Permit #2009110081
Permit Details
Status: COED
| Parcel Id: 07-11-31-5112-00000-0120 |
| COMMERCIAL SQUARE FOOTAGE: 61139 sqft |
| Total Square Footage: 61139 sqft |
| Block: 00000 |
| Subdivision: 1164 - PINE LAKES INDUSTRIAL PARK |
| Job Phone: 386-257-3570 |
| Location Address: 2 COMMERCE BLVD |
| Type: CIA - COMMERCIAL INTERIOR EXTERIOR ALTERATION |
| Issue Date: 11/19/2009 |
| NOC: RECORDED |
| Applicant name: CHARLES ANDREW COLEMAN |
| Owner: TWO COMMERCE LLC |
|
Address 11 COMMERCE BLVD PALM COAST, FL 32164 |
| Lot: 0120 |
| Contracted Stated Job Value: ¤1,550,000.00 |
| Job Description: RENOVATE EXISTING OFFICE SPACE & CONVERSION OF WAREHOUSE SPACE TO OFFICE SPACE |
| Type: CN |
Contractor
COLEMAN GOODEMOTE CONSTRUCTION COMPANY INC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
619 N. BEACH ST. DAYTONA BEACH, FL 32114 |
CGC057396 (Exp: 08/31/2026) | 386-257-3570 | 386-253-6692 |
Sub Contractors
PAUL NOEL BIELEFELDT
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
320 Aragon Street Holly Hill, FL 32117 |
EC0001646 (Exp: 08/31/2026) | (386) 677-0447 | 386-673-9868 |
WILFRED FREDERICK EVANS
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
500 CARSWELL AVE HOLLY HILL, FL 32117 |
CAC057460 (Exp: 08/31/2018) | (386) 253-7627 | (386)255-1470 |
ROBERT V VON KAAS
| Status | Location Address | State License Number | Phone |
| CANCEL |
909 Carswell Avenue Holly Hill, FL 32117 |
CFC057448 (Exp: 08/31/2010) | (386) 253-8222 |
Inspection History
| Type | Request Date | Result | Inspector |
| ELECTRICAL FINAL | 05/14/2010 | APPROVED | LHITES |
| Note: THIS IS A REINSPECTION | |||
| UTILITY COMMERCIAL FINAL | 05/14/2010 | FINAL APPROVED | KKING |
| UTILITY COMPANY FINAL | 05/14/2010 | APPROVED | KKING |
| ENGINEERING FINAL | 05/14/2010 | APPROVED | JMODEN |
| FINAL COMPLETE BUILDING INSPECTION | 05/14/2010 | APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION | |||
| FIRE FINAL | 05/13/2010 | APPROVED - AS NOTED | JPATTEE |
| Note: Provide sprinkler head in SW HVAC room. | |||
| ELECTRICAL FINAL | 05/13/2010 | CANCELLED BY APPLICANT | LHITES |
| Note: THIS IS A REINSPECTION contractor did not have final set of plans | |||
| H.V.A.C. FINAL | 05/13/2010 | APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION | |||
| PLUMBING FINAL | 05/12/2010 | APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 5/12/2010 3:34:28 PM ALL PHASES ARE COMPLETE FOR THE PLUMBING. | |||
| LANDSCAPE FINAL | 05/12/2010 | APPROVED | WBUTLER |
| ELECTRICAL FINAL | 05/03/2010 | PARTIALLY APPROVED | LHITES |
| Note: THIS IS A RE INSPECTION phase three is approved | |||
| FINAL COMPLETE BUILDING INSPECTION | 05/03/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 5/3/2010 3:10:36 PM PHASE 3 IS OK. | |||
| ABOVE CEILING | 04/27/2010 | APPROVED | LHITES |
| Note: phase 3 | |||
| ELECTRICAL FINAL | 04/19/2010 | PARTIALLY APPROVED | LHITES |
| Note: THIS IS A REINSPECTION | |||
| FINAL COMPLETE BUILDING INSPECTION | 04/15/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: Inspection Resulted at 4/15/2010 3:23:40 PM PHASE 2 IS OK. | |||
| ABOVE CEILING | 04/13/2010 | APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 4/13/2010 3:27:23 PM ABOVE CEILING MECHANICAL IS COMPLETE. | |||
| H.V.A.C. FINAL | 04/12/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 4/12/2010 3:07:09 PM PHASES 2 AND 3 ARE OK. NEED REVISION FOR 2 TON UNIT ADDED AT UPS ROOM. | |||
| PLUMBING FINAL | 04/12/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: Inspection Resulted at 4/12/2010 3:07:10 PM PHASES 2 AND 3 ARE OK. | |||
| FIRE FINAL | 04/12/2010 | APPROVED - AS NOTED | JPATTEE |
| Note: Phase 2,3 | |||
| ELECTRICAL FINAL | 04/12/2010 | Disapproved -FEE REQUIRED | LHITES |
| Note: Inspection Resulted at 4/12/2010 2:46:20 PM CANNOT FINAL ELECTRIC FOR PHASE 2 AND 3 UNTIL CUBICLES ARE SET | |||
| COMMERCIAL POWER INSPECTION | 04/08/2010 | APPROVED | LHITES |
| Note: THIS IS A REINSPECTION Inspection Resulted at 4/8/2010 3:48:24 PM GENERATOR START UP | |||
| PLUMBING FINAL | 04/08/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: the upstairs bathrooms are ok. | |||
| ABOVE CEILING | 04/08/2010 | APPROVED | LHITES |
| Note: THIS IS A REINSPECTION | |||
| ABOVE CEILING | 04/06/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 4/6/2010 2:31:57 PM ALL ABOVE CEILING MECHANICAL IS OK EXCEPT FOR THE EXHAUST IN THE NEW UPSTAIRS BATHROOMS. | |||
| COMMERCIAL POWER INSPECTION | 04/05/2010 | PARTIALLY APPROVED | LHITES |
| Note: Inspection Resulted at 4/5/2010 2:11:55 PM FEEDERS TO UPS SYSTEM AND ELECTRIC ROOM 135 A | |||
| MONOLITHIC SLAB INSPECTION/SLAB | 03/31/2010 | APPROVED | JHINDMAN |
| COMMERCIAL POWER INSPECTION | 03/22/2010 | APPROVED | LHITES |
| Note: THIS IS A REINSPECTION Inspection Resulted at 3/22/2010 1:49:14 PM THIS WAS AN INSPECTION FOR THE CHANGE OF MAIN SERVICE. CALLED SUSAN WITH FPL 11:30 | |||
| LINTEL | 03/09/2010 | APPROVED - AS NOTED | JHINDMAN |
| Note: Inspection Resulted at 3/9/2010 3:34:32 PM NEED REVISION FOR THE DELETION OF THE WINDOW AT THE SCREEN PORCH. | |||
| TEMPORARY POLE | 03/09/2010 | APPROVED | JHINDMAN |
| Note: Inspection Resulted at 3/9/2010 3:34:33 PM CALLED FPL ON 3-9-10 AT 10:00 P.M. | |||
| H.V.A.C. ROUGH | 02/25/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 2/25/2010 3:40:55 PM PHASE 2, 2ND FLOOR SUPPLY DUCT. | |||
| FRAMING | 02/25/2010 | APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 2/25/2010 3:40:56 PM FRAMING IS COMPLETE. | |||
| FRAMING | 02/24/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 2/24/2010 3:27:26 PM ALL FRAMING EXCEPT FOR HAT CHANNEL IN PHASE 4 IS OK. | |||
| ABOVE CEILING | 02/24/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 2/24/2010 3:27:27 PM ALL MECHANICAL EXCEPT PHASE 2 RESTROOMS AND PHASE 4. | |||
| SECOND ROUGH PLUMBING INSPECTION | 02/24/2010 | APPROVED | JHINDMAN |
| Note: Inspection Resulted at 2/24/2010 3:27:27 PM ALL PHASES | |||
| 2ND ROUGH ELECTRICAL | 02/24/2010 | PARTIALLY APPROVED | LHITES |
| Note: THIS IS A REINSPECTION Inspection Resulted at 2/24/2010 1:43:20 PM HIGHLITED ON PLANS | |||
| LATH /BRICK FLASHING | 02/23/2010 | APPROVED | JHINDMAN |
| EXTERIOR WALL SHEATHING/SHEAR WALL | 02/19/2010 | APPROVED | JHINDMAN |
| FRAMING | 02/18/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 2/18/2010 9:48:24 AM FURRING FOR THE CLOSING IN OF EXTERIOR OPENINGS ON THE WEST SIDE. | |||
| ABOVE CEILING | 02/16/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 2/16/2010 12:43:07 PM ABOVE CEILING FOR HVAC IN PHASE 3 | |||
| PROJECT STATUS INSPECTION | 02/12/2010 | APPROVED | JHINDMAN |
| Note: I visited the jobsite at 2:00 p.m. on 2-12-10. The job is proceeding according to the plans. | |||
| LINTEL | 02/11/2010 | APPROVED | JHINDMAN |
| Note: Inspection Resulted at 2/11/2010 2:57:59 PM ENTRY DOOR ON WEST SIDE OF BUILDING. | |||
| SECOND ROUGH PLUMBING INSPECTION | 02/10/2010 | APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION | |||
| H.V.A.C. ROUGH | 02/10/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 2/10/2010 1:51:39 PM FIRST FLOOR SUPPLY AND RETURN DUCTS. | |||
| PROJECT STATUS INSPECTION | 02/09/2010 | APPROVED | JHINDMAN |
| PROJECT STATUS INSPECTION | 02/08/2010 | APPROVED | JHINDMAN |
| Note: I visited the jobsite at 2:30 p.m. on 2-8-10. The job is progressing according to the plans. | |||
| PROJECT STATUS INSPECTION | 02/04/2010 | APPROVED - AS NOTED | JHINDMAN |
| Note: I visited the jobsite at 2:45 on 2-4-10. The job is proceeding according to the plans. | |||
| PROJECT STATUS INSPECTION | 02/02/2010 | APPROVED - AS NOTED | JHINDMAN |
| Note: I visited the jobsite at 2:45 p.m. on 2-2-10. The job is progressing according to the plans. | |||
| PROJECT STATUS INSPECTION | 02/01/2010 | APPROVED - AS NOTED | JHINDMAN |
| Note: I visited the jobsite on 2-1-10 at 2:30 p.m. The job progressing per plan. | |||
| PROJECT STATUS INSPECTION | 01/28/2010 | APPROVED - AS NOTED | JHINDMAN |
| Note: I visited the jobsite on 1-28-10 at 1:00 p.m. The job is progressing according to plan. | |||
| PROJECT STATUS INSPECTION | 01/27/2010 | APPROVED - AS NOTED | JHINDMAN |
| Note: I visited the job at 2:30 p.m.on 1-27-10. Project appears to be proceeding according to plan. | |||
| FIRST ROUGH PLUMBING INSPECTION | 01/26/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 1/26/2010 3:22:41 PM FIRST ROUGH PLUMBING IN PHASE 2 IS APPROVED. COMPRESSED AIR LINES IN PHASE 1 IS APPROVED. | |||
| 2ND ROUGH ELECTRICAL | 01/26/2010 | PARTIALLY APPROVED | LHITES |
| Note: THIS IS A REINSPECTION Inspection Resulted at 1/26/2010 10:20:25 AM 2ND FLOOR WALLS ONLY HIGHLITED ON PLANS | |||
| PROJECT STATUS INSPECTION | 01/22/2010 | APPROVED - AS NOTED | JHINDMAN |
| Note: I visited the jobsite on 1-22-10 at 3:00 p.m. The job appears to be proceeding according to the plans. | |||
| H.V.A.C. ROUGH | 01/21/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 1/21/2010 2:08:12 PM INSPECTED SUPPLY AND RETURN DUCT ROUGH ON AHU 1AND 4 IN PHASE 2. INSPECTED SUPPLY AND RETURN DUCT ROUGH FOR AHU 3 IN PHASE 3. | |||
| UNDERGROUND ELECTRICAL | 01/19/2010 | APPROVED | LHITES |
| Note: Inspection Resulted at 1/19/2010 10:20:56 AM FLOOR BOXES HIGHLITED ON PLANS | |||
| 2ND ROUGH ELECTRICAL | 01/19/2010 | APPROVED | LHITES |
| Note: THIS IS A REINSPECTION Inspection Resulted at 1/19/2010 10:20:57 AM LOBBY WALLS HIGHLITED ON PLANS | |||
| PROJECT STATUS INSPECTION | 01/19/2010 | APPROVED - AS NOTED | JHINDMAN |
| Note: visited jobsite 11:00 a.m. on 1-19-10. Job is progressing according to plans. | |||
| FIRST ROUGH PLUMBING INSPECTION | 01/15/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 1/15/2010 2:08:13 PM 2ND FLOOR PHASE 2 BATHROOMS ARE OK. | |||
| ABOVE CEILING | 01/15/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: Inspection Resulted at 1/15/2010 2:08:14 PM PHASE 2 AHU4 SUPPLY AND RETURN DROPS AND LIGHTS IN MAIL RELEASE AND USPS ROOMS ARE OK. PROVIDE AS BUILTS FOR THE MAIL RELEASE ROOM LIGHTS THAT ARE NOT BEING INSTALLED. | |||
| PROJECT STATUS INSPECTION | 01/14/2010 | APPROVED | JHINDMAN |
| Note: I visited the jobsite at 2:00 p.m. on 1-14-10. job is progressing accordingly. | |||
| PROJECT STATUS INSPECTION | 01/13/2010 | APPROVED | JHINDMAN |
| Note: I visited the jobsite at 12:30 p.m. on 1-13-10. project appears to be progressing to plan. | |||
| ABOVE CEILING | 01/12/2010 | CANCELLED BY APPLICANT | LHITES |
| Note: Inspection Resulted at 1/12/2010 10:26:40 AM SUPER CALLED IN WRONG INSPECTION | |||
| H.V.A.C. ROUGH | 01/12/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 1/12/2010 3:27:57 PM FRESH AIR INTAKE DUCTS IN PHASE 3 ARE OK TO WRAP WITH INSULATION. | |||
| FIREWALL FINAL INSPECTION | 01/12/2010 | APPROVED | JLEWIS |
| 2ND ROUGH ELECTRICAL | 01/07/2010 | PARTIALLY APPROVED | LHITES |
| Note: THIS IS A REINSPECTION Inspection Resulted at 1/7/2010 11:22:36 AM WALLS ONLY. HIGHLITED ON PLANS. PHASE 2 AND 3 | |||
| FRAMING | 01/07/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: Inspection Resulted at 1/7/2010 2:55:09 PM EXTERIOR WALLS PHASE ARE OK, STRUCTURAL GRID IN PHASE 4 IS OK. | |||
| SECOND ROUGH PLUMBING INSPECTION | 01/07/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: Inspection Resulted at 1/7/2010 2:52:34 PM EAST BATHROOMS PHASE 2 | |||
| FIRST ROUGH PLUMBING INSPECTION | 01/06/2010 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 1/6/2010 3:02:51 PM PARTIAL AIR LINE IN PHASE ONE. | |||
| PROJECT STATUS INSPECTION | 01/04/2010 | APPROVED | JHINDMAN |
| Note: visited jobsite at 1:00 p.m. construction appears to be proceeding according to the plans. | |||
| PROJECT STATUS INSPECTION | 12/30/2009 | APPROVED | JHINDMAN |
| Note: I visited the jobsite at 11:00 a.m. The job appears to be progressing according to the plans. | |||
| FRAMING | 12/17/2009 | PARTIALLY APPROVED | CMINI |
| Note: requested by contractor Inspection Resulted at 12/17/2009 3:28:16 PM PARTIALL FRAMING ON 1ST AND 2ND FL. | |||
| FIRE FINAL | 12/17/2009 | APPROVED - AS NOTED | JPATTEE |
| Note: Phase 1 | |||
| COMMERCIAL BUILDING FINAL | 12/17/2009 | PARTIALLY APPROVED | JHINDMAN |
| Note: Inspection Resulted at 12/17/2009 3:33:06 PM PHASE ONE IS SAFE AND COMPLETE FOR TEMPORARY OCCUPANCY. | |||
| FRAMING | 12/16/2009 | PARTIALLY APPROVED | RMARVEL |
| Note: west side middle of building. 4 office walls. high lighted on plans. | |||
| COMMERCIAL POWER INSPECTION | 12/16/2009 | PARTIALLY APPROVED | RMARVEL |
| Note: Inspection Resulted at 12/16/2009 1:39:01 PM 1ST AND THIRD SORTING MACHINE AT DISCONNECTS ARE OK FOR POWER. | |||
| 2ND ROUGH ELECTRICAL | 12/15/2009 | PARTIALLY APPROVED | RMARVEL |
| Note: ok to power sorting machine #2 through temporary hookup. 4 offices west middle of building. highlighted on plans.power for ac system in sorting room is ok. | |||
| 2ND ROUGH ELECTRICAL | 12/14/2009 | PARTIALLY APPROVED | RMARVEL |
| Note: Inspection Resulted at 12/14/2009 2:33:34 PM LIGHTING IN WHAREHOUSE ARE ONLY. | |||
| H.V.A.C. FINAL | 12/11/2009 | PARTIALLY APPROVED | JHINDMAN |
| Note: a/c units 18, 19, and 20. | |||
| LINTEL | 12/11/2009 | APPROVED | JHINDMAN |
| Note: exterior door at letter sorting area. | |||
| H.V.A.C. ROUGH | 12/10/2009 | PARTIALLY APPROVED | JHINDMAN |
| Note: Inspection Resulted at 12/10/2009 10:11:14 AM 3 FRESH AIR INTAKES AND 3 RETURNS IN THE LOADING DOCK AREA ARE OK TO INSULATE. | |||
| FRAMING | 12/08/2009 | APPROVED | RMARVEL |
| Note: THIS IS A REINSPECTION Michael called to schedule this inspection Inspection Resulted at 12/8/2009 3:39:49 PM HIGHLIGHTED ON PLANS. | |||
| 2ND ROUGH ELECTRICAL | 12/08/2009 | PARTIALLY APPROVED | RMARVEL |
| Note: Inspection Resulted at 12/8/2009 3:39:04 PM HIGHLIGHTED ON PLANS. | |||
| FRAMING | 12/07/2009 | PARTIALLY APPROVED | DROCKWELL |
| Note: THIS IS A REINSPECTION Inspection Resulted at 12/7/2009 12:59:22 PM FIREWALL FRAMING AT STAIRS...OK | |||
| FIRST ROUGH PLUMBING INSPECTION | 12/07/2009 | PARTIALLY APPROVED | JHINDMAN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 12/7/2009 3:35:50 PM FIRST ROUGH OK IN ROOMS 123, 124, 125, 149, 150,AND 151. | |||
| FIRST ROUGH PLUMBING INSPECTION | 12/04/2009 | CANCELLED BY APPLICANT | JHINDMAN |
| Note: THIS IS A REINSPECTION | |||
| FIREWALL INSPECTION | 12/03/2009 | APPROVED | JPATTEE |
| FIRST ROUGH PLUMBING INSPECTION | 12/01/2009 | Disapproved -FEE REQUIRED | JHINDMAN |
| Note: Inspection Resulted at 12/1/2009 3:39:21 PM PLUMBING IS NOT PER PLAN | |||
| FIREWALL INSPECTION | 11/25/2009 | APPROVED | JLEWIS |
| FRAMING | 11/24/2009 | Disapproved -FEE REQUIRED | LHITES |
| Note: Inspection Resulted at 11/24/2009 9:43:29 AM NEED REVISION FOR USE OF 20 GA. STEEL INSTEAD OF PLAN APPROVED 16 GA. |
Review History
| Department | Status | Date In | Date Out |
| ELEC | COMPLETE | 05/14/2010 | 05/14/2010 |
| Note: Released By: LHITES Electrical as built drawings E-1 thru E-32 | |||
| MECH | COMPLETE | 05/14/2010 | 05/14/2010 |
| Note: Released By: JMCGOWEN HVAC as built drawings M-1 thru M-15 | |||
| PLUM | COMPLETE | 05/14/2010 | 05/14/2010 |
| Note: Released By: JMCGOWEN Plumbing as built drawings P-1 thru P-12 | |||
| UD1 | COMPLETE | 04/21/2010 | 04/21/2010 |
| Note: Released By: CJOHNSON addition of connection sewer line from ne sanitary service 2} sanitary sewer service addition plans from zev cohen signed and sealed and dated Apr 16,2010 2) e-mail from zev cohen & bean section 0 p.e.& f.d.e.p. re: permit exemption | |||
| MECH | COMPLETE | 04/15/2010 | 04/15/2010 |
| Note: Released By: JMCGOWEN add 1 (2) ton split hvac system to electrical change on 1st floor revised mechanical sheet m-1 from m.t. fara j1 dated 3/24/2010 | |||
| ELEC | COMPLETE | 04/06/2010 | 04/07/2010 |
| Note: Released By: LHITES Response to electrical review comments from LHites dated 3/31/2010 Revised electrical sheets E-7,9,12,27,29,30 From M.T.Faraji S&S and dated 4/4/2010 Releasing this revision. Electrician will be marking up an as built for final revised drawings from M.T.Faraji. | |||
| MECH | COMPLETE | 04/06/2010 | 04/07/2010 |
| Note: Released By: JMCGOWEN add ehaust fans and supply air to 2nd floor bathrooms 216 and 217 Revised drawings m-6 from MTFarraji S&S 4/4/2010 | |||
| ELEC | HOLD | 03/25/2010 | 03/29/2010 |
| Note: Held By: LHITES Response to electric plan review comments 1. Please clarify circuit PB- 29:31 shown in schedule as existinf AHU, but as 4 receptacles (PB-29) and refrigerator (PB-31) in staff lounge on E-12. 2. Please clarify load in MDA for T6 transformer, Panel PA3, Panel LC 3. Please clarify load in panel LB for transformer feeding panel PB. Update panel calculations and panel E load. 4.Please clarify load in panel LA for transformer feeding panel PA. Update panel calculations and panel E load. 5. Please clarify load in panel LF1 from PK transformer. Update panel calculations and panel E load. 6. Please clarify load in panel LF1 from PA2 transformer. Update panel calculations and panel E load. 7. Need all HVAC load per panel and panel schedule. 8. Need new locations for all panels and transformers, MDA,UPS, E layout, and electric room 135A. | |||
| BLD | COMPLETE | 03/24/2010 | 03/24/2010 |
| Note: Released By: FREODICA Correction to Revision: Submitted Florida Produc Approval for garage door. | |||
| ENGIN1 | COMPLETE | 03/24/2010 | 03/31/2010 |
| Note: Released By: AWEBB | |||
| BLD | HOLD | 03/23/2010 | 03/23/2010 |
| Note: Held By: FREODICA revision - addition of a recessed truck well on the south side of the building and new garage door opening. Submitted plans S-1 to S-4, C-1, A-3, A-6, A-8, A-12. Held By: FREODICA Review comment: 1. Provide Florida Product Approval for garage door. | |||
| PLUM | COMPLETE | 03/19/2010 | 03/19/2010 |
| Note: Released By: FREODICA sump pump in new truck well south side | |||
| ELEC | HOLD | 03/19/2010 | 03/19/2010 |
| Note: Held By: SKNOPF CITY OF PALM COAST BUILDING DIVISION Comments on Revision to #2009110081 (Palm Coast Data Retrofit @ 2 Commerce Blvd.) 3/19/2010 The following items must be resolved in order to complete the Building Permit plan review. Electrical Comments: 1. All previous comments dated 3-12 unanswered. 2. Sheet A-8 shows a new sump pump being added for new truck well & door South side. Provide revised electrical plans showing circuit, circuit breaker size, and revised panel and demand load calculation. …………………………………………… Susan J. Knopf Plans Examiner City of Palm Coast - Building Division 160 Cypress Point Pkwy Ste B106 Palm Coast, Florida 32164-3216 [tel]: (386) 986-2463 [fax]: (386) 986-3781 [email]: sknopf@ci.palm-coast.fl.us | |||
| BLD | COMPLETE | 03/19/2010 | 03/19/2010 |
| Note: Released By: FREODICA revision- delete borrow lites at exterior door from room 134"client services" Note: Previously approved on 3-9-10. No charge. | |||
| ZON | COMPLETE | 03/19/2010 | 03/24/2010 |
| Note: Released By: ECOYNE revision - addition of a recessed truck well on the south side of the building | |||
| ELEC | HOLD | 03/11/2010 | 03/12/2010 |
| Note: Held By: SKNOPF Revision Add ups system per revised Elec. drawings E-7,8,9,10,11,12,27,28,29,30 and 8 1/2 x 11 " Service load calc" sheet S+S CITY OF PALM COAST BUILDING DIVISION Comments on Revision to #2009110081 (Palm Coast Data Renovation @ 2 Commerce Blvd.) 3/12/2010 The following items must be resolved in order to complete the Building Permit plan review. Electrical Comments: 1. Clarify circuit PA-14 shown for refrigerator room 123 on E7, plus floor receptacles room 119 on E8. 2. Clarify circuit PA-32 shown on E8 for both CU-21 and 6 cubicle receptacles in room 134. 3. Clarify circuit PK30 shown E8 for 5 receptacles room 134 and 2 GFI receptacles on E7 room 124/125. 4. Clarify circuit PA32-34 shown for receptacles room 132/133 on E9, and CU21 on E8. 5. Clarify new panel PA33 shown room 135A, but not shown on Riser or fed from any existing panel schedule. 6. Clarify circuit LF1-14:16:18 shown for both AHU16 & CU16 on Sheet E9. 7. Clarify circuit PA32-17 shown for 6 cubicle receptacles room 152 on E9, and AHU21 on E8. 8. Clarify circuit PA32-19 shown for 4 cubicle receptacles room 152 on E9, and AHU21 on E8. 9. Clarify circuit PA32-32 shown for 5 receptacles rooms 144/145/146/153 on E9, and CU21 on E8. 10. Coordinate labeling for all Presort Machines between panel circuits on E28, and location on E10. 11. Clarify PB1-1 shown for receptacles Lee/Gary/Bryan's offices on E11, and Comp/Network Equip Rm on E12. 12. Clarify copier circuit PA33-2 shown on plan, but not in panel schedule. 13. Clarify circuit PB-37:39 shown in schedule as existing CU, but shown for 3 receptacles in Mike's office on E12 14. Clarify circuit PB-29:31 shown in schedule as ex. AHU, but as 4 receptacles (PB-29) & refrig (PB-31) in Staff Lounge on E12. 15. Coordinate Panel PA3 MCB (riser) or MLO (panel schedule). OCP is required on feeder from 150KVA TB transformer to Panel PA3. 16. Clarify load in MDA for T6 transformer, Panel PA3, Panel LC. 17. Clarify load in Panel LB for transformer feeding Panel PB. Update panel calculations and Panel E load. 18. Clarify load in Panel LA for transformer feeding Panel PA. Update panel calculations and Panel E load. 19. Clarify load in Panel LF1 from PK transformer. Update panel calculations and Panel E load. 20. Clarify load in Panel LF1 from PA2 transformer. Update panel calculations and Panel E load. 21. Clarify load in Panel LF2 for transformer circuit 32:34:36. Riser shows no transformer from this panel. 22. Clarify load in UPS MDP for Panel PA32. 23. Coordinate panel loads with actual loads shown for following circuits and update calculations accordingly: a. PB1-2 (printer), 5, 24, 26, 28, 30, 32, 36 b. PA32-36 (4 rcpts) c. PB-2 (7 rcpts), 23 (4 rcpts), 25 (4 rcpts), 33 (4 rcpts) d. PK-16 (microwave nameplate), 20 (microwave nameplate), 22 (5 rcpts), 24 (7 rcpts), 26 (6 rcpts), 30 (7 rcpts @ 2 locations), 32 (5 rcpts) e. PA-2 (5 rcpts), 4 (5 rcpts), 6 (5 rcpts), 14 (fridge plus 2 rcpts), 16 (5 rcpts), 3 (7 rcpts), 5 (4 rcpts), 11 (6 rcpts), 13 (5 rcpts), 17 (5 rcpts), 19 (6 rcpts), 35 (3 rcpts) f. PC1-11 (6 rcpts), 4 (5 rcpts), 6 (5 rcpts), 12 (5 rcpts), 14 (5 rcpts), 16 (5 rcpts), 24 (vending), 28 (refrigerator) g. PA31-3 (6 rcpts), 4 (6 rcpts), 6 (6 rcpts), 8 (6 rcpts), 9 (5 rcpts) 24. Sheet E27 Riser - Provide OCP for feeder from 150KVA transformer to UPS MDP per NEC Table 450.3(B). 25. Sheet E27 Riser - Clarify panel identification on riser for 'CP' ('CD') 26. Sheet E27 Riser - Identify grounding electrode conductors & grounding electrodes for all transformers per NEC 250. 27. Provide circuits for existing and new receptacles in following rooms: 110, 111, 104, 103, 167, 109, 130, 113, 118, 119, 120, 134, next to ATS, south exterior wall on E10, @ stair 13 on E11, Expansion room on E11, hallway @ Files E12, Verification room E12, Staff Lounge E12, Restroom mop sink E12, conference room E11, Visitors room E11, Membership room E12, 1-Hr rated wall E12. 28. Update all HVAC loads per nameplate & update panel loads & load calculations. Jobsite visit showed loads vary from panel schedules. 29. Provide circuits on plans for all HVAC units. 30. Provide revised load calculations including convenience receptacles, air compressor, misc. equipment load, and HVAC load per nameplate ratings. …………………………………………… Susan J. Knopf Plans Examiner City of Palm Coast - Building Division 160 Cypress Point Pkwy Ste B106 Palm Coast, Florida 32164-3216 [tel]: (386) 986-2463 [fax]: (386) 986-3781 [email]: sknopf@ci.palm-coast.fl.us | |||
| BLD | COMPLETE | 03/10/2010 | 03/10/2010 |
| Note: Released By: FREODICA Remove side lights from exterior door | |||
| ZON | COMPLETE | 03/09/2010 | 03/09/2010 |
| Note: Released By: BBARTON Remove side lights from exterior door Elevation page not needed, change is minimal. | |||
| PLLA | COMPLETE | 03/01/2010 | 03/01/2010 |
| Note: Released By: CBENNETT CB 3/01/2010 Revision has addressed Mr. Butler's comments. | |||
| BLD | COMPLETE | 02/26/2010 | 03/01/2010 |
| Note: Released By: JJOSEPH Revision Add permanent emergency generator per drawings C-1 by BPF design Inc. Dated 1-6-10 and A-3j dated 1-6-10 | |||
| ELEC | COMPLETE | 02/26/2010 | 03/01/2010 |
| Note: Released By: SKNOPF Revision Response to comments from S. Knopf dated 2/23/2010 Revised Drawings E-30 S & S and dated 2/23/2010 and "service load calculation" Sheet S & S and dated 2/23/2010 Located presort machines, added receptacles, updated panel schedules, updated service load calculation. Missing panel schedule "PA2". Final set of drawings will have all circuits correctly identified with correct loads, and final revised load calculations per Electrical Supervisor and Mohsen Faraji. | |||
| PLUM | COMPLETE | 02/23/2010 | 02/25/2010 |
| Note: Released By: FREODICA Revision 4 dated 2/20/10: Delete insta- hot water heaters and add two (2) - 30 gallon wh and utilize one existing wh to provide hot water to all lavs & sinks. Revised P-1,2,4,5,6,8,&12. | |||
| ELEC | HOLD | 02/23/2010 | 02/23/2010 |
| Note: Held By: SKNOPF Revision Response to comments from S. Knopf Revised Drawings E-10, 27, 28, 29 AND 30 S&S AND DATED 2/17/10 CITY OF PALM COAST BUILDING DIVISION Comments on Permit #2009110081 (Renovate Palm Coast Data @ 2 Commerce Blvd.) 2/23/2010 The following items must be resolved in order to complete the Building Permit plan review. Electrical Comments: 1. Revise MDA total connected KVA. Revise total demand KVA/amps to coordinate with revised service load calculation. 2. Previous Comment #15 from 2/16/2010: a. Revise service load calculation to reflect 100% lighting load if using NEC Table 220.42, not hotel/motel demand factors. b. Revise power demand factors to reflect NEC Table 220.44. c. Motor loads such as compressors, MSIL sorters, and exhaust fans cannot be reduced with demand factors for NEC 220.14(I). Please see NEC 220.50. d. Equipment and specific appliance loads cannot be reduced with demand factors for NEC 220.14(I). Please see NEC 220.14(A). e. Load shown for sorter machines does not reflect their continuous load. …………………………………………… Susan J. Knopf Plans Examiner City of Palm Coast - Building Division 2 Commerce Boulevard Palm Coast, Florida 32164-3216 [tel]: (386) 986-2463 [fax]: (386) 986-3781 [email]: sknopf@ci.palm-coast.fl.us | |||
| ELEC | COMPLETE | 02/16/2010 | 02/16/2010 |
| Note: Released By: LHITES Request to install temporary service to allow Palm Coast Data to continue using phase I, while the main distribution panel is replaced | |||
| BLD | COMPLETE | 02/15/2010 | 02/15/2010 |
| Note: Released By: JMCGOWEN Revision install stucco panels on for fixt louwers and store front window & west wall wind & light scoops structural design 1/5-s1 & calls form hb & assoc 3pg ated 1/21/2010 new sheet a52 from bpf dated 2/12/2010 1pg. adendum ltr form bpf design dateds 2/11/2010 1pg | |||
| ELEC | HOLD | 02/12/2010 | 02/16/2010 |
| Note: Held By: SKNOPF Response to commehnts from Susan 2 set of load calculations & panel schedules CITY OF PALM COAST BUILDING DIVISION Comments on Revision to Permit #2009110081 (Palm Coast Data Interior Renovation @ 2 Commerce Blvd.) 2/16/2010 The following items must be resolved in order to complete the Building Permit plan review. Electrical Comments - several of the following comments were noted on 2-10-2010: 1. Presort machines: a. Provide location of presort machines and circuits on power plans. b. Revise quantity of conductors to presort machines Panel PS sheet E28. c. Coordinate quantity of presort machines sheet E28 panel schedule with sheet E27 Riser. 2. Panel PF1/PF2 - Revise total demand KVA/amperage and update load in MDA. 3. Panel PK1 - Revise load calculation per NEC 220.14(A). 4. Panel PA3 - Update circuit loads for 16:18:20 and panel load calculations. 5. Panel LD - Coordinate demand load calculation sheet E29 with 8-1/2' x 11" panel schedule. 6. Panel PK - Revise loads for circuit 1:3:5 subpanel PK1. 7. Panel LA - Revise phase load totals and demand KVA/amps. 8. Panel LB - Revise phase load totals and demand KVA/amps. 9. Panel LC - Revise phase load totals and demand KVA/amps. 10. Panel PF2 - Revise phase load totals and demand KVA/amps. 11. Panel PB1 - Revise demand KVA. 12. Panel E: a. Include lighting loads for subpanel LE, unless high-bay lighting fixtures, conduit, and wiring are removed. b. Revise loads carried over from Panels LF1, LA, LB, and LC. 13. Panel MDA - Revise all circuit loads this distribution panelboard. 14. Panel total demand KVA/amps should reflect continuous lighting loads in panel load calculations. 15. Service Load Calculation: a. Revise service load calculation to reflect 100% lighting load if using NEC Table 220.42, not hotel/motel demand factors. b. Revise power demand factors to reflect NEC Table 220.44. c. Motors loads such as compressors, MSIL sorters, and exhaust fans cannot be reduced with demand factors for NEC 220.14(I). Please see NEC 220.50. d. Equipment and specific appliance loads cannot be reduced with demand factors for NEC 220.14(I). Please see NEC 220.14(A). e. Load shown for sorter machines does not reflect their continuous load. …………………………………………… Susan J. Knopf Plans Examiner City of Palm Coast - Building Division 2 Commerce Boulevard Palm Coast, Florida 32164-3216 [tel]: (386) 986-2463 [fax]: (386) 986-3781 [email]: sknopf@ci.palm-coast.fl.us | |||
| ELEC | HOLD | 02/10/2010 | 02/10/2010 |
| Note: Held By: LHITES Temporary main power 1.) Need circuits in panels LD and PF1 2.) Need to know how electrician is going to tap in vault. 3.) Talked with electrical supervisor to clarify what is needed on revision. Said he would draw again with added information. Larry Hites, senior building inspector,plans examiner. | |||
| ELEC | HOLD | 02/09/2010 | 02/10/2010 |
| Note: Held By: SKNOPF Response letter to Revision Comments. Ltr 9 pages dated 2/4/10 from Mohsen T. Faraji, P.A. Drwgs E-10,11,12,27,28,29,30 S&S and dated 2/4/10 from Mohsen T. Faraji, P.A. CITY OF PALM COAST BUILDING DIVISION Comments on Revision to #2009110081 (Palm Coast Data Interior Alteration @ 2 Commerce Blvd.) 2/10/2010 The following items must be resolved in order to complete the Building Permit plan review. Electrical Comments: 1. Load calculations to be signed and sealed. 2. E27: a. Provide revised 3PH feeder from Panel E to Panel LF2 b. Provide feeder sizes from Panel E to LF1 and LF1 to PA2 transformer c. Riser shows PB as 100A MCB panel. Schedule shows 200A MLO. 3. Panel PS: a. Revise KVA loads on 8-1/2"x 11" load calc sheet to coordinate with amp loads E28 b. Coordinate E-28 schedule, riser and load calc sheet for quantity of 50A presort machines. c. Provide locations of all presort machines on plans. 4. Panel PB: a. Revise KVA loads on 8-1/2" x 11" load calc sheet to coordinate with amp loads E29 5. Panel PK1: Coordinate circuit loads on 8-1/2" x 11" sheet to match panel loads E29 6. Panel PA3: Coordinate load calc totals on 8-1/2" x 11" sheet to match panel load calcs E30 7. Panel LC: Missing circuit breaker and loads for Panel PD 8. Panel LD: Revise the following loads to coordinate 8-1/2" x 11" sheet with E29 a. Compressor charger b. HVAC loads c. Forklift loads 9. Panel PA32: Revise phase amp load totals 10. Panel E: a. Revise subpanel LC loads b. Revise elevator load per NEC 620 and Table 430.22E 11. Panel MDA: Revise the following loads in panel: a. Subpanel E circuit 14:16:18 b. Subpanel LD circuit 1:3:5 c. T7 transformer to Panel PS circuit 8:10:12 12. It appears that the demand loads for Panels E and MDA may exceed their capacity. Please revise the load calculation for the following panels to reflect actual demand load: a. PS, PB, PK, PK1, LA, LB, PC1/PC2, LC, LD, PA32, E b. Provide Service Demand Load Calculations …………………………………………… Susan J. Knopf Plans Examiner City of Palm Coast - Building Division 2 Commerce Boulevard Palm Coast, Florida 32164-3216 [tel]: (386) 986-2463 [fax]: (386) 986-3781 [email]: sknopf@ci.palm-coast.fl.us | |||
| MECH | COMPLETE | 01/22/2010 | 01/22/2010 |
| Note: Released By: FREODICA REVISION HVAC SYSTEM APPROVED equal letter from M.J Faraji, PE dated 1/19/2010 | |||
| PLUM | COMPLETE | 01/22/2010 | 01/22/2010 |
| Note: Released By: FREODICA Revised plumbing sheets P-2 & P-7 5&3 12/22/09 depicting piping revisions to bathrooms 10.5 & 10.6 Note: Revision 3, sheets P1, P2, P3, P4, P7, P9 & P11. | |||
| BLD | COMPLETE | 01/21/2010 | 01/22/2010 |
| Note: Released By: JJOSEPH Revision addendum/clarification doc #8 generator pad design dwg c-1 dated 1-6-10 by b.p.f dwg a-3 dated 1-6-10 by b.p.f. sketch sk-03 dated 12-30-09 by devlen eng. inc | |||
| PLLA | HOLD | 01/20/2010 | 01/21/2010 |
| Note: Held By: WBUTLER revised generator location Shrubs shown around the generator need to be on the north and east sides of the generator, not the south side. Also need to state that the shrubs to be 7-gallon, 30" tall and spaced 4' o.c. and planted in a mulched bed. CB 3/1/2010 Rivision has addressed Mr. Bulters comments. | |||
| ELEC | HOLD | 12/29/2009 | 12/30/2009 |
| Note: Held By: SKNOPF Revised electrical sheets E-10,E-27,E-28,E-29,& E-30 S&S 12/22/2009 depictling changes to mail sort area CITY OF PALM COAST BUILDING DIVISION Comments on Revision to Permit #2009110081 (Palm Coast Data @ 2 Commerce Blvd.) 12/30/2009 The following items must be resolved in order to complete the Building Permit plan review. Electrical Comments: 1. Provide a panel demand demand load calculation for the following new panels: a. Panel PS b. Panel PB c. Panel PK d. Panel PK1 e. Panel PA3 f. Panel LD g. Distribution Panelboard MDPN 2. MDPE Schedule on Sheet E28 does not include the circuit breaker or loads for Panel E and Transformer T4 (Panel PC). Revise panel schedule, update loads, and provide demand load calculation. 3. Panel E Schedule on Sheet E30 does not include the circuit breaker or loads for Panel PA2 and Panel LB. Revise panel schedule, update loads, and provide demand load calculation. 4. Riser on Sheet E27 shows Panel LB feeding Panel PB1. Provide panel schedule and demand load calculation for PB1. 5. New MDPN per Riser (E27) is listed as existing panel in MDPN schedule. 6. Coordinate whether the following panels are new or existing between Riser (E27) and panel schedules: a. PA31 b. PA32 c. PD d. LD e. PK1 7. Pre-sort machines listed in Panel PS are running on a 24 hour-a-day basis. Revise demand load calculation to include equipment at 125%. 8. Panels LG1 and LG2 are shown located in the Southeast corner of the building on E10, but Riser (E27) has note that they are to be eliminated and no panel schedules were provided for these panels. Please coordinate drawings. 9. Clarify nomenclature panel "MDA" (E27) with "MDPN" (E30). 10. Identify panel MDPE on Riser (E27). 11. Provide feeder conductor and conduit sizes for the following on the Riser (E27): a. Panel LF1 to Transformer TA b. Transformer TA to Panel PK c. Panel PK to Panel PK1 d. Panel PA3 to Panel PA31 e. Panel PA3 to Panel PA32 12. Note 2 Sheet E10 stating secondary is 6 sets of 750MCM does not match Riser (E27) showing 4 sets of #500. Clarify all service feeders and coordinate. …………………………………………… Susan J. Knopf Plans Examiner City of Palm Coast - Building Division 2 Commerce Boulevard Palm Coast, Florida 32164-3216 [tel]: (386) 986-2463 [fax]: (386) 986-3781 [email]: sknopf@ci.palm-coast.fl.us | |||
| ELEC | HOLD | 12/21/2009 | 12/21/2009 |
| Note: Held By: SKNOPF CITY OF PALM COAST BUILDING DIVISION Comments on Revision to #2009110081 (Palm Coast Data Interior Renovation @ 2 Commerce Blvd.) 12/21/2009 The following items must be resolved in order to complete the Building Permit plan review. Electrical Comments: 1. Sheet E7 shows a new duplex receptacle on circuit PF1-3, but panel schedule shows a 1P 30A circuit breaker as the overcurrent protection for this circuit. 2. Sheet E10 shows new circuits LD-33,35,37 for a new compressor, but panel schedule on E29 shows the circuit breaker on circuits LD-31,33,35. Coordinate. 3. Revised panel actual loads are still incorrect for all panels shown on Sheet E29. Please provide panel load calculations, and revised service calculation with revised riser diagram. …………………………………………… Susan J. Knopf Plans Examiner City of Palm Coast - Building Division 2 Commerce Boulevard Palm Coast, Florida 32164-3216 [tel]: (386) 986-2463 [fax]: (386) 986-3781 [email]: sknopf@ci.palm-coast.fl.us | |||
| FD1 | COMPLETE | 12/21/2009 | 12/22/2009 |
| Note: Released By: JPATTEE Revision Signed and sealed life safety plans A-1 & A-2 | |||
| BLD | HOLD | 12/21/2009 | 12/21/2009 |
| Note: Held By: JMCGOWEN Revision Signed and Sealed clarification #4 Re: Stair #4 Fire provide third party testing report for fire rating evaluation of said doors. | |||
| PLUM | HOLD | 12/21/2009 | 12/21/2009 |
| Note: Held By: FREODICA Revision Revised plumbing drawings p 1,2,3,4,9 & 11 Revision comment: 1. Submitted plumbing plans (drawing sheets P1 & P2) for sanitary lines do not match with the latest approved revision for sanitary riser diagrams. Coordinate & revise. | |||
| MECH | COMPLETE | 12/18/2009 | 12/21/2009 |
| Note: Released By: JMCGOWEN revision - hard copies of previously approved duct system | |||
| FI1 | COMPLETE | 12/16/2009 | 12/22/2009 |
| Note: Released By: JPATTEE Revision 2 sets A-1 and A-2 life safety plans. "Additional copies for JPattee per his request" | |||
| PLUM | COMPLETE | 12/14/2009 | 12/14/2009 |
| Note: Released By: JMCGOWEN Revised plumbing dwg3 p1 & p7 previlously reviewed by e-mail | |||
| ELEC | COMPLETE | 12/14/2009 | 12/14/2009 |
| Note: Released By: JMCGOWEN Revised electrical plans phase (1) Revised plumbing lines showing air lines for phase (1) provide panel schedule and service riser detail before final inspection | |||
| BLD | COMPLETE | 12/11/2009 | 12/11/2009 |
| Note: Released By: JMCGOWEN Revision for building phase plans | |||
| FI1 | HOLD | 12/11/2009 | 12/14/2009 |
| Note: Held By: JPATTEE Revision stairwell #4 existing doors requesting by Jeff Provide a life safety plan for each phase for review/ approval | |||
| BLD | COMPLETE | 12/11/2009 | 12/11/2009 |
| Note: Released By: JMCGOWEN Revision by devlen eng. cut out in cmv wall for new door previously reviewd by email | |||
| BLD | COMPLETE | 12/10/2009 | 12/10/2009 |
| Note: Released By: JMCGOWEN door opening detail | |||
| MECH | COMPLETE | 12/10/2009 | 12/10/2009 |
| Note: Released By: JMCGOWEN duct hanger detail revision | |||
| BLD | COMPLETE | 12/07/2009 | 12/07/2009 |
| Note: Released By: JMCGOWEN revise plumbing drawings | |||
| PLLA | COMPLETE | 11/19/2009 | 11/19/2009 |
| Note: Released By: WBUTLER | |||
| FI1 | COMPLETE | 11/18/2009 | 11/18/2009 |
| Note: Released By: JPATTEE responde to comments | |||
| FI1 | HOLD | 11/10/2009 | 11/12/2009 |
| Note: Held By: JPATTEE Sheet A6, Hall 168, door labeled #2 exceeds allowable swing into corridor. Sheet A7, hall 165,163, doors labeled 3,7 exceed allowable swing into corridor. Sheet A3, Stairway #4 door 7 exceeds allowable swing into corridor. Sheet E1, staff lounge does not indicate emergency lighting. Sheet E1, Mail release room may not have adequate energency lighting . Sheet E3 Men and womens bathroom do not indicate emergency lighting. Provide design criteria for automatic fire sprinkler system per FAC 61G15-32.002 (5). | |||
| BLD | COMPLETE | 11/10/2009 | 11/10/2009 |
| Note: Released By: JMCGOWEN | |||
| ZON | COMPLETE | 11/09/2009 | 11/09/2009 |
| Note: Released By: ECOYNE Outside Generator to be permitted at a later date (letter on file) | |||
| ELEC | COMPLETE | 11/09/2009 | 11/09/2009 |
| Note: Released By: JMCGOWEN | |||
| MECH | COMPLETE | 11/09/2009 | 11/09/2009 |
| Note: Released By: JMCGOWEN | |||
| PLUM | COMPLETE | 11/09/2009 | 11/09/2009 |
| Note: Released By: JMCGOWEN | |||
| UD1 | COMPLETE | 11/09/2009 | 11/10/2009 |
| Note: Released By: CJOHNSON | |||
| BLD | HOLD | 11/05/2009 | 11/09/2009 |
| Note: Held By: JJOSEPH Need to change the door swing between the segment A and C from the client services to the lounge by providing an addendum that change will be made. | |||
| ZON | HOLD | 11/04/2009 | 11/05/2009 |
| Note: Held By: ECOYNE provide site plan showing dimensions of generator pad and location faxed 11/06/09 4:00pm |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 05/14/2010 |
| REINSPECTION FEE | ¤40.00 | 05/14/2010 |
| REINSPECTION FEE | ¤40.00 | 05/14/2010 |
| REVISION | ¤40.00 | 05/14/2010 |
| REVISION | ¤120.00 | 05/14/2010 |
| REVISION | ¤320.00 | 05/14/2010 |
| REVISION | ¤40.00 | 05/14/2010 |
| REVISION | ¤80.00 | 05/14/2010 |
| REVISION | ¤240.00 | 05/14/2010 |
| REVISION | ¤200.00 | 05/14/2010 |
| REVISION | ¤40.00 | 05/14/2010 |
| REVISION | ¤80.00 | 05/14/2010 |
| REVISION | ¤80.00 | 05/14/2010 |
| REVISION | ¤40.00 | 05/14/2010 |
| REVISION | ¤320.00 | 05/14/2010 |
| REVISION | ¤40.00 | 05/14/2010 |
| REVISION | ¤40.00 | 05/14/2010 |
| REVISION | ¤40.00 | 05/14/2010 |
| REVISION | ¤80.00 | 05/14/2010 |
| REVISION | ¤40.00 | 05/14/2010 |
| REVISION | ¤40.00 | 05/14/2010 |
| REVISION | ¤40.00 | 05/14/2010 |
| REVISION | ¤40.00 | 05/14/2010 |
| REVISION | ¤40.00 | 05/14/2010 |
| REVISION | ¤80.00 | 05/14/2010 |
| AUTHORIZATION LETTER | ¤500.00 | 05/14/2010 |
| BUILDING CODE ADMIN FUND | ¤305.70 | 11/19/2009 |
| BUILDING DISCOUNT 100% | (¤14,096.25) | 11/19/2009 |
| ELECTRIC FEE | ¤990.00 | 11/19/2009 |
| FIRE PLANS REVIEW | ¤611.39 | 11/19/2009 |
| MECHANICAL FEE | ¤990.00 | 11/19/2009 |
| PERMIT FEE | ¤10,850.00 | 11/19/2009 |
| PLAN CHECK FEE | ¤1,782.50 | 11/19/2009 |
| PLUMBING FEE | ¤990.00 | 11/19/2009 |
| RADON FEE | ¤305.70 | 11/19/2009 |
| ADMIN COMMERCIAL | ¤60.00 | 11/19/2009 |
| SITE PLAN 20 | ¤20.00 | 11/19/2009 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤5,509.04 |