I want to search for...

Permit #2013110222

Permit Details

Status: COED

Parcel Id: 16-11-31-1260-00000-0320
CONDITIONED SPACE: 2040 sqft
GARAGE: 426 sqft
OPENED PORCH (WITH ROOF) : 191 sqft
PATIO/DECK (NO ROOF) : 70 sqft
Total Square Footage: 2727 sqft
Block: 00000
Subdivision: 2081 - Creekside Village at Grand Haven
Job Phone: 386-947-4481
Location Address: 45 CREEKSIDE DR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 11/26/2013
NOC: RECORDED
Applicant name: ERIC CHRISTOPHER OLSEN
Owner: MIKITA JOSEPH E & VICTORIA H&W

Address

14 PINE HARBOR DR

PALM COAST, FL 32137

Lot: 0320
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

OLSEN CUSTOM HOMES AND CONSULTING INC
Status Location Address State License Number Phone Fax
ACTIVE

131 MAGNOLIA AVE

DAYTONA BEACH, FL 32114

CGC1508852 (Exp: 08/31/2026) 386-947-4481 (386)947-4484

Sub Contractors

BENJAMIN EDWARD SMITH
Status Location Address State License Number Phone
CANCEL

131 MAGNOLIA AVE

DAYTONA BEACH, FL 32114

EC13004288 (Exp: 08/31/2016) 386-265-2687
DANIEL P HUCKS
Status Location Address State License Number Phone Fax
CANCEL

400 N. U.S. 1

Ormond Beach, FL 32174

CAC029376 (Exp: 08/31/2024) 386-672-8494 386-673-7856
JOHN BRADLEY WINFREY JR
Status Location Address State License Number Phone Fax
ACTIVE

1685 S. CLARA AVE

Deland, FL 32720

CFC054901 (Exp: 08/31/2026) 386-734-0154 386-734-2751
JACK DOUGLAS LANIER
Status Location Address State License Number Phone Fax
ACTIVE

485 COMMERCE WAY

LONGWOOD , FL 32750

CCC058022 (Exp: 08/31/2026) (321)441-2300 (321)441-2313

Inspection History

Type Request Date Result Inspector
U -UTILITY RESIDENTIAL FINAL 06/06/2014 FINAL APPROVED DSPENCER
U - SEWER TIE IN 06/05/2014 APPROVED DSPENCER
Note: THIS IS A REINSPECTION
BLD - BUILDING FINAL 06/05/2014 FINAL APPROVED CMINI
Note: aproved by Mike Navarra
BLD - BUILDING FINAL 06/04/2014 Disapproved -FEE REQUIRED CMINI
Note: Inspection Resulted at 6/4/2014 3:21:37 PM DISCONNECTING MEANS WITH IN SIGHT OF AND READILY ACCESSIBLE ..NEC 440.14....ALL OPEN ROOF VENTS WHICH EXTEND THROUGH A ROOF SHALL BE TERMINATED AT 6" ABOVE THE ROOF..FBC P3103.1
FINAL APRON (AFTER POUR/DRIVEWAY) 06/04/2014 APPROVED RGROSS
ROW FINAL 06/04/2014 APPROVED RGROSS
U - SEWER TIE IN 06/04/2014 Disapproved -FEE REQUIRED DSPENCER
Note: THIS IS A REINSPECTION Inspection Resulted at 6/4/2014 11:40:18 AM CONNECTED BURIED MUST BE UNCOVERED AND INSPEDCTED FROM 6" X4" REDUCER TO TOP 45 BEND CALL FOR VISUAL INSPECTION
FINAL SURVEY (OFFICE USE ONLY) 06/03/2014 APPROVED FREODICA
PRE-APRON (PRE-POUR/DRIVEWAY) 05/12/2014 APPROVED GLALIMA
Note: 2 PART POUR READY FOR PAVERS
PRE-APRON (PRE-POUR/DRIVEWAY) 04/25/2014 PARTIALLY APPROVED GLALIMA
ELECTRIC - EARLY POWER 04/25/2014 APPROVED - AS NOTED CMINI
Note: Inspection Resulted at 4/25/2014 3:56:37 PM ALLREADY APPROVED YESTURDAY
ELECTRIC - EARLY POWER 04/24/2014 APPROVED - AS NOTED CMINI
Note: Inspection Resulted at 4/24/2014 3:03:37 PM CALLED FPL TO RELEASE POWER AT 2:00,SPOKE WITH SUSAN
GRAVITY SEWER TEST 04/16/2014 AUDIT - PRIVATE PROVIDER INSPECTION CMINI
Note: Inspection Resulted at 4/16/2014 3:17:08 PM OK
LATH/BRICK/ WATER BARRIER 03/25/2014 AUDIT - PRIVATE PROVIDER INSPECTION CMINI
Note: Inspection Resulted at 3/25/2014 3:20:22 PM OK approved by Robert Waldrop
INSULATION 03/19/2014 APPROVED CMINI
Note: approved by Mike Navarra
ROOF SHEATHING / BRACES/TIES/DOWN CELL 03/18/2014 APPROVED - AS NOTED CMINI
Note: THIS IS A REINSPECTION..corrections made approved by Mike Navarra
ALL ROUGH 03/18/2014 APPROVED - AS NOTED CMINI
Note: 5' head needed pressure..strap dryer vent every 4'..add required recptacle in hall way ..ground metal enclosure .. approved by Mike Navarra
FRAMING 03/18/2014 AUDIT - PRIVATE PROVIDER INSPECTION CMINI
ROOF SHEATHING / BRACES/TIES/DOWN CELL 02/18/2014 Disapproved -FEE REQUIRED DROCKWELL
Note: Inspection Resulted at 2/18/2014 2:56:49 PM ROOF METALS NOT INSTALLED AS REQUIRED/PROVIDE SOLID BLOCKING AT HIP-PLYWOOD CANNOT EXCEED 24IN W/GRAIN/REMOVE SHINNERS SAME AREA/MISSING STRAP ON GIRDER G1G/TRUSS H5C NOT STRAPPED AT BEARING POINT/GABLE END NOT BRACED-PROVIDE APPROVED DETAIL NOT IN PLAN/INTERIOR BEARING WALL SHOWS 2X10 HEADERS-NOT 2X8/SAME HEADERS NOT STRAPPED PER PLAN DETAIL/TRUSS ENGINEERING NOT ON SITE/INCOMPLETE INSPECTION. roof sheathing approved by Mike Navarra
ELECTRIC-TUG 02/12/2014 APPROVED - AS NOTED CMINI
Note: Inspection Resulted at 2/12/2014 3:06:10 PM CALLED FPL TO RELEASE POWER AT 1:15 PM,SPOKE WITH KAREN
TIE BEAM / LINTEL 02/04/2014 AUDIT - PRIVATE PROVIDER INSPECTION DROCKWELL
Note: Inspection Resulted at 2/4/2014 3:03:14 PM APPROVED LINTEL INSPECTION approved by Mike Navarra
FOUND SURVEY APPROVED (OFFICE) 01/29/2014 APPROVED FREODICA
MONOLITHIC SLAB 01/23/2014 APPROVED - AS NOTED CMINI
Note: THIS IS A REINSPECTION Inspection Resulted at 1/23/2014 3:01:45 PM CORRECTIONS MADE
MONOLITHIC SLAB 01/21/2014 Disapproved -FEE REQUIRED CMINI
Note: Inspection Resulted at 1/21/2014 1:30:02 PM PLAN SHOWS BELL FOOTERS ON DETAIL (B) AND (H). NEEDS CORRECTION..MISSING UFER..NEC..250.52(3)...RELIEVING ARCH IN FOOTING NEEDED OVER PIPES. P2603.5 approved by Robert Waldrop BN 4320 on 1/20/14
PLUMBING 1ST ROUGH UNDERGROUND 01/15/2014 APPROVED CMINI
Note: THIS IS A REINSPECTION
PLUMBING 1ST ROUGH UNDERGROUND 01/14/2014 Disapproved -FEE REQUIRED CMINI
Note: THIS IS A REINSPECTION Inspection Resulted at 1/14/2014 2:47:22 PM PROVIDE 5FT HEAD PRESSURE ON SANITARY.FBC 312
U - SEWER TIE IN 01/10/2014 PARTIALLY APPROVED DSPENCER
Note: THIS IS A REINSPECTION Inspection Resulted at 1/10/2014 10:49:03 AM BOTTOM IS CONNECTED CORRECTLY TOP IS NOT COMPLETED RECALL INSPECTION WHEN COMPLETED FOR APPROVAL OF TIE IN INSPECTION
U - SEWER TIE IN 12/31/2013 Disapproved -FEE REQUIRED DSPENCER
Note: THIS IS A REINSPECTION Inspection Resulted at 12/31/2013 2:11:55 PM NOT TIED IN.GRAVITY SEWER, THE SEWER TIE-IN INSPECTION MUST BE CALLED IN THE DAY BEFORE THE TIE-IN. THE MORNING OF THE TIE-IN THE INSPECTOR MUST BE CONTACTED TO COORDINATE THE TIME OF THE TIE-IN SO HE CAN WITNESS THE TIE-IN. SEE COMMENT IN GENERAL NOTES DANNY SPENCER 386-569-9082
U - SEWER TIE IN 12/30/2013 Disapproved -FEE REQUIRED DSPENCER
Note: Inspection Resulted at 12/30/2013 2:06:37 PM CONNECTION HAS NOT BEEN MADE. CALL IN PERMIT CODE FOR INSPECTION THE DAY BEFORE WORK IS SCHEDULED TO BE DONE AND ON THE DAY WORK IS BEING DONE COORDINATE IN THE AM.WITH THE UTILITIES FOR A TIME TO BE INSPECTED AT 386-569-9082
PLUMBING 1ST ROUGH UNDERGROUND 12/27/2013 Disapproved - NO FEE RMARVEL
Note: Inspection Resulted at 12/27/2013 2:28:02 PM PLUMBING RISER DOES NOT MATCH CITY STAMPED APPROVED PLANS. PROVIDE 5FT HEAD PRESSURE ON SANITARY. approved by Mike Navarra report on file

Review History

Department Status Date In Date Out
BLD COMPLETE 06/06/2014 06/06/2014
Note: Engineer's letter from Universal Engineering Sciences dated 6-5-2014 re. final inspection of the project.
SW1 COMPLETE 06/03/2014 06/03/2014
Note: Released By: FREODICA final s
SW1 COMPLETE 01/29/2014 01/29/2014
Note: Released By: FREODICA foundation survey
ZON COMPLETE 01/08/2014 01/09/2014
PLUM COMPLETE 01/08/2014 01/08/2014
Note: NA
BLD COMPLETE 12/26/2013 12/27/2013
SW1 COMPLETE 12/26/2013 12/27/2013
ZON HOLD 12/26/2013 12/27/2013
Note: revise site plan to show patio addition and correct house floor plan
MECH COMPLETE 11/25/2013 11/26/2013
ZON COMPLETE 11/25/2013 11/26/2013
BLD COMPLETE 11/12/2013 11/14/2013
ELEC COMPLETE 11/12/2013 11/12/2013
ENGIN1 COMPLETE 11/12/2013 11/13/2013
Note: No swale plan required.
MECH HOLD 11/12/2013 11/12/2013
Note: 1. Directional orientation of the building shown on energy calculation does not match with the orientation shown on site plan. Coordinate and revise to complty with 2010 FBC 107.2.1. 2. Florida room is classified as habitable space and requires heating and/or cooling per 2010 FBC R 301.2.1.1.2. Revise hvac plan to include that space to be ventilated.
PLUM COMPLETE 11/12/2013 11/12/2013
SW1 COMPLETE 11/12/2013 11/12/2013
UD1 COMPLETE 11/12/2013 11/12/2013
Note: See comments in the general notes Keith King 386-9318009
URB COMPLETE 11/12/2013 11/13/2013
ZON COMPLETE 11/12/2013 11/15/2013

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 06/06/2014
REINSPECTION FEE ¤40.00 06/06/2014
REINSPECTION FEE ¤40.00 06/06/2014
REINSPECTION FEE ¤40.00 06/06/2014
REINSPECTION FEE ¤40.00 06/06/2014
REINSPECTION FEE ¤40.00 06/06/2014
REINSPECTION FEE ¤40.00 06/06/2014
NEW RESIDENTIAL INSPECTIONS ¤508.00 11/26/2013
SITE PLAN 20 ¤20.00 11/26/2013
SURCHARGE FS 533.721 ¤19.00 11/26/2013
SURCHARGE - FS 468.631 ¤19.00 11/26/2013
STORM WATER PERMIT FEES ¤80.00 11/26/2013
3% TRANS IMPACT FEE CREDIT (¤90.51) 11/26/2013
ADMIN FEE ¤20.00 11/26/2013
ELECTRIC FEE ¤212.40 11/26/2013
3% FIRE IMPACT FEE CREDIT (¤6.24) 11/26/2013
IMPACT FEE FIRE NONRESIDENTIAL ¤207.99 11/26/2013
IMPACT FEE PARKS ¤1,343.98 11/26/2013
IMPACT FEE SCHOOL ¤3,600.00 11/26/2013
IMPACT FEE TRANSPORTATION ¤3,017.05 11/26/2013
MECHANICAL FEE ¤212.40 11/26/2013
3% PARKS IMPACT FEE CREDIT (¤40.32) 11/26/2013
PLAN CHECK FEE ¤101.60 11/26/2013
PLUMBING FEE ¤212.40 11/26/2013
Fees Total Due: ¤0.00 Total Paid: ¤9,716.75