Permit #2010100215
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7025-000G0-0210 |
| Total Square Footage: 11831 sqft |
| Block: 000G0 |
| Subdivision: - |
| Job Phone: 386-338-7785 |
| Location Address: 85 CYPRESS POINT PKWY |
| Type: CSD - COMMERCIAL SITE DEVELOPMENT |
| Issue Date: 10/29/2010 |
| NOC: Unknown |
| Applicant name: THOMAS M SCAGLIONE |
| Owner: INTERNATIONAL CARPET OF FLORIDA LLC |
|
Address 109 S. SIXTH ST FLAGLER BEACH, FL 32136 |
| Lot: 0210 |
| Contracted Stated Job Value: ¤500,000.00 |
| Job Description: SITE DEVELOPMENT - (NIKZAD PLAZA) RETAIL SHOPS SITE & BLDG SHELL |
| Type: CN |
Contractor
T-CON GROUP, INC.
| Status | Location Address | State License Number | Phone |
| CANCEL |
3246 NORTH POWERLINE ROAD POMPANO BEACH, FL 33069 |
CBC1251999 (Exp: 08/31/2020) | 954-825-8369 |
Sub Contractors
ISAAC WALTER JOHNSTON
| Status | Location Address | State License Number | Phone |
| ACTIVE |
887 BRENTWOOD DRIVE Daytona Beach, FL 32117 |
CFC023634 (Exp: 08/31/2026) | (386) 252-7047 |
CHARLES K DAVIS
| Status | Location Address | State License Number | Phone |
| ACTIVE |
3000 E MOODY BLVD BLDG 2 BUNNELL , FL 32110 |
EC13004270 (Exp: 08/31/2026) | 386-931-6614 |
Inspection History
| Type | Request Date | Result | Inspector |
| HANDICAPPED RAMP INSPECTION | 11/22/2011 | APPROVED | CMINI |
| HANDICAPPED PARKING AND SIGNAGE | 11/22/2011 | APPROVED | CMINI |
| LANDSCAPE - LANDSCAPE/IRRIGATION FINAL | 11/22/2011 | APPROVED | WBUTLER |
| Note: THIS IS A REINSPECTION | |||
| ENGINEERING FINAL | 11/22/2011 | FINAL APPROVED | LFITZGERALD |
| TRAFFIC ENGINEER | 11/22/2011 | APPROVED | LFITZGERALD |
| Note: Inspection Resulted at 11/22/2011 11:55:36 AM BOB BOGGS REVIEWED PLAN AS-BUILTS AND SITE CONDITIONS;ONLY COMMENT WAS REGARDING THE DROP OFF-POTENTIAL HAZARD TO A VEHICLE ALONG THE CONCRETE PAVEMENT WHERE A FUTURE DRIVEWAY(WEST SIDE-FRONT) WILL CONNECT THE OTHER SITE | |||
| LANDSCAPE FINAL | 11/08/2011 | APPROVED | WBUTLER |
| Note: Permit #2010100215 Work complete and approved. | |||
| LANDSCAPE FINAL | 11/08/2011 | CANCELLED BY INSPECTOR | WBUTLER |
| Note: THIS IS A REINSPECTION | |||
| LANDSCAPE - PUNCH LIST | 11/08/2011 | APPROVED | WBUTLER |
| LANDSCAPE - BONDED LANDSCAPE/IRRIGATION ASBUILTS | 11/08/2011 | APPROVED | WBUTLER |
| LANDSCAPE - BARRICADE / EROSION CONTROL | 11/08/2011 | APPROVED | WBUTLER |
| LANDSCAPE - LOCATION BACKFLOW PREVENTOR PAD | 11/08/2011 | APPROVED | WBUTLER |
| LANDSCAPE - SITE INSPECTION | 11/08/2011 | APPROVED | WBUTLER |
| ENG SITE DEV FINAL | 10/28/2011 | APPROVED - AS NOTED | JCOLASANTI |
| Note: THIS IS A REINSPECTION requested by contractot Inspection Resulted at 10/28/2011 11:34:36 AM CONTRACTOR MUST HAVE APPROVED AS-BUILTS, DENSITY TEST REPORTS, LETTER OF COMPLETION FROM ENGINEER APPROVED BY THE COPC AND ALL UTILITY DEPT FINAL BEFORE PROJECT CAN BE FINALED | |||
| ENG SITE DEV FINAL | 10/26/2011 | CANCELLED BY APPLICANT | JCOLASANTI |
| Note: THIS IS A REINSPECTION REQUESTED BY TOM | |||
| ENG SUBSTANTIAL COMPLETION (OFFICE USE) | 10/14/2011 | Disapproved -FEE REQUIRED | JMCGOWEN |
| Note: THE FOLLOWING ITEMS NEED TO BE CORRECTED AND PUNCLIST COMPLETION INSPECTION CALLED IN. "$250.00 HANDICAP PARKING FINE" SIGNS MUST BE 6" PER PLANS, ADA MATS NEED TO BE INSTALLED, DRAINAGE BASIN LOCATED IN 17`` LANDSCAPE ISLAND NEEDS TO BE EXPOSED, DUMPSTER WALLS NEED TO BE FINISHED PAINTED, PAINT TOP CAP OF DUMPSTER BALAS, REMOVE SILT FENCE AND FABRIC FROM STRUCTURES LOCATED WEST OF BUILDING IN SWALE, REMOVE FOAM FROM BIKE RACK, CLEAN UP ALL CEMENT PILES AND DIRT PILES THROUGHT SITE, FINISH WORK AT GREESE TRAP PER UTILITY INSTRUCTIONS AND REPLACE CEMENT AND STRIPING. COMPLETE PUNCH LIST SENT BY ENGINEER. i contacted tom and he is aware that a final asbuilt is required with chages made. he will meet with us friday 11/18/11 | |||
| ENG-SUBSTANTIAL WALK THRU - PUNCH | 10/14/2011 | APPROVED - AS NOTED | JCOLASANTI |
| Note: per request from tom Inspection Resulted at 10/14/2011 3:35:20 PM THE FOLLOWING ITEMS NEED TO BE CORRECTED AND PUNCLIST COMPLETION INSPECTION CALLED IN. "$250.00 HANDICAP PARKING FINE" SIGNS MUST BE 6" PER PLANS, ADA MATS NEED TO BE INSTALLED, DRAINAGE BASIN LOCATED IN 17`` LANDSCAPE ISLAND NEEDS TO BE EXPOSED, DUMPSTER WALLS NEED TO BE FINISHED PAINTED, PAINT TOP CAP OF DUMPSTER BALAS, REMOVE SILT FENCE AND FABRIC FROM STRUCTURES LOCATED WEST OF BUILDING IN SWALE, REMOVE FOAM FROM BIKE RACK, CLEAN UP ALL CEMENT PILES AND DIRT PILES THROUGHT SITE, FINISH WORK AT GREESE TRAP PER UTILITY INSTRUCTIONS AND REPLACE CEMENT AND STRIPING. COMPLETE PUNCH LIST SENT BY ENGINEER. | |||
| ENG SITE DEV FINAL | 10/13/2011 | CANCELLED BY APPLICANT | JCOLASANTI |
| Note: REQUESTED BY CONTRACTOR AT 1:30 | |||
| LANDSCAPE - LANDSCAPE/IRRIGATION FINAL | 10/13/2011 | Disapproved -FEE REQUIRED | WBUTLER |
| Note: PUNCHLIST FOR NIZCAD PLAZA LANDSCAPE AND IRRIGATION Permit Number 2010100215 10/13/11 1. One irrigation head on zone 1 near the holly tree closest to the entrance drive has been cut off by a mower. 2. On zone 1 in front of the backflow preventers there is a spray head that needs to be installed on a riser to clear the viburnum shrubs. 3. Several plants have died or do not even approach the quality of a Florida Number 1 shrub and will require replacement. These shrubs have been flagged with red survey ribbon. 4. Need to replace the sod on the west side of the bike rack that had dirt piled on it. It is mostly dead now. Also it appears that the east side of the site and the side on the north of the rear parking area was never sodded and it is total weeds. Need to either scrape all the weeds off (or spray with weed killer) and then re-sod with St. Augustine grass per the approved plan. 5. Clean up debris on the site, grass clumps, roots, concrete and asphalt, etc. 6. On irrigation zone 2, missing one spray head on the west side of the entrance drive against the curb. Need to install this per plan. 7. An area in the front buffer that does not have sod needs to be sodded and the dead, weedy area on the west side of the entrance drive off Cypress Point Parkway needs new sod. 8. Need to raise some of the heads on zone 2 so they clear the top of the grass. 9. When as-builts are submitted for the irrigation plans, make sure the following information is provided: - Measurements from two fixed points for the location of the valve boxes - A card in the controller that notes each zone by number and describes what area of the site it generally covers (make sure the zone numbering on the clock matches the numbering on the as-built) - Pick up all heads that were installed and not shown (there were a couple extra that were provided) and also show the added heads noted in this punch list. 10. On zone 3 need another riser on the southernmost spray head on the east hedge row in order to clear the top of the hedge. 11. Need to raise one head in the northeast landscape parking lot island that is hardly clearing the mulch. 12. Need to remove all mulch from the stems of the plants. 13. Fix the disturbed mulch around the concrete pads on the north side of the building. 14. Owner's option-All trees are not staked per the plan. If owner elects not to stake the trees, remove the old strapping from the trunks. 15. Remove silt fence from mitered end section from the west side of the site. 16. Adjust the heads on the west side of the building so the spray does not hit the building and move the heads further out that are closer than 12" to wall. 17. On zone 3, the first planting strip in front of the building needs an end strip to fully irrigate the holly shrubs. 18. In the center island in the front of the building, there are two side strips but also need an end strip on each end to reach the end holly shrubs. 19. Need sod on the west side of the parking lot as there is bare dirt. 20. Need to add one end strip in the front landscape planter just west of the landscape island with the oak trees. 21. One nozzle broken along the front of the building in the landscape island in front of the building. | |||
| CONCRETE FORMING - OTHER | 08/16/2011 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 8/16/2011 3:25:30 PM INSPECTED PARKING AREA IN FRONT OF BUILDING FOR CONCRETE POUR. CONTRACTOR WILL NEED TO CALL IN INSPECTION FOR PROPER PLACEMENT OF SAW CUTS. | |||
| ENGTESTING - SOIL DENSITY | 08/16/2011 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| CONCRETE FORMING - OTHER | 07/19/2011 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION per request from TOm Inspection Resulted at 7/19/2011 3:32:24 PM FRONT WEST END OF PARKING LOT IS PREPED, DENSITY PASSSED AND IS READY FOR CONCRETE. | |||
| CONCRETE FORMING - OTHER | 07/01/2011 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 7/1/2011 3:13:59 PM EAST SIDE OF SITE PARKING LOT IS APPROVED FOR CEMENT POUR. AREA MARKED ON PLANS. | |||
| CONCRETE FORMING - OTHER | 06/30/2011 | CANCELLED BY APPLICANT | JCOLASANTI |
| CONCRETE FORMING - OTHER | 06/29/2011 | CANCELLED BY APPLICANT | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| CONCRETE FORMING - OTHER | 06/28/2011 | CANCELLED BY APPLICANT | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| ENGTESTING - SOIL DENSITY | 06/28/2011 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 6/28/2011 3:46:19 PM EAST SIDE PARKING @ INLET, SIDE CENTER AND SIDE END. SOUTHWEST PARKING LOT NW AND SW SECTIONS. | |||
| SITE LIGHTING - PLACEMENT / FOUNDATION | 06/28/2011 | PARTIALLY APPROVED | CMINI |
| Note: Inspection Resulted at 6/28/2011 3:44:06 PM FOOTER HOLES | |||
| ENGTESTING - SOIL DENSITY | 06/27/2011 | CANCELLED BY APPLICANT | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| CONCRETE FORMING - OTHER | 06/27/2011 | CANCELLED BY APPLICANT | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| CONCRETE FORMING - OTHER | 06/23/2011 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 6/23/2011 2:45:52 PM SAW CUTS FOR CONCRETE PARKING LOT COMPLETE UPTO DUMPSTER PAD. I TOLD CONTRACTOR TO HAVE COPC STAMP PLAN REVISION FOR CONCRETE PARKING LOT BY NEXT INSPECTION. | |||
| CONCRETE FORMING - OTHER | 06/21/2011 | CANCELLED BY APPLICANT | JCOLASANTI |
| ENGTESTING - SOIL DENSITY | 06/17/2011 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| ENG-TEST- SUBGRADE | 06/17/2011 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| ENGTESTING - SOIL DENSITY | 06/15/2011 | CANCELLED BY APPLICANT | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| ENGTESTING - SOIL DENSITY | 06/14/2011 | CANCELLED BY APPLICANT | JCOLASANTI |
| ENG-TEST- SUBGRADE | 06/13/2011 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 6/13/2011 2:39:46 PM INSPECTED SUBGRADE FOR PARKING LOT CEMENT POUR AT REAR 1/3 OF LOT. DENSITY TEST WILL BE NEEDED. AREA INSPECTED MARKED ON PLANS. | |||
| LANDSCAPE- TREE QUALITY | 06/03/2011 | APPROVED | WBUTLER |
| LANDSCAPE- TREE QUALITY | 06/02/2011 | APPROVED | WBUTLER |
| SITE LIGHTING - PLACEMENT / FOUNDATION | 05/27/2011 | APPROVED - AS NOTED | CMINI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 5/27/2011 2:36:12 PM UNDERGROUND SITE AND FEEDER | |||
| SITE STRUCTURE - RETAINING WALL (FOUNDATION, POURED CELL ,BOND BEAM) | 05/10/2011 | APPROVED - AS NOTED | CMINI |
| Note: Inspection Resulted at 5/10/2011 12:55:04 PM THIS WAS AN INSPECTION ON THE DUMPSTER ENCLOSURE LINTEL STEEL.OK | |||
| SITE LIGHTING - PLACEMENT / FOUNDATION | 05/10/2011 | PARTIALLY APPROVED | CMINI |
| Note: Inspection Resulted at 5/10/2011 12:55:05 PM PARTIAL UNDERGROUNG ON SITE LIGHTING MARKED ON PLANS. | |||
| CONCRETE FORM - SIDEWALK | 04/11/2011 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| CONCRETE FORMI - CURBING | 04/11/2011 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| BUILDING-SITE STRUCTURE - TRASH DUMPSTER | 04/07/2011 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| BUILDING-SITE STRUCTURE - TRASH DUMPSTER | 03/30/2011 | Disapproved -FEE REQUIRED | JCOLASANTI |
| Note: Inspection Resulted at 3/30/2011 3:07:31 PM DUMPSTER PAD MISSING WIRE MESH, PAD NEEDS COMPACTION AT 98% PER PLANS, NO TEST REPORT ON SITE. REPAIR WASHOUT LOCATED AT REAR RIGHT IN PAD. | |||
| CONCRETE FORMI - CURBING | 03/15/2011 | Disapproved -FEE REQUIRED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 3/15/2011 3:26:21 PM INSPECTED CURB FRONT WEST OF BUILDING WAS FORMED NOT ACCORDING TO PLAN. CONTRACTOR NEEDS REVISION OR RE-SET FORMS TO PLAN. | |||
| CONCRETE FORM - SIDEWALK | 03/10/2011 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 3/10/2011 3:39:18 PM SIDEWALK FORMS EAST OF BUILDING ATTACHED TO CURB HAS BEEN INSPECTED AND MARKED ON PLANS. | |||
| CONCRETE FORMI - CURBING | 03/08/2011 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 3/8/2011 3:33:43 PM CONTRACTOR FORMED "F" CURB AROUND EAST AND REAR OF BUILDING. AREA MARKED AND DATED ON PLANS. | |||
| CONCRETE FORMI - CURBING | 03/04/2011 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 3/4/2011 3:28:24 PM CURB FORMS INSPECTED PER PLANS SE END OF BUILDING. AREA NOTED ON PLANS. | |||
| CONCRETE FORMI - CURBING | 03/03/2011 | PARTIALLY APPROVED | JCOLASANTI |
| Note: Inspection Resulted at 3/3/2011 3:44:25 PM APPROVED CURB AND SIDEWALK ALONG CYPRESS POINT. MARKED AREA APPROVED ON PLANS. INSPECTED SIDEWALK REPAIR THAT WAS REMOVED FOR UTILITY INSTALLATION. | |||
| CONCRETE FORM - SIDEWALK | 03/03/2011 | PARTIALLY APPROVED | JCOLASANTI |
| Note: Inspection Resulted at 3/3/2011 3:44:27 PM INSPECTED 7`` SIDEWALK FORMS NEXT TO CURB BY CYPRESS POINT. SIDEWALK AREA MARKED ON PLANS. | |||
| STMWTR - STRUCTURE/PIPE ATTACHMENT | 12/27/2010 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| STMWTR - STRUCTURE PLACEMENT | 12/27/2010 | APPROVED - AS NOTED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 12/27/2010 3:41:49 PM NEED REVISION FOR ELEVATION OF PIPE INVERT INTO STRUCTURE | |||
| STMWTR - PIPE PLACEMENT | 12/27/2010 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| STMWTR - PIPE PLACEMENT | 12/22/2010 | PARTIALLY APPROVED | CMINI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 12/22/2010 2:59:42 PM DRAINAGE PIPE INSTALLED CIRCLED ON PLAN. | |||
| STMWTR - STRUCTURE PLACEMENT | 12/22/2010 | PARTIALLY APPROVED | CMINI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 12/22/2010 2:59:42 PM PIPE PLACMENT STRUCTURES HIGHLIGHTED ON PLAN. | |||
| STMWTR - STRUCTURE/PIPE ATTACHMENT | 12/22/2010 | PARTIALLY APPROVED | CMINI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 12/22/2010 2:59:43 PM PIPE ATTACHMENT CIRCLED ON PLAN | |||
| STMWTR - STRUCTURE/PIPE ATTACHMENT | 12/20/2010 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 12/20/2010 3:46:40 PM DRAINAGE PIPE BEING ATTACHED TO INLET STRUCTURE #4, 5 AND 6 PER SPECIFICATIONS. | |||
| STMWTR - STRUCTURE PLACEMENT | 12/20/2010 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 12/20/2010 3:46:39 PM CONTRACTOR PLACED INLET #5 AND 6 PER PLANS | |||
| STMWTR - PIPE PLACEMENT | 12/20/2010 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 12/20/2010 3:46:40 PM CONTRACTOR PLACED 80`` OF 18" DRAINAGE PIPE AND 60`` OF 15" PIPE. | |||
| STMWTR - PIPE PLACEMENT | 12/17/2010 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 12/17/2010 3:07:21 PM PLACED 110 LF OF RCP ALONG EAST SIDE OF PROPERTY | |||
| STMWTR - STRUCTURE PLACEMENT | 12/17/2010 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 12/17/2010 3:07:21 PM PLACED TYPE "C" INLET #4 | |||
| STMWTR - STRUCTURE/PIPE ATTACHMENT | 12/17/2010 | PARTIALLY APPROVED | JCOLASANTI |
| STMWTR - STRUCTURE PLACEMENT | 12/16/2010 | PARTIALLY APPROVED | JCOLASANTI |
| Note: Inspection Resulted at 12/16/2010 3:40:54 PM CONTRACTOR PLACED STRUCTURE #2 AND #3. 57 STONE USED FOR BEDDING. | |||
| STMWTR - PIPE PLACEMENT | 12/16/2010 | PARTIALLY APPROVED | JCOLASANTI |
| Note: Inspection Resulted at 12/16/2010 3:40:54 PM INSTALLED 186 LF OF 24" STORM PIPE. FILLED AND COMPACTED TO SPRINGLINE | |||
| STMWTR - STRUCTURE/PIPE ATTACHMENT | 12/16/2010 | PARTIALLY APPROVED | JCOLASANTI |
| Note: Inspection Resulted at 12/16/2010 3:40:55 PM TOLD CONTRACTOR TO APPLY SKIM COAT CONCRETE TO ANY EXPOSED REBAR FROM CUTTING PIPE TO LENGTH TO FIT STRUCTURE | |||
| STMWTR - PIPE PLACEMENT | 12/15/2010 | PARTIALLY APPROVED | JCOLASANTI |
| STMWTR - STRUCTURE PLACEMENT | 12/15/2010 | PARTIALLY APPROVED | JCOLASANTI |
| ENG-TEST- SUBGRADE | 12/02/2010 | PARTIALLY APPROVED | JCOLASANTI |
| Note: Inspection Resulted at 12/2/2010 3:04:23 PM DENSITY TEST PASSED ON FIRST LIFT FOR ON SITE FILL DIRT | |||
| ENG-TEST- SUBGRADE | 11/24/2010 | APPROVED | JCOLASANTI |
| Note: Tom from T-Con called to schedule this inspection Inspection Resulted at 11/24/2010 4:00:57 PM SUBGRADE READY FOR FILL. | |||
| ENG- CLEARING | 11/23/2010 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| ENG- CLEARING | 11/19/2010 | PARTIALLY APPROVED | JCOLASANTI |
| Note: Inspection Resulted at 11/19/2010 3:15:01 PM CONTRACTOR COMPLETED TREE CLEARING, BEGININING GRUBING OF ORGANICS ON SITE | |||
| ENG- CLEARING | 11/18/2010 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 11/18/2010 3:52:17 PM CLEARING OPERATION CONTINUING FOR PROJECT. "TRUCKS ENTERING AND LEAVING HIGHWAY" SIGN HAS BEEN PLACED. | |||
| ENG- CLEARING | 11/17/2010 | PARTIALLY APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 11/17/2010 2:49:50 PM CONTRACTOR CONTINUING WITH CLEARING OPERATION, REMOVING TREES AND GRUBING. INSPECTOR TOLD TOM GC CONTRACTOR TO PLACE "TRUCKS ENTERING AND LEAVING HIGHWAY" SIGN TO ALERT CARS TRAVELING ON CYPRESS PARKWAY ABOUT CONSTRUCTION. | |||
| ENG- CLEARING | 11/16/2010 | PARTIALLY APPROVED | JCOLASANTI |
| Note: Inspection Resulted at 11/16/2010 3:20:38 PM CONTRACTOR STARTING CLEARING OPERATION PER PLANS AND SPECIFICATIONS. ALL TREES TO BE REMOVED PER REVISIED LANDSCAPING PLANS | |||
| ENG -SILT FENCE | 11/15/2010 | PARTIALLY APPROVED | JCOLASANTI |
| Note: Inspection Resulted at 11/15/2010 3:40:59 PM SILT FENCE WILL NEED TO BE MAINTAINED THROUGH OUT CONSTRUCTION. PERIODIC INSPECTIONS WILL BE NEEDED AFTER RAIN EVENTS. | |||
| ENG -CONSTRUCTION ENTRANCE | 11/15/2010 | APPROVED | JCOLASANTI |
| PRE CONSTRUCTION MEETING | 11/05/2010 | APPROVED - AS NOTED | JCOLASANTI |
| Note: MET WITH CONTRACTOR AND EXPLAINED ABOUT HOW THE INSPECTIONS WORK TO CALL IN WHEN NEEDED...BUILDING,FIRE,UTILITY,URBAN FORRESTER AND PUBLIC WORKS WERE PRESENT AT MEETING ON JOB SITE. |
Review History
| Department | Status | Date In | Date Out |
| DSD | COMPLETE | 11/04/2011 | 11/04/2011 |
| UD1 | COMPLETE | 11/04/2011 | 11/15/2011 |
| PLLA | COMPLETE | 11/04/2011 | 11/04/2011 |
| Note: Approved. | |||
| FI1 | COMPLETE | 11/04/2011 | 11/04/2011 |
| ENGIN1 | COMPLETE | 11/04/2011 | 11/04/2011 |
| Note: No Comment | |||
| BLD | COMPLETE | 11/04/2011 | 11/04/2011 |
| ENGIN1 | COMPLETE | 10/26/2011 | 10/28/2011 |
| Note: Released By: JBOSTWICK No Comment | |||
| ENGIN1 | COMPLETE | 06/07/2011 | 06/07/2011 |
| Note: Released by JBostwick | |||
| UD1 | COMPLETE | 06/07/2011 | 06/07/2011 |
| DSD | COMPLETE | 03/23/2011 | 03/28/2011 |
| Note: Does not require environmental review. | |||
| ZON | COMPLETE | 03/23/2011 | 03/28/2011 |
| ENGIN1 | COMPLETE | 03/23/2011 | 03/24/2011 |
| SW1 | COMPLETE | 01/07/2011 | 01/07/2011 |
| Note: Released By: JJOSEPH signed & sealed site plans | |||
| SW1 | HOLD | 12/22/2010 | 12/22/2010 |
| Note: Held By: JJOSEPH Provide signed and sealed Revised Site Plan showing where the change will take place. On offsite storm tie in raise proposed grade from 24.0 to 25.5 ft |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADDITIONAL FEE | ¤40.00 | 11/21/2011 |
| REINSPECTION FEE | ¤40.00 | 11/21/2011 |
| REINSPECTION FEE | ¤40.00 | 11/21/2011 |
| REINSPECTION FEE | ¤40.00 | 11/21/2011 |
| REVISION | ¤40.00 | 11/21/2011 |
| REVISION | ¤40.00 | 11/21/2011 |
| SITE DEVELOPMENT PER ACRE | ¤6,510.00 | 10/29/2010 |
| ADMIN COMMERCIAL | ¤60.00 | 10/29/2010 |
| BUILDING DISCOUNT 100% | (¤54.00) | 10/29/2010 |
| SITE DEVELOPMENT BASE- ENGIN | ¤1,100.00 | 10/29/2010 |
| PERMIT FEE | ¤125.00 | 10/29/2010 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤7,981.00 |