I want to search for...

Permit #2009110452

Permit Details

Status: CANCEL

Parcel Id: 07-11-31-1090-00000-00B0
Subdivision: 1228 - SOUTHWEST QUADRANT
Job Phone: 386-338-7785
Location Address: 160 CYPRESS POINT PKWY
Type: CIA - COMMERCIAL INTERIOR EXTERIOR ALTERATION
Issue Date: 02/18/2010
NOC: Unknown
Applicant name: THOMAS M SCAGLIONE
Owner: ASNACO LLC C/O INTERSTATE HOLDINGS INC

Address

1307 S INTERNATIONAL PKWY

LAKE MARY, FL 32746

Address

SUITE 2051

LAKE MARY, FL 32746

Contracted Stated Job Value: ¤1,122.00
Job Description: BLDG C UNIT 110 - ELECTRICAL/MECH FOR REFRIG. DISPLAY CASES SEAFOOD MARKET
Type: CN

Contractor

T-CON GROUP, INC.
Status Location Address State License Number Phone
CANCEL

3246 NORTH POWERLINE ROAD

POMPANO BEACH, FL 33069

CBC1251999 (Exp: 08/31/2020) 954-825-8369

Sub Contractors

MICHAEL ALLEN PHILLIPS
Status Location Address State License Number Phone Fax
CANCEL

PO BOX 478

BUNNELL, FL 32110

CAC1814966 (Exp: 08/31/2014) 386-262-6034 866-369-7390
JOHN EDWARD GAMBONE
Status Location Address State License Number Phone Fax
CANCEL

55 BARRISTER LN

PALM COAST, FL 32137

ER13013466 (Exp: 08/31/2014) 386-586-9144 (386)246-6305

Inspection History

Type Request Date Result Inspector
UTILITY COMMERCIAL FINAL 11/18/2010 Disapproved - NO FEE DSPENCER
Note: Inspection Resulted at 11/18/2010 3:50:03 PM PLEASE CALL PAT GARRETT OR DANNY SPENCER TO MEET ON SITE # 386-931-2560 OR #386-569-9082 TO ARRANGE MEETING AND RESCHEDULE INSPECTION
UTILITY COMPANY FINAL 11/18/2010 APPROVED DSPENCER
FIRE FINAL 11/18/2010 Disapproved -FEE REQUIRED LHITES
Note: Inspection Resulted at 11/18/2010 12:24:53 PM 1. NONE OF THE EMERGENCY LIGHTS ARE WORKING. 2. MUST HAVE FIRE EXTINGUISHERS IN PLACE FOR FINAL INSPECTION
ELECTRICAL FINAL 11/17/2010 APPROVED CMINI
Note: THIS IS A REINSPECTION
ELECTRICAL FINAL 11/10/2010 CANCELLED BY APPLICANT CMINI
2ND ROUGH ELECTRICAL 11/09/2010 APPROVED RMARVEL
Note: THIS IS A REINSPECTION
ABOVE CEILING 11/09/2010 APPROVED RMARVEL
Note: THIS IS A REINSPECTION
2ND ROUGH ELECTRICAL 10/22/2010 Disapproved -FEE REQUIRED RMARVEL
Note: PER REQUEST FROM TOM Inspection Resulted at 10/22/2010 3:30:30 PM BURIAL DEPTH ON CONDUIT TO CONDENSORS FOR COOLERS NEED TO BE 18IN. 2 LOCATIONS OF RECEPTACLES DO NOT MATCH REVISED PLANS WHERE QUAD RECEPTACLES AIN PLACE OVER DUPLEX. NEED K.O. PLUG ON CONDENSORS WHERE THERE ARE UNSED OPENINGS. THIS INCLUDES SUB PANEL.
ABOVE CEILING 10/22/2010 Disapproved -FEE REQUIRED RMARVEL
Note: PER REQUEST FROM TOM Inspection Resulted at 10/22/2010 3:30:29 PM RECHECK STRAPPING IN MULTIPLE LOCATIONS.
ELECTRIC FEEDER 10/22/2010 APPROVED RMARVEL
Note: REQUEST FROM TOM
PATIO 08/11/2010 APPROVED - AS NOTED CMINI
Note: FOR AC COMPRESSORS PER LARRY HITES Inspection Resulted at 8/11/2010 3:30:59 PM PATIO SLAB FOR A/C
COMMERCIAL POWER INSPECTION 07/23/2010 APPROVED RMARVEL
Note: THIS IS A REINSPECTION
COMMERCIAL POWER INSPECTION 07/13/2010 Disapproved -FEE REQUIRED RMARVEL
Note: Wintz came in to schedule this inspection Inspection Resulted at 7/13/2010 10:37:17 AM OPEN BOX ABOVE REAR DOOR. SWITCH HANGING OUT OF WALL WITH BOX PARTIALLY COVERED BY ADJOINING WALL. NEED PLANS FOR INSPECTION.
FRAMING 04/29/2010 APPROVED CMINI
Note: THIS IS A REINSPECTION
FRAMING 04/23/2010 Disapproved -FEE REQUIRED CMINI
Note: THIS IS A REINSPECTION Inspection Resulted at 4/23/2010 1:24:03 PM NEED TO HAVE FRAMING PLAN ON JOB FOR INSPECTION
FRAMING 04/20/2010 Disapproved -FEE REQUIRED JHINDMAN
Note: requested by contractor Inspection Resulted at 4/20/2010 2:58:16 PM PLANS CALL FOR WOOD FRAME WALLS.
MONOLITHIC SLAB INSPECTION/SLAB 04/08/2010 APPROVED CMINI
COMMERCIAL BUILDING FINAL
UTILITY COMMERCIAL FINAL
Note: THIS IS A REINSPECTION
FIRE FINAL
Note: THIS IS A REINSPECTION

Review History

Department Status Date In Date Out
ELEC COMPLETE 11/15/2010 11/15/2010
Note: Released By: JMCGOWEN Revised panel schedule change electrical contractor
BLD COMPLETE 10/14/2010 10/14/2010
Note: Released By: JJOSEPH
BLD HOLD 10/12/2010 10/12/2010
Note: Held By: JJOSEPH Seafood counter needs to be accessible. Faxed and Emailed on 10/12/10 at 9:30AM
ELEC COMPLETE 09/24/2010 09/24/2010
Note: Released By: LHITES revision- changed the location of equipment
BLD HOLD 07/29/2010 07/29/2010
Note: Held By: FREODICA 1. Provide thickness and elevation above grade of slab for compressors.
BLD COMPLETE 07/29/2010 07/29/2010
Note: Released By: FREODICA Revision: Added 14' L x4' W x 4" thick concrete slab for compressors.
PLLA COMPLETE 07/27/2010 07/27/2010
Note: Released By: WBUTLER
ZON COMPLETE 07/23/2010 07/23/2010
Note: Released By: ECOYNE
ENGIN1 COMPLETE 07/23/2010 07/27/2010
Note: Released By: AWEBB
BLD COMPLETE 04/26/2010 04/26/2010
Note: Released By: JMCGOWEN change 2x4 wood frame to metal studs non structural
ELEC COMPLETE 02/18/2010 02/18/2010
Note: Released By: SKNOPF
ZON COMPLETE 02/18/2010 02/18/2010
Note: Released By: ECOYNE
FI1 CANCEL 02/18/2010 02/18/2010
Note: no review required - per Jeff P.
UD1 COMPLETE 02/18/2010 02/18/2010
Note: Released By: CJOHNSON Plumbing was submitted under a different permit
MECH COMPLETE 02/17/2010 02/17/2010
Note: Released By: FREODICA Correction on hold comment for exhaust hood 1. Exhaust hood is not required as electric stove and fryer were removed
BLD COMPLETE 02/17/2010 02/18/2010
Note: Released By: JJOSEPH Correction plans deletion of hood,stove,fryer clarify mop sink on inner & outer wall of new extended closet.
MECH HOLD 02/12/2010 02/12/2010
Note: Held By: FREODICA Correction comment: 1. Provide separate permit for exhaust hood. Hood shall be type 1.
BLD HOLD 02/12/2010 02/12/2010
Note: Held By: JJOSEPH 1.Revise the drawing to make separation between the Food preparation area and the rest of Store. 2. Please make a revision on the bathroom area, it cannot open into the Food preparation area. 3.Need to provide occupancy classification (use of space) and occupant load .
ELEC HOLD 02/11/2010 02/12/2010
Note: Held By: SKNOPF CITY OF PALM COAST BUILDING DIVISION Comments on Permit Application#2009110452 (Fish Store/Restaurant @ Unit C110 160 Cypress Point Pkwy.) 2/12/2010 The following items must be resolved in order to complete the Building Permit plan review. Electrical Comments: 1. Identify circuits for commercial electric stove, fryer, exhaust hood and make-up air. 2. Provide entirely revised load calculations. 3. A separate permit must be pulled for the hood. 4. Provide disconnects for AHU and Water Heater. 5. Coordinate amperage of all equipment between power plan and panel schedule loads. …………………………………………… Susan J. Knopf Plans Examiner City of Palm Coast - Building Division 2 Commerce Boulevard Palm Coast, Florida 32164-3216 [tel]: (386) 986-2463 [fax]: (386) 986-3781 [email]: sknopf@ci.palm-coast.fl.us
ELEC COMPLETE 01/26/2010 01/26/2010
Note: Released By: SKNOPF Revised load calcs (per engineer) Approved for Release.
BLD HOLD 01/26/2010 02/12/2010
Note: Held By: JJOSEPH Correction exted partition closet for mop sink & water heater business & occupancy classification exhaust hood detail enclosed.
BLD HOLD 01/26/2010 01/26/2010
Note: Held By: JJOSEPH Need to provide occupancy classification (use of space) and occupant load before releasing the permit application
ELEC HOLD 01/15/2010 01/15/2010
Note: Held By: SKNOPF correction - new calcs CITY OF PALM COAST BUILDING DIVISION Comments on Permit Application#2009110452 (Tenant Upfit for Unit C-110 @ 160 Cypress Point Pkwy.) 1/15/2010 The following items must be resolved in order to complete the Building Permit plan review. Electrical Comments: 1. Provide Load Calculations. 2. Verify AHU and CU loads. 3. Verify use of circuit C110-10. 4. Clarify circuit numbers for ACU's. 5. Clarify use of circuit #20. …………………………………………… Susan J. Knopf Plans Examiner City of Palm Coast - Building Division 2 Commerce Boulevard Palm Coast, Florida 32164-3216 [tel]: (386) 986-2463 [fax]: (386) 986-3781 [email]: sknopf@ci.palm-coast.fl.us
PLUM CANCEL 01/14/2010 01/14/2010
Note: Plumbing was applied under separate Permit Application No. 2010010285.
ELEC HOLD 01/05/2010 01/05/2010
Note: Held By: SKNOPF changed lt's circuit to new panel schedule corrected load calcs changed service to 225 CITY OF PALM COAST BUILDING DIVISION Comments on Permit Application#2009110452 (Tenant Upfit Suite C110 @ 160 Cypress Point Pkwy.) 1/5/2010 The following items must be resolved in order to complete the Building Permit plan review. Previous Electrical Comments from 12/30/2009: 1. Complete. 2. Previous Item #2: Provide a revised Demand Load Calculation per FBC 106.3.5 Electrical #7 and NEC 220 Part III showing the actual existing loads plus all of the new loads. Total shown for new equipment loads is incorrect. Revise. 3. Previous Item #3: Provide a revised partial Electrical Riser Diagram, as required dependent on resulting Demand Load Calculation Item #2 above, showing the tenant feeder conductor size, feeder OCP, and panel. #3/0 THWN is only good for 200A. Revise feeder size and identify correct conduit size for new feeder. 4. Complete. Previous Electrical Comments from 1-4-2010: 1. Complete. 2. Complete. 3. Coordinate the loads shown in the load calculation totals on the plan sheet with the loads shown for the same new equipment in the panel schedule for the following: a. Ice Machine - Load calc. shows 6.8A (.8KVA) vs. Panel Sched. shows .5KVA b. Meat Case - Load calc. shows 8.9A (1.1KVA) vs. Panel Sched. shows .8KVA c. Seafood Salad - Load calc. shows 4.1A (.5KVA) vs. Panel Sched. shows .8 KVA d. Standup Freezer - Load calc. shows 5.3A (.6KVA) vs. Panel Sched. shows .8KVA e. Meat Grinder - Load calc. shows 8.2A (1.0KVA) vs. Panel Sched. shows .6KVA f. Walk-in Cooler - Load calc. shows 5.2A (.6KVA) vs. Panel Sched. shows .8KVA g. Meat Cutter - Load calc. shows 7A (1.5KVA) vs. Panel Sched. shows 5KVA h. Hot Water Heater - Load calc. shows 26A (5.4KVA) vs. Panel Sched. shows 3.5KVA i. 125A Sub-panel - Load calc. shows 38.6A (8.0KVA) vs Panel Sched. 7.8KVA 4. Complete. New Electrical Comments: 1. Circuit # 20 is shown on both existing power plan for 6 receptacles and on new equipment power plan for Walk-in Cooler. Coordinate circuits. 2. New Equipment demand load total shown is incorrect per information and values given on equipment location plan. Revise new equipment demand total. 3. Demand Load calculation given shows 222.5A, but feeder is still shown as #3/0 THHN with a 200A circuit breaker OCP. #3/0 THHN is only good up to 200A. Revise feeder and OCP to accommodate demand load and provide size and type of conduit for revised feeder. …………………………………………… Susan J. Knopf Plans Examiner City of Palm Coast - Building Division 2 Commerce Boulevard Palm Coast, Florida 32164-3216 [tel]: (386) 986-2463 [fax]: (386) 986-3781 [email]: sknopf@ci.palm-coast.fl.us
MECH COMPLETE 01/04/2010 01/04/2010
Note: Released By: FREODICA Note: If walk-in cooler is packaged type (plug- in electrical), mechanical review is not required but if condenser is a remote from cooler, mechanical revision is required.
PLUM HOLD 01/04/2010 01/05/2010
Note: Held By: FREODICA NEW PLUMBING RISER WITH EXISTING SEWER & SINK ADDITION NO MECHANICAL CHANGES Review Comments for submitted corrections Based on previous review comments dated 12/23/09 the ff. items need to be addressed: Item 1 : Sanitary layout & riser diagram - Sanitay layout does not show the building backgound and location of plumbing fixtures. Riser diagram does not show where the new sanitary lines and vent system are tied in to the existing. Item 2: Dometic water layout & riser - Need to be addressed. Item 3: Material specifications of DWV & domestic water - Need to be addressed. Item 5: Plumbing fixture specifications- need to be addressed. Item 6: Provide drinking fountain - need to be addressed.
ELEC HOLD 12/31/2009 01/04/2010
Note: Held By: SKNOPF ELECTRIC REVISION/NO MECHANICAL CHANGES /NEW PLUMBING RISER WITH EXIST SEWER & SINK ADDITION CITY OF PALM COAST BUILDING DIVISION Comments on Permit Application#2009110452 (Tenant Upfit Suite C110 @ 160 Cypress Point Pkwy.) 1/4/2010 The following items must be resolved in order to complete the Building Permit plan review. Previous Electrical Comments from 12/30/2010: 1. Previous Item #3: Circuit #8 is shown on both lighting and power plans. Revise load in panel and coordinate circuit identification. 2. Previous Item #4: Provide a revised Demand Load Calculation per FBC 106.3.5 Electrical #7 and NEC 220 Part III showing the actual existing loads plus all of the new loads. New given equipment loads plus actual existing loads appear to be greater than 200A service change shown. 3. Previous Item #5: Provide a revised partial Electrical Riser Diagram, as required dependent on resulting Demand Load Calculation Item #2 above, showing the tenant feeder conductor size, feeder OCP, and panel. 4. Previous Item #11: Shell building plans show that an Insta-Hot was installed in this tenant space for the bathroom sink, but this equipment is not listed in the submitted panel schedule. Provide circuit identification, circuit breaker size, and load for this equipment if it is to remain. If it is to be deleted, and replaced with hot water piping from the new Hot Water Heater, show on plans that the Insta-Hot is to be deleted on plans and panel schedule. New Electrical Comments: 1. The circuits identified in the panel schedule do not match the circuits on the layout plan for the following: a. 1, 2, 3, 4, 5, 6, 7, 8, 9, 11:13, 12:14, 16:18, 15:17, 26 and 28. Coordinated between panel schedule and plans submitted. 2. The revised Demand Load Calculation is missing the following information: a. Revised existing load should include the 2-pole Condensing Unit loads. b. New equipment total load. c. All continuous loads are to be included at 125% (includes wire size, circuit breaker and load calc.) 3. Coordinate the loads shown in the load calculation totals on the plan sheet with the loads shown for the same new equipment in the panel schedule for the following: a. Ice Machine - Load calc. shows 6.8A (.8KVA) vs. Panel Sched. shows .5KVA b. Meat Case - Load calc. shows 8.9A (1.1KVA) vs. Panel Sched. shows .8KVA c. Seafood Salad - Load calc. shows 4.1A (.5KVA) vs. Panel Sched. shows .8 KVA d. Standup Freezer - Load calc. shows 5.3A (.6KVA) vs. Panel Sched. shows .8KVA e. Meat Grinder - Load calc. shows 8.2A (1.0KVA) vs. Panel Sched. shows .6KVA f. Walk-in Cooler - Load calc. shows 5.2A (.6KVA) vs. Panel Sched. shows .8KVA g. Meat Cutter - Load calc. shows 7A (1.5KVA) vs. Panel Sched. shows 5KVA h. Hot Water Heater - Load calc. shows 26A (5.4KVA) vs. Panel Sched. shows 3.5KVA i. 125A Sub-panel - Load calc. shows 38.6A (8.0KVA) vs Panel Sched. 7.8KVA 4. Ground wire for feeder from Meter to 225A panel does not match from plan to riser. Coordinate. …………………………………………… Susan J. Knopf Plans Examiner City of Palm Coast - Building Division 2 Commerce Boulevard Palm Coast, Florida 32164-3216 [tel]: (386) 986-2463 [fax]: (386) 986-3781 [email]: sknopf@ci.palm-coast.fl.us
ELEC HOLD 12/30/2009 12/30/2009
Note: Held By: SKNOPF ELECTRICAL PLAN REVIEW CORRECTIONS/CORRECTION CAME IN ON 12/28/2009 NOT ABLE TO REVIEW WAITING ON UTLITIES TO SEND ORIGINAL FOLDER BACK TO BD. CITY OF PALM COAST BUILDING DIVISION Comments on Permit Application#2009110452 (Commercial Interior Alteration @ Unit C-110, 160 Cypress Point Pkwy.) 12/30/2009 The following items must be resolved in order to complete the Building Permit plan review. Previous Electrical Comments from 12-22-2009: 1. Complete. 2. Complete. 3. Circuit #8 is shown on both lighting plan and power plan (bath area). Revise panel load. 4. Provide a revised Demand Load Calculation per FBC 106.3.5 Electrical #7 and NEC 220 Part III showing the actual existing loads. New given equipment loads plus actual existing loads appear to be greater than 200A. 5. Provide a revised partial Electrical Riser Diagram, as required dependent on resulting Demand Load Calculation Item #4 above, showing the tenant feeder conductor size, feeder OCP, and panel. 6. Provide manufacturer's submittal documents for all commercial kitchen equipment. 7. Panel schedule shows the AHU as 2P with 2 different sizes for the circuit breaker. Identify correct circuit breaker sizes. There are 2 AHU and 2 ACU in this space. Revise panel schedule to accurately reflect required circuit breaker sizes and loads for these 4 units per nameplates. 8. Same as #7. 9. Complete. 10. Panel schedule identifies circuit #36 as "fish counter", but this equipment is not identified on drawings. Provide location and type of device for this circuit. 11. Shell building plans show that an Insta-Hot was installed in this tenant space for the bathroom sink, but this equipment is not listed in the submitted panel schedule. Provide circuit identification, circuit breaker size, and load for this equipment. 12. Deleted. 13. Walk-In Cooler is shown as a 1P 20A circuit breaker with a 200VA load in the panel schedule. Update panel schedule with nameplate load. 14. Provide location on plan sheet for circuit #41 Wrapper equipment. 15. Complete. 16. Complete. 17. Revise loads in panel schedule for circuits 25 and 27 to reflect actual quantity of receptacles on each circuit per NEC 220.14(I). 18. Deleted. 19. Complete. New Electrical Comments resulting from latest submitted documents: 1. None of the new circuits submitted for the new equipment match the circuits shown on the panel schedule. 2. Latest load calculation submitted does not include new "Fish counter" or "Wrapper" equipment. 3. Remove "Electric Stove" from panel schedule as it appears to have been deleted. …………………………………………… Susan J. Knopf Plans Examiner City of Palm Coast - Building Division 2 Commerce Boulevard Palm Coast, Florida 32164-3216 [tel]: (386) 986-2463 [fax]: (386) 986-3781 [email]: sknopf@ci.palm-coast.fl.us
MECH HOLD 12/23/2009 12/23/2009
Note: Held By: FREODICA 1. Provide HVAC plans and details suitable for review, construction and inspection. 2. Provide information on the use of building space. Plan shows electric stove. Is the space used as a restaurant? 3. Provide exhaust hood for the electric stove. Provide information on its type, duct layout, size, fan specifications & make- up air system.
PLUM HOLD 12/23/2009 12/23/2009
Note: Held By: FREODICA 1. Provide sanitary layout and riser diagram suitable for review, construction and inspection. 2. Provide domestic water layout and riser diagram. 3. Provide material specifications for sanitary (DWV) and domestic water. 4. Provide occupancy classification and occupant load. 5. Provide plumbing fixture specifications. 6. Provide drinking fountain.
UD1 HOLD 12/23/2009 12/29/2009
Note: Held By: CJOHNSON 1. Provide legible water & sanitary layout for review. 2. I understand an exemption was approved for the grease interceptor. Provide grease interceptor exemption letter. Label the under the sink grease trap with size on the plans. Provide spec sheet for the device
ELEC HOLD 12/22/2009 12/22/2009
Note: Held By: SKNOPF CITY OF PALM COAST BUILDING DIVISION Comments on Permit Application#2009110452 (Commercial Interior Alteration @ Unit C-110, 160 Cypress Point Pkwy.) 12/22/2009 The following items must be resolved in order to complete the Building Permit plan review. Electrical Comments: 1. Provide full size plans/details suitable for review, construction and inspection. Plans must be large enough for electronic scanning and filing, minimum 11" x 17". 2. Identify all circuits, both new and existing, on plan sheet for all lighting, devices, and equipment. Identify whether new equipment is to be plug-and-cord to a receptacle and show receptacle location, or hard-wired. 3. Circuit #8 is shown on both lighting plan and power plan (bath area). Revise panel load. 4. Provide a Demand Load Calculation per FBC 106.3.5 Electrical #7 and NEC 220 Part III. 5. Provide a partial Electrical Riser Diagram showing the tenant feeder conductor size, feeder OCP, and panel. 6. Provide manufacturer's submittal documents for all commercial kitchen equipment. 7. Panel schedule shows the AHU as 2P with 2 different sizes for the circuit breaker. Identify correct circuit breaker size. 8. Circuit breaker sizes on submitted panel schedule do not match loads for existing AHU and ACU. Identify correct circuit breaker size required per each unit nameplate. 9. Plan shows meat cutter is 30A, but panel schedule shows circuit breaker is 2P 20A. Identify correct circuit breaker size and equipment load per nameplate rating. 10. Panel schedule identifies circuit #36 as "fish counter", but this equipment is not identified on drawings. Provide location and type of device for this circuit. 11. Shell building plans show that an Insta-Hot was installed in this tenant space for the bathroom sink, but this equipment is not listed in the submitted panel schedule. Provide circuit identification, circuit breaker size, and load for this equipment. 12. Revise commercial stove load in panel schedule to be distributed across 2 phases. 13. Walk-In Cooler is shown as a 1P 20A circuit breaker with a 200VA load. Submit manufacturer electrical data, or photocopy of nameplate electrical data. 14. Provide location on plan sheet for circuit #41 Wrapper equipment. 15. Shell building plans show that tenant service panel, OCP, and feeder are 150A, but plans submitted show a 200A panel. Please clarify. 16. Provide manufacturer submittal electrical data for "125A Compressor sub-panel" listed as circuits 19, 21 in the panel schedule and show location of sub-panel and equipment. Provide sub-panel loads in main tenant panel. Include any sub-panels on Electrical Riser diagram with feeder sizes and OCP shown. 17. Revise loads in panel schedule for circuits 25 and 27 to reflect actual quantity of receptacles on each circuit per NEC 220.14(I). 18. Provide hood and make-up air circuits, circuit breaker sizes, and loads per FBC Mechanical sections 506 and 507, and NEC 220.14(A) and NEC 422 Appliances. 19. Provide method of installation for electrical branch circuits to free-standing equipment (meat case, standing freezer, seafood salad display). Identify type of conduit to these units. …………………………………………… Susan J. Knopf Plans Examiner City of Palm Coast - Building Division 2 Commerce Boulevard Palm Coast, Florida 32164-3216 [tel]: (386) 986-2463 [fax]: (386) 986-3781 [email]: sknopf@ci.palm-coast.fl.us
FI1 HOLD 12/01/2009 12/02/2009
Note: Held By: JPATTEE Provide detailed floor plan indicating location of equipment
BLD HOLD 11/30/2009 12/01/2009
Note: Held By: JJOSEPH Provide occupancy classification (use of space) and occupant load.
ELEC HOLD 11/23/2009 11/23/2009
Note: Held By: SKNOPF CITY OF PALM COAST BUILDING DIVISION Comments on Permit Application#2009110452(Restaurant @ 160 Cypress Point Pkwy.) 11/23/2009 The following items must be resolved in order to complete the Building Permit plan review. Electrical Comments: 1. Provide Revised Demand Load Calculation per FBC 106.3.5 Electrical #7 and NEC 220 Part III. 2. Electrical Power Plan submitted is not for this building or address. Provide detail/plan suitable for review, construction and inspection. 3. Provide manufacturer's submittal documents for all commercial kitchen equipment. 4. Circuit breaker sizes shown on revised panel schedule do not match loads for existing AHU and ACU. 5. Existing loads do not match revised panel schedule circuits 25 and 27. 6. Circuit 22 is an existing circuit for an outside sign, but revised panel schedule shows this circuit for a 2P Meat Cutter. 7. Circuit 8 is shown on existing plans as both lighting and bath GFCI. Revise panel loads. 8. A separate permit will be required for the ansul system. 9. Identify plumbing and architectural changes and plumbing contractor. …………………………………………… Susan J. Knopf Plans Examiner City of Palm Coast - Building Division 2 Commerce Boulevard Palm Coast, Florida 32164-3216 [tel]: (386) 986-2463 [fax]: (386) 986-3781 [email]: sknopf@ci.palm-coast.fl.us
ZON HOLD 11/23/2009 11/24/2009
Note: Held By: ECOYNE provide use of unit e-mail 11/23/09 8:36am

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
CONTRACTOR CHANGE ¤40.00 07/08/2010
REINSPECTION FEE ¤40.00 07/08/2010
REINSPECTION FEE ¤40.00 07/08/2010
REVISION ¤40.00 07/08/2010
BUILDING DISCOUNT 100% (¤352.81) 02/18/2010
ELECTRIC FEE ¤60.67 02/18/2010
FIRE PLANS REVIEW ¤25.00 02/18/2010
MECHANICAL FEE ¤60.67 02/18/2010
PERMIT FEE ¤50.00 02/18/2010
PLAN CHECK FEE ¤100.00 02/18/2010
PLUMBING FEE ¤60.67 02/18/2010
REVISION ¤200.00 02/18/2010
REVISION ¤40.00 02/18/2010
REVISION ¤40.00 02/18/2010
REVISION ¤40.00 02/18/2010
REVISION ¤40.00 02/18/2010
SITE PLAN 20 ¤20.00 02/18/2010
ADMIN COMMERCIAL ¤60.00 02/18/2010
CONTRACTOR CHANGE ¤40.00 02/18/2010
ADDITIONAL FEE ¤40.00
REINSPECTION FEE ¤40.00
REINSPECTION FEE ¤40.00
REVISION ¤40.00
REVISION ¤40.00
REVISION ¤40.00
REVISION ¤40.00
REINSPECTION FEE ¤40.00
REINSPECTION FEE ¤40.00
Fees Total Due: ¤360.00 Total Paid: ¤644.20