Contractors
TRUMAN E GAILEY JR
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
231 Jean St. DAYTONA BEACH, FL 32114 |
EC0000265 (Exp: 08/31/2026) | (386) 255-1418 | (386)255-3429 |
ROBERT G DELLO RUSSO
| Status | Location Address | State License Number | Phone | Fax |
| DECEASED |
531 CODISCO WAY SANFORD, FL 32771 |
CAC032448 (Exp: 08/31/2022) | (407)831-2665 | (407)333-3853 |
GARY WAYNE EVERS
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 740106 ORANGE CITY, FL 32763 |
CFC050566 (Exp: 08/31/2026) | 386-775-0909 | 386-775-0918 |
WAYNE STEED
| Status | Location Address | State License Number | Phone |
| CANCEL |
318 N. PINE AVENUE IVERNESS, FL 34450 |
CCC058299 (Exp: 08/31/2010) | (352)637-2422 |
CHARLES MONTGOMERY
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
111 TECH DRIVE SANFORD, FL 32771 |
74974000011990 (Exp: 06/30/2012) | (407)328-3000 | (407)328-3001 |
Inspection History
| Type | Request Date | Result | Inspector |
| FINAL COMPLETE BUILDING INSPECTION | 01/02/2007 | FINAL APPROVED | JLEVRAULT |
| Note: THIS IS A REINSPECTION CANNOT POST A 99 BECAUSE OF OUTSTANDING FIREWALL INSPECTIONS. | |||
| FINAL COMPLETE BUILDING INSPECTION | 12/27/2006 | Disapproved - NO FEE | JLEVRAULT |
| Note: CANCELLED BY JOB SUPER. | |||
| LANDSCAPE FINAL | 12/22/2006 | APPROVED | WBUTLER |
| FIRE FINAL | 12/22/2006 | APPROVED - AS NOTED | JPATTEE |
| Note: fire alarm not final yet | |||
| ENGINEERING FINAL | 12/19/2006 | APPROVED | DMAY |
| UTILITY COMMERCIAL FINAL | 12/18/2006 | APPROVED | KKING |
| Note: THIS IS A REINSPECTION | |||
| UTILITY COMPANY FINAL | 12/18/2006 | APPROVED | TSCHWEERS |
| H.V.A.C. FINAL | 12/15/2006 | APPROVED | JMCGOWEN |
| ELECTRICAL FINAL | 12/14/2006 | APPROVED | LHITES |
| PLUMBING FINAL | 12/13/2006 | APPROVED | JMCGOWEN |
| UTILITY COMPANY FINAL | 12/12/2006 | APPROVED | TSCHWEERS |
| UTILITY COMMERCIAL FINAL | 12/12/2006 | CANCELLED BY APPLICANT | KKING |
| COMMERCIAL POWER INSPECTION | 11/21/2006 | APPROVED | LHITES |
| Note: CALLED FPL SUSAN AT 11?21/06 | |||
| COMMERCIAL POWER INSPECTION | 11/09/2006 | APPROVED | LHITES |
| Note: 2nd floor | |||
| COMMERCIAL POWER INSPECTION | 11/07/2006 | APPROVED | RMARVEL |
| Note: 1st floor. | |||
| COMMERCIAL POWER INSPECTION | 10/27/2006 | APPROVED | LHITES |
| Note: release power to whole building. need meters to be set. all units plus house panel. | |||
| INSULATION INSPECTION | 10/24/2006 | APPROVED - AS NOTED | JLEVRAULT |
| Note: THIRD FLOOR INSULATION APPROVED. | |||
| INSULATION INSPECTION | 10/23/2006 | Disapproved -FEE REQUIRED | JHINDMAN |
| Note: FIRESTOP ALL CHASES AND DROP CEILINGS | |||
| COMMERCIAL POWER INSPECTION | 10/23/2006 | APPROVED | JMCGOWEN |
| FRAMING | 10/18/2006 | APPROVED - AS NOTED | JLEVRAULT |
| Note: THIRD FLOOR FRAMING APPROVED. | |||
| ALL ROUGH | 10/16/2006 | Disapproved -FEE REQUIRED | JMCGOWEN |
| Note: install slider frames, fireblock all chases, drop ceilings and changes in ceiling elevations per j.h. electric ok per r. marvel. hvac ok per joe mcgowen | |||
| INSULATION INSPECTION | 10/12/2006 | APPROVED - AS NOTED | JLEVRAULT |
| Note: THIS IS A REINSPECTION SECOND FLOOR INSULATION APPROVED. | |||
| INSULATION INSPECTION | 10/11/2006 | CANCELLED BY APPLICANT | JHINDMAN |
| Note: called at 9:30 | |||
| FIREWALL INSPECTION | 10/05/2006 | APPROVED | JPATTEE |
| Note: THIS IS A REINSPECTION | |||
| SECOND ROUGH PLUMBING INSPECTION | 10/05/2006 | APPROVED | JGIBSON |
| THRESHOLD/AFFIDAVIT | 10/04/2006 | APPROVED | PPROVIDER |
| Note: Threshold inspectors report. Law & Associates, Inc. Threshold Inspectors | |||
| INSULATION INSPECTION | 10/02/2006 | APPROVED | JLEVRAULT |
| Note: 1st floor insulation | |||
| FIREWALL INSPECTION | 09/29/2006 | CANCELLED BY APPLICANT | JPATTEE |
| Note: THIS IS A REINSPECTION CONTRACTOR CALLED IN TO SCHEDULE A FIREWALL INSPECTION FOR 9/29/06 | |||
| FRAMING | 09/29/2006 | APPROVED - AS NOTED | JLEVRAULT |
| Note: CONTRACTOR CALLED IN TO SCHEDULE A FRAMING INSPECTION FOR 9/29/06 SECOND FLOOR APPROVED. | |||
| FRAMING | 09/27/2006 | APPROVED - AS NOTED | JLEVRAULT |
| Note: THIS IS A REINSPECTION FIRST FLOOR FRAMING APPROVED. | |||
| FIREWALL INSPECTION | 09/27/2006 | CANCELLED BY APPLICANT | JPATTEE |
| FRAMING | 09/26/2006 | Disapproved -FEE REQUIRED | JLEVRAULT |
| Note: FIRST AND SECOND FLOOR NOT READY. | |||
| 2ND ROUGH ELECTRICAL | 09/22/2006 | APPROVED - AS NOTED | RMARVEL |
| Note: 2nd floor only. | |||
| H.V.A.C. ROUGH | 09/20/2006 | APPROVED - AS NOTED | JLEVRAULT |
| Note: SECOND FLOOR APPROVED. | |||
| FIREWALL INSPECTION | 09/20/2006 | APPROVED | JPATTEE |
| SECOND ROUGH PLUMBING INSPECTION | 09/14/2006 | APPROVED - AS NOTED | JGIBSON |
| Note: FIRST & SECOND FLOOR ONLY OK. | |||
| SECOND FLOOR SLAB INSPECTION | 09/07/2006 | APPROVED | PPROVIDER |
| Note: Threshold inspectors report. elevator cap slab | |||
| ROOF SHEATHING/BRACES/TIES/ DOWN CELL | 09/07/2006 | APPROVED | PPROVIDER |
| Note: Threshold inspectors report. | |||
| H.V.A.C. ROUGH | 09/01/2006 | APPROVED - AS NOTED | JLEVRAULT |
| Note: 1st floor only | |||
| 2ND ROUGH ELECTRICAL | 09/01/2006 | APPROVED | RMARVEL |
| LINTEL | 08/25/2006 | APPROVED | PPROVIDER |
| Note: Threshold inspectors report. parapit wall | |||
| LINTEL | 08/21/2006 | APPROVED | PPROVIDER |
| Note: Threshold inspectors report. 3rd floor lintel | |||
| TEMPORARY POLE | 08/16/2006 | APPROVED | JLEVRAULT |
| SECOND FLOOR SLAB INSPECTION | 08/09/2006 | APPROVED | PPROVIDER |
| Note: Threshold inspectors report. 3rd floor slab | |||
| SECOND FLOOR SLAB INSPECTION | 07/25/2006 | APPROVED | PPROVIDER |
| Note: Threshold inspectors report. 2nd floor slab. | |||
| LINTEL | 07/19/2006 | APPROVED | PPROVIDER |
| Note: Threshold inspectors report. 1st floor lintel | |||
| MONOLITHIC SLAB INSPECTION/SLAB | 07/08/2006 | APPROVED | PPROVIDER |
| Note: Threshold inspectors report. 1st floor slab | |||
| FIRST ROUGH PLUMBING INSPECTION | 07/06/2006 | APPROVED | PGALLMANN |
| FIRST ROUGH PLUMBING INSPECTION | 07/05/2006 | Disapproved -FEE REQUIRED | PGALLMANN |
| Note: CONDENSATE AND EMERGENCY WASTE LINES WERE BACK-PITCHED. | |||
| UNDERGROUND ELECTRICAL | 07/05/2006 | APPROVED | RMARVEL |
| STEM FOOTING FOUNDATION | 06/26/2006 | APPROVED | PPROVIDER |
| Note: Threshold inspectors report. | |||
| POURED CELL | 06/23/2006 | APPROVED | PPROVIDER |
| Note: Threshold inspectors report. | |||
| FOOTER | 06/19/2006 | APPROVED | PPROVIDER |
| Note: Threshold inspectors report |
Review History
| Department | Status | Date In | Date Out |
| BLD | COMPLETE | 10/17/2006 | 10/17/2006 |
| Note: Released By: CCOTE Approved for Release. REVISION: Truss repairs. | |||
| BLD | COMPLETE | 09/12/2006 | 09/13/2006 |
| Note: Released By: LWOODROME Revision: Truss repair | |||
| BLD | COMPLETE | 06/12/2006 | 06/13/2006 |
| Note: Released By: LWOODROME Revision: Plumbing risers | |||
| BLD | COMPLETE | 06/07/2006 | 06/12/2006 |
| Note: Released By: LWOODROME Approved for release. Checked by FR | |||
| BLD | HOLD | 05/24/2006 | 05/31/2006 |
| Note: Held By: FREODICA Comments on Permit Application No. 2006040774 - Tidelands - Building No. 14 1. On M3, indicate sizes of PVC condensate drain lines (plan key notes 3 & 8). Clarify plan key note 7 as exhaust layout is not typical for both 2nd & 3rd floors. 2. Similarly on E3, 2nd & 3rd floors are not typical on common areas. Clarify plan key notes 1, 2, & 3 locations at the 3rd floor as elevator equipment room is at the 2nd floor only. 3. On P5, Domestic Water Riser for Unit B does not match the layout. 4. On P6, coordinate pipe sizes on Overall Building Sanitary Riser against individual sanitary risers shown on P5. | |||
| FD1 | COMPLETE | 05/23/2006 | 05/23/2006 |
| Note: Released By: JPATTEE | |||
| FD1 | COMPLETE | 04/20/2006 | 05/02/2006 |
| Note: Released By: JPATTEE Held By: JPATTEE Plans do not provide design criteria for automatic fire sprinkler system per Florida Administrative Code. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 01/03/2007 |
| REINSPECTION FEE | ¤40.00 | 01/03/2007 |
| REINSPECTION FEE | ¤40.00 | 01/03/2007 |
| REINSPECTION FEE | ¤40.00 | 01/03/2007 |
| REVISION | ¤40.00 | 01/03/2007 |
| REVISION | ¤40.00 | 01/03/2007 |
| REVISION | ¤40.00 | 01/03/2007 |
| TRANS IMPACT FEE - CONDO/APT | ¤19,673.52 | 06/12/2006 |
| ADMIN FEE | ¤20.00 | 06/12/2006 |
| BUILDING CODE ADMIN FUND | ¤100.71 | 06/12/2006 |
| ELECTRIC FEE | ¤1,033.80 | 06/12/2006 |
| FIRE COMM IMPACT FEE 4/1/06 | ¤10,012.59 | 06/12/2006 |
| FIRE PLANS REVIEW | ¤201.42 | 06/12/2006 |
| MECHANICAL FEE | ¤1,033.80 | 06/12/2006 |
| PERMIT FEE | ¤9,201.50 | 06/12/2006 |
| PARKS IMPACT FEE 4/1/06 | ¤13,908.24 | 06/12/2006 |
| PLUMBING FEE | ¤1,033.80 | 06/12/2006 |
| RADON FEE | ¤100.71 | 06/12/2006 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤56,600.09 |