I want to search for...
Permit #2012020186
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7021-00150-0050 |
| Block: 00150 |
| Subdivision: 2186 - SECTION 21-WYNNFIELD |
| Job Phone: (386)447-7077 |
| Location Address: 149 WELLSTONE DR |
| Type: DR - DRIVEWAY |
| Issue Date: 02/08/2012 |
| NOC: Unknown |
| Applicant name: MARK M SCHOFIELD |
| Owner: ADAMS CHARLES J & LOUISE BUBSER |
|
Address 7 BRISTOL DRIVE PALM COAST, FL 32164 |
| Lot: 0050 |
| Contracted Stated Job Value: ¤1,500.00 |
| Job Description: REMOVE & REPLACE DRIVEWAY & SIDEWALK ADDITION- REF # 2011060058 |
| Type: CN |
Contractor
STAY HARD CONCRETE LLC
| Status | Location Address | Phone |
| CANCEL |
52 LEE DRIVE PALM COAST, FL 32137 |
(386)447-7077 |
Inspection History
| Type | Request Date | Result | Inspector |
| FINAL APRON (AFTER POUR/DRIVEWAY) | 07/20/2012 | FINAL APPROVED | KHOWELL |
| Note: THIS IS A REINSPECTION requested by contractor | |||
| PRE-APRON (PRE-POUR/DRIVEWAY) | 07/17/2012 | APPROVED - AS NOTED | GLALIMA |
| Note: THIS IS A REINSPECTION THIS IS A DRIVEWAY THAT WAS POURED WITH NO INSPECTION OR PERMIT. THE CONCRETE THAT DID NOT MEET THE CITY OF PALM COAST CODOF SEC. 42 - 42 OF RIGHT OF WAY UTILIZATION. CONCRETE HAS BEEN REMOVED . NEW INSPECTION FOR 7 / 17 / 2012 PASSED READY TO POUR. | |||
| PRE-APRON (PRE-POUR/DRIVEWAY) | 04/17/2012 | Disapproved - NO FEE | GLALIMA |
| Note: THIS IS A REINSPECTION requested by contractor ON SITE MEET WITH OWNER OF STAY HARD CONCRETE BUILDING INSPECTOR ' CHARLIE MIMI GARY LALIMA R.O.W INSPCTOR . 10 : 44 A:M . DRIVEWAY WAS INSTALLED WITH OUT A PERMIT OR A PRE-POUR CONCRETE INSPECTION , CORE THICKNESS WAS PERFORMED BY UNIVERSAL ENGINEERING SCIENCES , CORE THICKNESS CAME BACK FAILED AT 4 1/4 " UNDER DRIVEWAYS SEC. 42-42 5' MIN FIBER MESH CONCRETE. OR 6" WITH OUT. REMOVE AND REPLACE CONCRETE FROM TOP OF CULVERT PIPE BACK TO FRIST SAW CUT. 9 ' X 16 ' IN DRIVEWAY. | |||
| U -UTILITY RESIDENTIAL FINAL | 02/10/2012 | APPROVED | KKING |
| FINAL APRON (AFTER POUR/DRIVEWAY) | 02/10/2012 | Disapproved -FEE REQUIRED | GLALIMA |
| Note: AS PER PRE-INSPECTION AND FINAL DRIVEWAY INSPECTION . MUST HAVE THIRD PARTY CORE TEST ON DRIVEWAY CONCRETE 11' FEET OFF ROAD. IN THE RIGHT OF WAY SEE PINK PAINT. MUST HAVE 5" OF 3,000 PSI. IN CITY RIGHT CALL INSPECTOR IF NEEDED. | |||
| FINAL - BUILDING MISC | 02/10/2012 | APPROVED | CMINI |
| ROW DAMAGE | 02/10/2012 | APPROVED | GLALIMA |
| Note: THIS IS A REINSPECTION NO ROAD DAMAGE OR SWALE DAMAGE | |||
| PRE-APRON (PRE-POUR/DRIVEWAY) | 02/10/2012 | Disapproved - NO FEE | GLALIMA |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| BUILDING DISCOUNT 100% | (¤18.00) | 02/08/2012 |
| PERMIT FEE | ¤20.00 | 02/08/2012 |
| SURCHARGE FS 533.721 | ¤2.00 | 02/08/2012 |
| SURCHARGE - FS 468.631 | ¤2.00 | 02/08/2012 |
| STORM WATER PERMIT FEES | ¤40.00 | 02/08/2012 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤46.00 |