I want to search for...
Permit #2013040247
Permit Details
Status: COED
| Parcel Id: 07-11-31-7009-00250-0230 |
| CONDITIONED SPACE: 2157 sqft |
| GARAGE: 550 sqft |
| SCREEN PORCH (SOLID ROOF) : 236 sqft |
| SCREEN PORCH (SOLID ROOF) : 67 sqft |
| Total Square Footage: 3010 sqft |
| Block: 00250 |
| Subdivision: 2208 - SECTION 9-FLORIDA PARK |
| Job Phone: (386)446-5161 |
| Location Address: 25 FALLON LN |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 04/22/2013 |
| NOC: RECORDED |
| Applicant name: HUGO A CAMACHO |
| Owner: SCHMIDT, ROBERT C JR & ROSA M |
|
Address 380 GERRY ROAD NORTH BRUSNWICK, NJ 08902 |
| Lot: 0230 |
| Contracted Stated Job Value: ¤220,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
IDEAL HOMES AT PALM COAST, INC.
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
PO BOX 353639 PALM COAST, FL 32137 |
CBC1250774 (Exp: 08/31/2026) | (386)446-5161 | (386)447-0238 |
Sub Contractors
WILLIAM FRANK DUDLEY JR.
| Status | Location Address | State License Number | Phone |
| ACTIVE |
P.O. BOX 978 Bunnell, FL 32110 |
EC0003177 (Exp: 08/31/2026) | (386)437-3068 |
PAUL S AIELLO
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
PO BOX 351926 PALM COAST, FL 32137 |
CAC1815808 (Exp: 08/31/2016) | (386)239-0053 | (386)323-1955 |
GLEN WILLIAM KEHLE
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
P. O. Box 353511 BUNNELL, FL 32110 |
CFC057241 (Exp: 08/31/2026) | (386) 447-4249 | (386) 437-8488 |
HUGO A CAMACHO
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
PO BOX 353639 PALM COAST, FL 32137 |
CCC1326139 (Exp: 08/31/2026) | (386)446-5161 | (386)447-0238 |
Inspection History
| Type | Request Date | Result | Inspector |
| U -UTILITY RESIDENTIAL FINAL | 01/24/2014 | FINAL APPROVED | DSPENCER |
| BLD - BUILDING FINAL | 01/23/2014 | FINAL APPROVED | CMINI |
| FINAL APRON (AFTER POUR/DRIVEWAY) | 01/06/2014 | APPROVED | RGROSS |
| ROW FINAL | 01/06/2014 | FINAL APPROVED | RGROSS |
| FINAL SURVEY (OFFICE USE ONLY) | 12/18/2013 | APPROVED | JMCGOWEN |
| ELECTRIC - EARLY POWER | 11/12/2013 | APPROVED | DROCKWELL |
| PRE-APRON (PRE-POUR/DRIVEWAY) | 11/05/2013 | APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION | |||
| PRE-APRON (PRE-POUR/DRIVEWAY) | 10/30/2013 | Disapproved -FEE REQUIRED | RGROSS |
| Note: Not formed according to the Approved Survey. Survey shows a 3' ft sidewalk to house entryway. Formed out to a 6' sidewalk. Must be reformed to current approved survey or new survey showing 6' sidewalk must be obtained. This is a circular driveway. Pipe EL. was good at this point, but as always, builder should recheck pipe EL. if time elapses while waiting on a new survey. | |||
| GRAVITY SEWER TEST | 10/15/2013 | APPROVED | CMINI |
| U - SEWER TIE IN | 10/15/2013 | APPROVED | DSPENCER |
| INSULATION | 08/06/2013 | APPROVED - AS NOTED | DROCKWELL |
| Note: Inspection Resulted at 8/6/2013 2:35:17 PM REQUESTED REVISION PROVIDED.....INSULATION OK | |||
| LATH/BRICK/ WATER BARRIER | 07/24/2013 | APPROVED | CMINI |
| ALL ROUGH | 07/22/2013 | APPROVED - AS NOTED | CMINI |
| Note: Inspection Resulted at 7/22/2013 3:18:29 PM NEED REVISION FOR ADDED OUTLETS NOTED ON PLAN,ADD NAIL PLATES NOTED ON PLAN,CHECK ON INSULATION | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 07/09/2013 | APPROVED | DROCKWELL |
| WALL SHEATHING | 06/27/2013 | APPROVED | DROCKWELL |
| ELECTRIC-TUG | 06/17/2013 | APPROVED | DROCKWELL |
| TIE BEAM / LINTEL | 05/22/2013 | APPROVED | DROCKWELL |
| Note: requested by hugo | |||
| FOUND SURVEY APPROVED (OFFICE) | 05/21/2013 | APPROVED | FREODICA |
| MONOLITHIC SLAB | 05/13/2013 | APPROVED - AS NOTED | DROCKWELL |
| Note: Inspection Resulted at 5/13/2013 11:49:40 AM CHECK STEEL IN GARAGE-SOME AREA``S HAVE NO CLEARANCE.NEED 2IN ALL AROUND STEEL FOR CONCRETE. | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 05/09/2013 | APPROVED | DROCKWELL |
| Note: THIS IS A REINSPECTION | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 05/08/2013 | Disapproved -FEE REQUIRED | DROCKWELL |
| Note: Inspection Resulted at 5/8/2013 12:23:07 PM MASTER BATH TOILET WASTE LINE DOES NOT MEET SLOPE REQUIREMENTS AS PER FBC-PLUMBING 704.1 |
Review History
| Department | Status | Date In | Date Out |
| SW1 | COMPLETE | 12/17/2013 | 12/18/2013 |
| Note: Released By: JMCGOWEN FINAL | |||
| BLD | COMPLETE | 10/30/2013 | 10/30/2013 |
| Note: n/a | |||
| ENGIN1 | COMPLETE | 10/30/2013 | 10/31/2013 |
| SW1 | COMPLETE | 10/30/2013 | 10/30/2013 |
| UD1 | COMPLETE | 10/30/2013 | 10/31/2013 |
| ZON | COMPLETE | 10/30/2013 | 11/04/2013 |
| ELEC | COMPLETE | 08/02/2013 | 08/02/2013 |
| BLD | COMPLETE | 06/28/2013 | 07/01/2013 |
| SW1 | COMPLETE | 05/21/2013 | 05/21/2013 |
| Note: Released By: FREODICA foundation survey | |||
| ZON | COMPLETE | 05/21/2013 | 05/21/2013 |
| Note: Released By: FREODICA foundtaion survey | |||
| BLD | COMPLETE | 05/17/2013 | 05/17/2013 |
| Note: Revision - added window in bathroom at rear of house | |||
| ELEC | COMPLETE | 04/19/2013 | 04/19/2013 |
| MECH | COMPLETE | 04/19/2013 | 04/19/2013 |
| BLD | COMPLETE | 04/12/2013 | 04/15/2013 |
| PLUM | COMPLETE | 04/12/2013 | 04/15/2013 |
| MECH | HOLD | 04/12/2013 | 04/15/2013 |
| Note: Title block information on hvac plan with a license number and company name of hvac contractor which is shown on floor plan signed and sealed by an engineer shall be deleted per 2010 FBC 107.1. | |||
| ELEC | HOLD | 04/12/2013 | 04/15/2013 |
| Note: Revise entrance conductor sizes to meet NEC T310.15 B C revise receptacle locations to meet NEC 210.52 | |||
| BLD | HOLD | 04/08/2013 | 04/09/2013 |
| Note: 1. Provide lintel details for bedroom 2. 2010 FBC R606.10. 2. Provide for hazardous location glazing per 2010 FBC R308.4. 3. Provide typical stair framing details 2010 FBC R311.7. | |||
| ELEC | HOLD | 04/08/2013 | 04/09/2013 |
| Note: Revise receptacle locations to meet NEC 210.52 provide an additional CO/smoke detector at bottom of stairs from bonus room FRBC R314 provide service entrance conductor sizes on riser detail NEC230 | |||
| ENGIN1 | COMPLETE | 04/08/2013 | 04/12/2013 |
| MECH | HOLD | 04/08/2013 | 04/09/2013 |
| Note: There are 2 mechanical duct layout submitted. Clarify which one to be used per 2010 FBC 107.1. If the stand alone plan prepared by hvac contractor would be used, provide license number on the plan and delete the one shown on floor plan. However, if mechanical duct layout shown on floor plan would be used, delete the signature the hvac contractor. | |||
| PLUM | HOLD | 04/08/2013 | 04/09/2013 |
| Note: 1. Sanitary riser diagram with license number and signature of plumbing contractor shall not be in the same plan signed and sealed by an engineer per 2010 FBC 107.1. 2. Provide pipe sizes of master bathroom branch line tie-in connection to main sanitary line, summer kitchen tie-in connection to shower and wet-vented lavatory per 2010 FBC 107.2.1. | |||
| SW1 | COMPLETE | 04/08/2013 | 04/09/2013 |
| UD1 | COMPLETE | 04/08/2013 | 04/09/2013 |
| URB | COMPLETE | 04/08/2013 | 04/09/2013 |
| ZON | COMPLETE | 04/08/2013 | 04/11/2013 |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REVISION | ¤40.00 | 01/27/2014 |
| REVISION | ¤40.00 | 01/27/2014 |
| REVISION | ¤40.00 | 01/27/2014 |
| REINSPECTION FEE | ¤40.00 | 01/27/2014 |
| REINSPECTION FEE | ¤40.00 | 01/27/2014 |
| NEW RESIDENTIAL INSPECTIONS | ¤526.00 | 04/22/2013 |
| SITE PLAN 20 | ¤20.00 | 04/22/2013 |
| SURCHARGE FS 533.721 | ¤19.57 | 04/22/2013 |
| SURCHARGE - FS 468.631 | ¤19.57 | 04/22/2013 |
| STORM WATER PERMIT FEES | ¤80.00 | 04/22/2013 |
| 3% TRANS IMPACT FEE CREDIT | (¤90.51) | 04/22/2013 |
| ADMIN FEE | ¤20.00 | 04/22/2013 |
| ELECTRIC FEE | ¤217.80 | 04/22/2013 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.24) | 04/22/2013 |
| IMPACT FEE FIRE NONRESIDENTIAL | ¤207.99 | 04/22/2013 |
| IMPACT FEE PARKS | ¤1,343.98 | 04/22/2013 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 04/22/2013 |
| IMPACT FEE TRANSPORTATION | ¤3,017.05 | 04/22/2013 |
| MECHANICAL FEE | ¤217.80 | 04/22/2013 |
| 3% PARKS IMPACT FEE CREDIT | (¤40.32) | 04/22/2013 |
| PLAN CHECK FEE | ¤105.20 | 04/22/2013 |
| PLUMBING FEE | ¤217.80 | 04/22/2013 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤9,675.69 |