I want to search for...
Permit #2011090556
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7034-00610-0060 |
| Block: 00610 |
| Subdivision: 2165 - SECTION 34-EASTHAMPTON |
| Job Phone: 386-547-6556 |
| Location Address: 5 ELLIS PL |
| Type: DR - DRIVEWAY |
| Issue Date: 10/07/2011 |
| NOC: RECORDED |
| Applicant name: RAY COPELAND |
| Owner: HESBEENS WALTER & RITA H&W |
|
Address 5 ELLIS PLACE PALM COAST, FL 32164 |
| Lot: 0060 |
| Contracted Stated Job Value: ¤4,600.00 |
| Job Description: REPLACE EXSTING CONCRETE DRIVEWAY/WALKWAY WITH BRICK PAVERS |
| Type: CN |
Contractor
ATLANTIC BRICK PAVERS INC
| Status | Location Address | Phone |
| HOLD |
8 SECRETARY TRAIL PALM COAST, FL 32164 |
386-547-6556 |
Inspection History
| Type | Request Date | Result | Inspector |
| STORMWATER FINAL | 12/12/2011 | APPROVED | GLALIMA |
| Note: THIS IS A REINSPECTION | |||
| FINAL APRON (AFTER POUR/DRIVEWAY) | 12/12/2011 | FINAL APPROVED | GLALIMA |
| U -UTILITY RESIDENTIAL FINAL | 12/06/2011 | APPROVED | JHARDING |
| FINAL APRON (AFTER POUR/DRIVEWAY) | 12/06/2011 | CANCELLED BY INSPECTOR | GLALIMA |
| Note: CANCELLED BY GARY BECAUSE OF WORK TO BE PERFORMED IN THE ROW AND CULVERT ENDS. | |||
| ROW DAMAGE | 12/06/2011 | APPROVED | GLALIMA |
| FINAL - BUILDING MISC | 12/06/2011 | APPROVED | RMARVEL |
| STORMWATER FINAL | 12/06/2011 | Disapproved -FEE REQUIRED | GLALIMA |
| Note: REMOVE SOD FROM EDGE OF ROAD BACK, THEN REGRADE WITH THE SOD PLACED BELOW ROAD FOR WATER RUN OFF. ALL IS TO BE PLACE AT SAME ELEVATION AS OTHER, SEE PINK PAINT IN DITCH ON RIGHT. FILL IN ALL AROUND CONCRETE "CULVERT" ENDS . IF NEEDED CALL GARY | |||
| PRE-APRON (PRE-POUR/DRIVEWAY) | 11/18/2011 | APPROVED | GLALIMA |
| Note: THIS IS A REINSPECTION | |||
| PRE-APRON (PRE-POUR/DRIVEWAY) | 11/16/2011 | CANCELLED BY APPLICANT | GLALIMA |
Review History
| Department | Status | Date In | Date Out |
| ZON | COMPLETE | 10/06/2011 | 10/06/2011 |
| ENGIN1 | COMPLETE | 10/04/2011 | 10/04/2011 |
| ZON | HOLD | 10/04/2011 | 10/04/2011 |
| Note: DRamirez Update the first page of the Right of Way Utilization Agreement to include both owners of the property. | |||
| ENGIN1 | HOLD | 09/29/2011 | 10/03/2011 |
| UD1 | COMPLETE | 09/29/2011 | 09/29/2011 |
| ZON | HOLD | 09/29/2011 | 09/29/2011 |
| Note: Provide a completed Right of way utilization agreement . | |||
| SW1 | COMPLETE | 09/29/2011 | 09/29/2011 |
| Note: Released by JJoseph |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 12/09/2011 |
| SITE PLAN 20 | ¤20.00 | 10/07/2011 |
| SURCHARGE FS 533.721 | ¤2.00 | 10/07/2011 |
| SURCHARGE - FS 468.631 | ¤2.00 | 10/07/2011 |
| STORM WATER PERMIT FEES | ¤40.00 | 10/07/2011 |
| BUILDING DISCOUNT 100% | (¤18.00) | 10/07/2011 |
| PERMIT FEE | ¤20.00 | 10/07/2011 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤106.00 |