I want to search for...
Permit #2014080215
Permit Details
Status: COED
| Parcel Id: 15-11-31-2970-00000-0940 |
| CONDITIONED SPACE: 2924 sqft |
| GARAGE: 763 sqft |
| OPENED PORCH (WITH ROOF) : 442 sqft |
| OPENED PORCH (WITH ROOF) : 81 sqft |
| Total Square Footage: 4210 sqft |
| Block: 00000 |
| Subdivision: 2070 - Grand Haven North Phase 1 @ Grand Haven |
| Job Phone: 386-947-4481 |
| Location Address: 55 NORTH PARK CIR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 09/09/2014 |
| NOC: RECORDED |
| Applicant name: ERIC CHRISTOPHER OLSEN |
| Owner: DECARLO, PAUL A |
|
Address 59 NORTH PARK CIRCLE PALM COAST, FL 32137 |
| Lot: 0940 |
| Contracted Stated Job Value: ¤350,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
OLSEN CUSTOM HOMES AND CONSULTING INC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
131 MAGNOLIA AVE DAYTONA BEACH, FL 32114 |
CGC1508852 (Exp: 08/31/2026) | 386-947-4481 | (386)947-4484 |
Sub Contractors
BENJAMIN EDWARD SMITH
| Status | Location Address | State License Number | Phone |
| CANCEL |
131 MAGNOLIA AVE DAYTONA BEACH, FL 32114 |
EC13004288 (Exp: 08/31/2016) | 386-265-2687 |
DANIEL P HUCKS
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
400 N. U.S. 1 Ormond Beach, FL 32174 |
CAC029376 (Exp: 08/31/2024) | 386-672-8494 | 386-673-7856 |
JOHN BRADLEY WINFREY JR
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
1685 S. CLARA AVE Deland, FL 32720 |
CFC054901 (Exp: 08/31/2026) | 386-734-0154 | 386-734-2751 |
ALFRED N FYOCK JR
| Status | Location Address | Mailing Address | State License Number | Phone | Fax |
| ACTIVE |
387 SAULS ORMOND BEACH, FL 32174 |
ST ORMOND BEACH, FL 32174 |
CCC1329075 (Exp: 08/31/2026) | 386-566-6112 | 386-673-4299 |
Inspection History
| Type | Request Date | Result | Inspector |
| U -UTILITY RESIDENTIAL FINAL | 02/25/2015 | FINAL APPROVED | DSPENCER |
| BLD - BUILDING FINAL | 02/24/2015 | FINAL APPROVED | CMINI |
| FINAL SURVEY (OFFICE USE ONLY) | 02/23/2015 | APPROVED | JHINDMAN |
| ROW FINAL | 02/23/2015 | FINAL APPROVED | GLALIMA |
| Note: THIS IS A REINSPECTION | |||
| FINAL APRON (AFTER POUR/DRIVEWAY) | 02/20/2015 | APPROVED | GLALIMA |
| ROW FINAL | 02/20/2015 | Disapproved - NO FEE | GLALIMA |
| Note: NEED TO GET WITH CONTRACTOR ABOUT CLEANING UP AT BASIN '' O AND IN BASIN | |||
| PRE-APRON (PRE-POUR/DRIVEWAY) | 01/27/2015 | APPROVED | GLALIMA |
| Note: THIS IS A REINSPECTION | |||
| ELECTRIC - EARLY POWER | 01/22/2015 | APPROVED - AS NOTED | CMINI |
| Note: Inspection Resulted at 1/22/2015 1:52:52 PM CALLED FPL TO RELEASE POWER AT 2PM,SPOKE WITH DELL | |||
| PRE-APRON (PRE-POUR/DRIVEWAY) | 01/22/2015 | PARTIALLY APPROVED | GLALIMA |
| U - SEWER TIE IN | 12/08/2014 | APPROVED | DSPENCER |
| Note: THIS IS A REINSPECTION | |||
| U - SEWER TIE IN | 12/05/2014 | APPROVED | DSPENCER |
| Note: Inspection Resulted at 12/5/2014 3:00:05 PM FOUND CONNECTION BURIED NO CALL WAS RECIEVED TO SCHEDULE A TIME FOR THE VISUAL INSPECTION | |||
| INSULATION | 12/05/2014 | APPROVED | CMINI |
| LATH/BRICK/ WATER BARRIER | 12/05/2014 | APPROVED | CMINI |
| GRAVITY SEWER TEST | 12/05/2014 | APPROVED | CMINI |
| Note: THIS IS A REINSPECTION | |||
| GRAVITY SEWER TEST | 12/04/2014 | Disapproved -FEE REQUIRED | CMINI |
| Note: THIS IS A REINSPECTION Inspection Resulted at 12/4/2014 11:32:56 AM NO WATER PRESSURE ON GRAVITY SEWER PIPE | |||
| GRAVITY SEWER TEST | 12/02/2014 | CANCELLED BY APPLICANT | CMINI |
| ALL ROUGH | 12/02/2014 | APPROVED | CMINI |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 12/02/2014 | APPROVED | CMINI |
| Note: THIS IS A REINSPECTION | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 11/07/2014 | Disapproved -FEE REQUIRED | JCOLASANTI |
| Note: Inspection Resulted at 11/7/2014 3:12:59 PM NOT READY, CONTINUES LOAD PATH NEEDS TO BE ACHIEVED AT VARIOUS LOCATIONS. STRAPS NEED TO BE NAILED VARIOUS LOCATIONS. STRAPS NEED TO BE PLACED AT LOAD HEADERS. SHEETING NEEDS TO BE REMOVED AT ENTRY FOR INSPECTION. BOLT DOWN ALL LOAD BEARING KNEEWALLS. | |||
| ELECTRIC-TUG | 11/04/2014 | APPROVED - AS NOTED | CMINI |
| Note: Inspection Resulted at 11/4/2014 2:54:00 PM CALLED FPL TO RELEASE POWER AT 3:00 SPOKE WITH SUSAN | |||
| TIE BEAM / LINTEL | 10/14/2014 | APPROVED | CMINI |
| FOUND SURVEY APPROVED (OFFICE) | 10/13/2014 | APPROVED | JHINDMAN |
| MONOLITHIC SLAB | 09/22/2014 | APPROVED | CMINI |
| PLUMBING 1ST ROUGH UNDERGROUND | 09/16/2014 | APPROVED | CMINI |
| U - SEWER TIE IN | 09/16/2014 | APPROVED | DSPENCER |
Review History
| Department | Status | Date In | Date Out |
| SW1 | COMPLETE | 02/23/2015 | 02/23/2015 |
| Note: Released By: JHINDMAN final s | |||
| SW1 | COMPLETE | 10/13/2014 | 10/13/2014 |
| Note: Released By: JHINDMAN FOUNDATION S | |||
| ELEC | COMPLETE | 08/27/2014 | 08/28/2014 |
| ELEC | HOLD | 08/21/2014 | 08/21/2014 |
| Note: 1. Provide a riser that meets 2008 NEC art 250 for the connection to the foundation steel before the first means of disconnect. J. Hindman 986-3784. The new riser must have all of the grounding conducters connected together before the first means of disconnect. | |||
| URB | COMPLETE | 08/21/2014 | 08/22/2014 |
| ZON | COMPLETE | 08/21/2014 | 08/22/2014 |
| BLD | COMPLETE | 08/11/2014 | 08/11/2014 |
| ELEC | HOLD | 08/11/2014 | 08/11/2014 |
| Note: 1. Provide a riser that meets 2008 NEC art 250 for the connection to the foundation steel before the first means of disconnect. J. Hindman 986-3784. | |||
| ENGIN1 | COMPLETE | 08/11/2014 | 08/11/2014 |
| Note: No swale plan required. | |||
| MECH | COMPLETE | 08/11/2014 | 08/11/2014 |
| PLUM | COMPLETE | 08/11/2014 | 08/11/2014 |
| SW1 | COMPLETE | 08/11/2014 | 08/11/2014 |
| UD1 | COMPLETE | 08/11/2014 | 08/11/2014 |
| Note: See comments in the general notes Keith King 386-9318009 | |||
| URB | HOLD | 08/11/2014 | 08/11/2014 |
| Note: Need to add 1-8' understory tree this lot requires 4 trees. Need the type of sod being installed. | |||
| ZON | HOLD | 08/11/2014 | 08/12/2014 |
| Note: Landscape Plan must depict sod type. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 02/26/2015 |
| REINSPECTION FEE | ¤40.00 | 02/26/2015 |
| REINSPECTION FEE | ¤40.00 | 02/26/2015 |
| NEW RESIDENTIAL INSPECTIONS | ¤754.00 | 09/09/2014 |
| SITE PLAN 20 | ¤20.00 | 09/09/2014 |
| SURCHARGE FS 533.721 | ¤26.75 | 09/09/2014 |
| SURCHARGE - FS 468.631 | ¤26.75 | 09/09/2014 |
| STORM WATER PERMIT FEES | ¤80.00 | 09/09/2014 |
| 3% TRANS IMPACT FEE CREDIT | (¤90.51) | 09/09/2014 |
| ADMIN FEE | ¤20.00 | 09/09/2014 |
| ELECTRIC FEE | ¤286.20 | 09/09/2014 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.33) | 09/09/2014 |
| IMPACT FEE FIRE NONRESIDENTIAL | ¤211.11 | 09/09/2014 |
| IMPACT FEE PARKS | ¤894.24 | 09/09/2014 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 09/09/2014 |
| IMPACT FEE TRANSPORTATION | ¤3,017.05 | 09/09/2014 |
| MECHANICAL FEE | ¤286.20 | 09/09/2014 |
| 3% PARKS IMPACT FEE CREDIT | (¤26.83) | 09/09/2014 |
| PLAN CHECK FEE | ¤150.80 | 09/09/2014 |
| PLUMBING FEE | ¤286.20 | 09/09/2014 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤9,655.63 |