I want to search for...

Permit #2007080318

Permit Details

Status: FINAL

Parcel Id: 07-11-31-7016-00090-0140
PATIO/DECK (NO ROOF) : 992 sqft
Total Square Footage: 1356 sqft
Block: 00090
Subdivision: -
Job Phone: (386)439-6316
Location Address: 10 CRABTREE CT
Type: PO - POOL
Issue Date: 08/24/2007
NOC: RECORDED
Applicant name: JAMES EDEN
Owner: MACCIOLI, JOSEPH R & MELVA D

Address

10 CRABTREE CT

PALM COAST, FL 32137

Lot: 0140
Contracted Stated Job Value: ¤15,000.00
Job Description: POOL W/SCREEN ENCLOSURE
Type: CN

Contractor

POOLS N SPAS OF CENTRAL FLORIDA, INC
Status Location Address State License Number Phone Fax
CANCEL

50 AUDUBON LANE

,

CPC035660 (Exp: 08/31/2012) 386-527-1795 386-269-0495

Sub Contractors

DARIN KEITH COURINGTON
Status Location Address State License Number Phone Fax
CANCEL

2032 ANNE CIRCLE

SOUTH DAYTONA, FL 32119

EC13002231 (Exp: 08/31/2012) (386)566-6464 000-000-0000
JAMES C EDEN
Status Location Address State License Number Phone Fax
CANCEL

50 AUDUBON LANE

FLAGLER BEACH, FL 32136

CGC059140 (Exp: 08/31/2014) 386-445-5054 386-439-9780

Inspection History

Type Request Date Result Inspector
POOL - FINAL 04/25/2008 FINAL APPROVED DROCKWELL
Note: Phil from Pools n Spas called to schedule this inspection for 4/25/08
STORMWATER FINAL INSPECTION 04/23/2008 APPROVED DRANDALL
Note: THIS IS A REINSPECTION
UTILITY COMPANY FINAL 04/04/2008 APPROVED TSCHWEERS
Note: Gravity ok.
STORMWATER FINAL INSPECTION 04/04/2008 Disapproved -FEE REQUIRED DRANDALL
Note: schedule per Phil 4/4/08 1. straw and seed exposed earth on adjacent right side 2. remove concrete washout from right front and right rear of property....marked 3. remove dirt pile from right adjacent property and seed and straw same area
ELEC & ALARM 04/03/2008 APPROVED LHITES
Note: THIS IS A REINSPECTION called by contractor
POOL DECK INSPECTION 04/01/2008 APPROVED - AS NOTED JMCGOWEN
Note: this was inspected by a third party,Robert M. Johnson and is on file
ELEC & ALARM 03/19/2008 Disapproved -FEE REQUIRED RMARVEL
Note: Requested by Robert (inspector) ALARMS ON DOORS AND WINDOWS ARE OK. NEED TO BOND SCREEN ENCLOSRE THAT IS WITHIN 5FT OF EDGE OF POOL.
RETAINING WALL FOUNDATION INSPECTION 02/05/2008 APPROVED - AS NOTED JMCGOWEN
Note: see revison for third party inspection
STEEL & GROUND 08/28/2007 APPROVED - AS NOTED ACOOPER
Note: POOL OK. MUST STOP AT CITY AND OBTAIN ADDENDUM FOR FOOTER AND RETAINING WALL. THIS MUST BE SUBMITTED, APPROVED BEFORE CONTINUING WITH RETAINING WALL. A COOPER 9313958.

Review History

Department Status Date In Date Out
BLD COMPLETE 04/01/2008 04/01/2008
Note: Released By: JMCGOWEN review pictures of e-potential bond wire installed 18 to 24 away from lip bonding to pool shell ladder., will be an 80 dollar processing fee .
BLD HOLD 02/19/2008 02/20/2008
Note: Held By: JMCGOWEN missed inspection form must be used when having a third party inspection done
BLD COMPLETE 02/05/2008 02/05/2008
Note: Released By: JMCGOWEN the missed inspection report will be accepted for stem wall foundation and retaining wall, need to provide missed inspection report for deck.
BLD COMPLETE 08/29/2007 09/11/2007
Note: Released By: FREODICA Approved for release. Rev.- added retaining wall for screen enclosure.
BLD COMPLETE 08/23/2007 08/23/2007
Note: Released By: FREODICA Approved for release. Reviewed by Auba.
BLD HOLD 08/21/2007 08/22/2007
Note: Held By: JJOSEPH All work associated with the installation of gas piping and equipment shall be completed under a separate building permit or added to this permit and shall include the submission of a gas riser diagram indicating pipe sizes, material and lengths as well as gas equipment BTU capacities, tank size and location.
SW1 COMPLETE 08/20/2007 08/21/2007
Note: Released By: WKINELL
ZON COMPLETE 08/20/2007 08/20/2007
Note: Released By: ECOYNE
ZON HOLD 08/16/2007 08/17/2007
Note: Held By: BBARTON/training 1. need to indicate roof type on color sheet 2. Need to show equipment pad on surveys

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
STORMWATER REINSPECTION FEE ¤35.00 04/11/2008
ADDITIONAL FEE ¤80.00 04/03/2008
REINSPECTION FEE ¤40.00 03/20/2008
REVISION ¤40.00 03/06/2008
REVISION ¤40.00 03/06/2008
STORM WATER PERMIT FEES ¤80.00 08/24/2007
ARC POOL/SCREEN REVIEW ¤50.00 08/24/2007
ELECTRIC FEE ¤49.20 08/24/2007
PERMIT FEE ¤192.00 08/24/2007
PLAN CHECK FEE ¤40.00 08/24/2007
Fees Total Due: ¤0.00 Total Paid: ¤646.20