I want to search for...

Permit #2011090556

Permit Details

Status: FINAL

Parcel Id: 07-11-31-7034-00610-0060
Block: 00610
Subdivision: 2165 - SECTION 34-EASTHAMPTON
Job Phone: 386-547-6556
Location Address: 5 ELLIS PL
Type: DR - DRIVEWAY
Issue Date: 10/07/2011
NOC: RECORDED
Applicant name: RAY COPELAND
Owner: HESBEENS WALTER & RITA H&W

Address

5 ELLIS PLACE

PALM COAST, FL 32164

Lot: 0060
Contracted Stated Job Value: ¤4,600.00
Job Description: REPLACE EXSTING CONCRETE DRIVEWAY/WALKWAY WITH BRICK PAVERS
Type: CN

Contractor

ATLANTIC BRICK PAVERS INC
Status Location Address Phone
HOLD

8 SECRETARY TRAIL

PALM COAST, FL 32164

386-547-6556

Inspection History

Type Request Date Result Inspector
STORMWATER FINAL 12/12/2011 APPROVED GLALIMA
Note: THIS IS A REINSPECTION
FINAL APRON (AFTER POUR/DRIVEWAY) 12/12/2011 FINAL APPROVED GLALIMA
U -UTILITY RESIDENTIAL FINAL 12/06/2011 APPROVED JHARDING
FINAL APRON (AFTER POUR/DRIVEWAY) 12/06/2011 CANCELLED BY INSPECTOR GLALIMA
Note: CANCELLED BY GARY BECAUSE OF WORK TO BE PERFORMED IN THE ROW AND CULVERT ENDS.
ROW DAMAGE 12/06/2011 APPROVED GLALIMA
FINAL - BUILDING MISC 12/06/2011 APPROVED RMARVEL
STORMWATER FINAL 12/06/2011 Disapproved -FEE REQUIRED GLALIMA
Note: REMOVE SOD FROM EDGE OF ROAD BACK, THEN REGRADE WITH THE SOD PLACED BELOW ROAD FOR WATER RUN OFF. ALL IS TO BE PLACE AT SAME ELEVATION AS OTHER, SEE PINK PAINT IN DITCH ON RIGHT. FILL IN ALL AROUND CONCRETE "CULVERT" ENDS . IF NEEDED CALL GARY
PRE-APRON (PRE-POUR/DRIVEWAY) 11/18/2011 APPROVED GLALIMA
Note: THIS IS A REINSPECTION
PRE-APRON (PRE-POUR/DRIVEWAY) 11/16/2011 CANCELLED BY APPLICANT GLALIMA

Review History

Department Status Date In Date Out
ZON COMPLETE 10/06/2011 10/06/2011
ENGIN1 COMPLETE 10/04/2011 10/04/2011
ZON HOLD 10/04/2011 10/04/2011
Note: DRamirez Update the first page of the Right of Way Utilization Agreement to include both owners of the property.
ENGIN1 HOLD 09/29/2011 10/03/2011
UD1 COMPLETE 09/29/2011 09/29/2011
ZON HOLD 09/29/2011 09/29/2011
Note: Provide a completed Right of way utilization agreement .
SW1 COMPLETE 09/29/2011 09/29/2011
Note: Released by JJoseph

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 12/09/2011
SITE PLAN 20 ¤20.00 10/07/2011
SURCHARGE FS 533.721 ¤2.00 10/07/2011
SURCHARGE - FS 468.631 ¤2.00 10/07/2011
STORM WATER PERMIT FEES ¤40.00 10/07/2011
BUILDING DISCOUNT 100% (¤18.00) 10/07/2011
PERMIT FEE ¤20.00 10/07/2011
Fees Total Due: ¤0.00 Total Paid: ¤106.00