Permit #2008110195
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-1090-000C0-0000 |
| Subdivision: 1228 - SOUTHWEST QUADRANT |
| Job Phone: (386)252-5555 |
| Location Address: 160 CYPRESS POINT PKWY |
| Type: GA - GAS |
| Issue Date: 11/25/2008 |
| NOC: Unknown |
| Applicant name: GEOFRRY DEFOREST |
| Owner: HIGHTOWER FINANCIAL SERVICES I NC TRUSTEE OF BCC I |
|
Address 1053 MAITLAND CENTER COMMONS MAITLAND, FL 23751 |
|
Address BLVD SUITE 201 MAITLAND, FL 23751 |
| Contracted Stated Job Value: ¤1,200.00 |
| Job Description: BLDG. D UNITS 101 A & B --- STUBOUT TO EXISTING LP 1000 GALLON TANK FOR "VENUTO'S PIZZA" |
| Type: CN |
Contractor
AMERIGAS
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
411 6TH STREET HOLLY HILL, FL 32117 |
01612 (Exp: 08/31/2010) | (386)252-5555 | (386)255-6657 |
Inspection History
| Type | Request Date | Result | Inspector |
| GAS ROUGH | 02/06/2009 | APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION ok per jerry | |||
| GAS FINAL | 02/06/2009 | FINAL APPROVED | JHINDMAN |
| Note: OK TO FINAL PER JERRY NO LANDSCAPE NEEDE PER LARRY | |||
| GAS ROUGH | 12/17/2008 | Disapproved -FEE REQUIRED | JHINDMAN |
| Note: Inspection Resulted at 12/17/2008 9:13:25 AM 1. GAS PIPE SIZING IS NOT PER PLAN 2.GAS PIPING MUST BE INDEPENDANTLY SUPPORTED AND MUST BE PROPERLY SUPPORTED PER MANUFACTURERS SPECS. |
Review History
| Department | Status | Date In | Date Out |
| BLD | COMPLETE | 01/06/2009 | 01/06/2009 |
| Note: Released By: FREODICA Revision: Revise gas riser diagram. Changed gas pipe size from 1-1/4" to 3/4" at 2 psi delivery pressure. | |||
| BLD | HOLD | 12/18/2008 | 12/18/2008 |
| Note: Held By: FREODICA Revision: 1. Provide revised gas riser diagram drawn on separate sheet and not on electrical plan. | |||
| BLD | COMPLETE | 11/18/2008 | 11/19/2008 |
| Note: Released By: JJOSEPH | |||
| ZON | COMPLETE | 11/18/2008 | 11/18/2008 |
| Note: Released By: BBARTON verified that tank is existing, this permit is for piping only no review needed by zoning |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 01/09/2009 |
| REVISION | ¤40.00 | 01/09/2009 |
| SITE PLAN 20 | ¤20.00 | 11/25/2008 |
| PERMIT FEE | ¤20.00 | 11/25/2008 |
| PLAN REVIEW 25 | ¤25.00 | 11/25/2008 |
| PLUMBING FEE | ¤60.72 | 11/25/2008 |