I want to search for...

Permit #2006041116

Permit Details

Status: FINAL

Parcel Id: 07-11-31-7006-00070-0150
Block: 00070
Subdivision: -
Job Phone: (386)586-0050
Location Address: 15 FLORAL CT
Type: SW - SEAWALL
Issue Date: 08/29/2006
NOC: Unknown
Applicant name: EDWARD RAY MULLINS
Owner: COPELAND M ARNOLD

Address

25 CLASSIC COURT S

PALM COAST, FL 32036

Lot: 0150
Contracted Stated Job Value: ¤19,850.00
Job Description: 90 FT VINYL SEAWALL
Type: CN

Contractor

M & D CONSTRUCTION OF NORTH FLORIDA INC
Status Location Address State License Number Phone Fax
CANCEL

6B MARKET PLACE COURT

PALM COAST, FL 32137

RR0052050 (Exp: 08/31/2008) (386)586-0050 (386)586-0051

Inspection History

Type Request Date Result Inspector
STORMWATER FINAL INSPECTION 09/27/2007 FINAL APPROVED DRANDALL
Note: THIS IS A REINSPECTION
LANDSCAPE FINAL 04/23/2007 APPROVED - AS NOTED LAPTEKAR
Note: THIS IS A REINSPECTION per Barbara G.......site is okay
LANDSCAPE FINAL 04/13/2007 Disapproved - NO FEE WBUTLER
Note: Sod that was used in the right-of-way was St. Augustine sod which will die as soon as we have a drought. Need to remove and replace with Bahia sod.
STORMWATER FINAL INSPECTION 03/05/2007 Disapproved -FEE REQUIRED DRANDALL
Note: seed & straw all exposed earth on property, traffic area used for construction.....regrade swale to flow properly, and sod all exposed earth
SEA WALL DEADMEN / CAP 11/13/2006 APPROVED CMINI
PRE CLEARING INSPECTION 11/09/2006 APPROVED WBUTLER

Review History

Department Status Date In Date Out
BLD COMPLETE 08/03/2006 08/04/2006
Note: Released By: CCOTE Approved for Release. Review by Fred R.
SW1 COMPLETE 08/02/2006 08/02/2006
Note: Released By: DREYNOLDS
URB HOLD 06/09/2006 06/09/2006
Note: Held By: WBUTLER Bill Butler has file 6-9-06, hh Site reinspected on 6/9/06 and floating turbidity barrier was in place but a tree survey was not included in the application packet nor were the clearing limits for access and backfilling shown on the survey. A permit has not been issued for a principal structure yet, therefore, until a revised clearing plan with tree barricades installed on site at the clearing limits is done, the permit cannot be issued for the seawall.
URB HOLD 05/02/2006 05/03/2006
Note: Held By: WBUTLER Plans were not submitted per Ordinance 2001-16 for lots without a principal structure existing on it. Need to resubmit plans according to this ordinance.
ZON COMPLETE 04/28/2006 05/02/2006
Note: Released By: HHERKERT
URB COMPLETE 08/02/2006
Note: Released By: BGROSSMAN

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
STORMWATER REINSPECTION FEE ¤35.00 04/12/2007
ARC SEAWALL REVIEW ¤20.00 08/29/2006
PERMIT FEE ¤119.10 08/29/2006
Fees Total Due: ¤0.00 Total Paid: ¤174.10