I want to search for...
Permit #2007030136
Permit Details
Status: COED
| Parcel Id: 07-11-31-7057-00560-0150 |
| CONDITIONED SPACE: 1168 sqft |
| GARAGE: 459 sqft |
| OPENED PORCH (WITH ROOF) : 180 sqft |
| OPENED PORCH (WITH ROOF) : 50 sqft |
| Total Square Footage: 1857 sqft |
| Block: 00560 |
| Subdivision: - |
| Job Phone: (386)775-4137 |
| Location Address: 19 UNIONTIN CT |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 05/09/2007 |
| NOC: RECORDED |
| Applicant name: GREGORY JOSEPH SEAL |
| Owner: MASTERPIECE HOMES |
|
Address PO BOX 740618 ORANGE CITY, FL 32774 |
| Lot: 0150 |
| Contracted Stated Job Value: ¤149,937.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
MASTERPIECE HOMES INC
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
PO BOX 740618 ORANGE CITY, FL 32763 |
CRC1327666 (Exp: 08/31/2010) | (386)775-4137 | (386)775-1397 |
Sub Contractors
RUSSELL J CARTER
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 302 DELAND, FL 32721 |
CFC1425938 (Exp: 08/31/2026) | 386-736-4220 | 386-736-4219 |
JEFFREY JAY MITCHELL
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
PO BOX 353178 PALM COAST, FL 32135 |
CCC1327078 (Exp: 08/31/2010) | (386)437-3929 | (386)447-2236 |
EDWARD DOUGLAS TENNANT
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
3370 AGRICULTURAL CENTER DRIVE ST. AUGUSTINE , FL 32092 |
CAC1813372 (Exp: 08/31/2026) | (904)829-8898 | (904)829-6587 |
PETER JOSEPH LYDEN
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
PO BOX 1009 BUNNELL, FL 32110 |
EC0002436 (Exp: 08/31/2014) | (386) 931-2568 | 386-313-3445 |
Inspection History
| Type | Request Date | Result | Inspector |
| FINAL COMPLETE BUILDING INSPECTION | 10/05/2007 | FINAL APPROVED | PGALLMANN |
| Note: THIS IS A REINSPECTION | |||
| FINAL COMPLETE BUILDING INSPECTION | 10/03/2007 | Disapproved -FEE REQUIRED | DROCKWELL |
| Note: 4`` CLEARANCE AROUND A/C RETURN AT CONNECTION/EXTEND WATER HEATER OVERFLOW TO LOWER FLOOR/MASTER BATH TOILET NOT ILLUMINATED/FILL A/C CHASE IN GARAGE WITH APPROPRIATE MATERIAL. | |||
| STORMWATER FINAL INSPECTION | 09/20/2007 | APPROVED - AS NOTED | GLALIMA |
| Note: NEED TO REPAIR ROAD DAMAGE / IT IS ALL CUT OUT . | |||
| UTILITY COMPANY FINAL | 09/18/2007 | APPROVED | PLAWRENCE |
| RESIDENTIAL EARLY POWER | 09/17/2007 | APPROVED - AS NOTED | RMARVEL |
| Note: requested by contractor AT THE FINAL CHECK TO MAKE SURE THATTHE WIEGHT OF THE HANGING FIXTURES IS ON THE CHAIN NOT THE FIXTURE CORD. | |||
| PRE DRIVEWAY | 08/31/2007 | APPROVED | DRANDALL |
| INSULATION INSPECTION | 08/09/2007 | APPROVED | DROCKWELL |
| Note: THIS IS A REINSPECTION | |||
| INSULATION INSPECTION | 08/08/2007 | Disapproved -FEE REQUIRED | PGALLMANN |
| Note: THIS IS A REINSPECTION... R-19 BATT INSULATION REQUIRED IN CEILING/FLOOR SYSTEM OVER GARAGE. SEE BUILDING DRAWINGS, SHEET #2. | |||
| INSULATION INSPECTION | 08/01/2007 | Disapproved -FEE REQUIRED | PGALLMANN |
| Note: 1) ONLY R11 INSULATION INSTALLED IN GARAGE CEILING. 2) ENERGY CALCULATIONS DO NOT ADDRESS GARAGE CEILING. | |||
| LATH /BRICK FLASHING | 07/31/2007 | APPROVED - AS NOTED | DROCKWELL |
| Note: VERTICAL EXPANSION JOINT ON 41FT SIDE | |||
| ALL ROUGH | 07/30/2007 | APPROVED | DROCKWELL |
| ROOF SHEATHING/BRACES/TIES/ DOWN CELL | 07/26/2007 | APPROVED | DROCKWELL |
| ROOF SHEATHING/BRACES/TIES/ DOWN CELL | 07/24/2007 | Disapproved -FEE REQUIRED | DROCKWELL |
| Note: LANS CALL FOR LSTA30 STRAPS 48`` O/C EXTERIOR WALL../ CLIP JOISTS AT BEARING WALL PER PLAN. | |||
| EXTERIOR WALL SHEATHING/SHEAR WALL | 07/17/2007 | APPROVED | DROCKWELL |
| LINTEL | 07/06/2007 | APPROVED | DROCKWELL |
| Note: | |||
| LINTEL | 07/05/2007 | Disapproved -FEE REQUIRED | DROCKWELL |
| Note: TIE-IN INCOMPLETE FRONT WALL AT GARAGE CHANGE IN HEIGHT.SEE S-3 FIGURE H IN PLANS. | |||
| FOUNDATION SURVEY APPROVED BY STORMWATER | 07/03/2007 | APPROVED | WKINELL |
| MONOLITHIC SLAB INSPECTION/SLAB | 06/27/2007 | APPROVED | DROCKWELL |
| FIRST ROUGH PLUMBING INSPECTION | 06/25/2007 | APPROVED | DROCKWELL |
| Note: THIS IS A REINSPECTION | |||
| FIRST ROUGH PLUMBING INSPECTION | 06/22/2007 | Disapproved -FEE REQUIRED | DROCKWELL |
| Note: Need head pressure on sanitary lines |
Review History
| Department | Status | Date In | Date Out |
| BLD | COMPLETE | 08/03/2007 | 08/07/2007 |
| Note: Released By: CCOTE Approved for Release. REVISION: Revised energy calcs. | |||
| SW1 | COMPLETE | 05/04/2007 | 05/04/2007 |
| Note: Released By: LAPTEKAR Received new topo survey with corrected proposed grade elevations and benchmark clearly labeled. | |||
| BLD | COMPLETE | 04/02/2007 | 04/03/2007 |
| Note: Released By: CCOTE Approved for Release per plan cover sheet. Review by Auba. | |||
| BLD | HOLD | 03/23/2007 | 03/26/2007 |
| Note: Held By: JJOSEPH According to 2006 supplement to Florida Building code ; decorative cementitious finish or coating can not be used over exterior masonry walls unless the block can be shown to be non-porous.Please change that terminology in Stuco or Cement portland Plaster. Indicate how the stuco will be applied over exterior masonry wall | |||
| ZON | COMPLETE | 03/22/2007 | 03/23/2007 |
| Note: Released By: ECOYNE | |||
| SW1 | HOLD | 03/22/2007 | 03/23/2007 |
| Note: Held By: LAPTEKAR Received new driveway detail plan. Still need revised grading plan ..left proposed elevations are higher than the proposed FFE. Also need the benchmark clearly labeled which power pole has the benchmark. | |||
| ZON | HOLD | 03/06/2007 | 03/08/2007 |
| Note: Held By: ECOYNE Need landscaping around front right corner. | |||
| SW1 | HOLD | 03/21/2007 | |
| Note: Held By: LAPTEKAR Lot grading plan and FFE do not match.on the left side of house..grading plan elevations are higher than the FFE. Benchmark on survey not clearly lableled. Driveway detail plan needs to incorporate a Masterpiece Logo, not the city sample. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| EARLY POWER INSPECTION | ¤40.00 | 10/05/2007 |
| REINSPECTION FEE | ¤40.00 | 10/05/2007 |
| REINSPECTION FEE | ¤40.00 | 10/05/2007 |
| REINSPECTION FEE | ¤40.00 | 10/05/2007 |
| REINSPECTION FEE | ¤40.00 | 10/05/2007 |
| REINSPECTION FEE | ¤40.00 | 10/05/2007 |
| REINSPECTION FEE | ¤40.00 | 10/05/2007 |
| REVISION | ¤40.00 | 10/05/2007 |
| ADDITIONAL FEE | ¤40.00 | 07/26/2007 |
| ADMIN FEE | ¤40.00 | 05/09/2007 |
| ARC HOUSE REVIEW | ¤125.00 | 05/09/2007 |
| BUILDING CODE ADMIN FUND | ¤9.29 | 05/09/2007 |
| ELECTRIC FEE | ¤240.00 | 05/09/2007 |
| SCHOOL BOARD IMPACT FEE RES | ¤3,600.00 | 05/09/2007 |
| STORM WATER PERMIT FEES | ¤80.00 | 05/09/2007 |
| 10/06 TRANS IMPACT FEE/MULTI | ¤3,631.83 | 05/09/2007 |
| FIRE IMPACT FEE 4-1-06 | ¤179.37 | 05/09/2007 |
| MECHANICAL FEE | ¤240.00 | 05/09/2007 |
| PERMIT FEE | ¤1,170.00 | 05/09/2007 |
| PARKS IMPACT FEE 4/1/06 | ¤1,159.02 | 05/09/2007 |
| PLAN CHECK FEE | ¤120.00 | 05/09/2007 |
| PLUMBING FEE | ¤240.00 | 05/09/2007 |
| RADON FEE | ¤9.29 | 05/09/2007 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤11,203.80 |