I want to search for...

Permit #2014080325

Permit Details

Status: COED

Parcel Id: 07-11-31-7004-00180-0090
CONDITIONED SPACE: 3112 sqft
GARAGE: 555 sqft
SCREEN PORCH (SOLID ROOF) : 308 sqft
OPENED PORCH (WITH ROOF) : 308 sqft
OPENED PORCH (WITH ROOF) : 68 sqft
Total Square Footage: 4351 sqft
Block: 00180
Subdivision: 2203 - SECTION 4-COUNTRY CLUB COVE
Job Phone: (386)445-9055
Location Address: 26 CORTES CT
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 09/26/2014
NOC: RECORDED
Applicant name: LUIS JORGE MEDEIROS
Owner: LOPES, CARLOS J & MARIA

Address

53 BRILL ST

NEWARK, NJ 07105

Lot: 0090
Contracted Stated Job Value: ¤289,900.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

NEW COASTAL HOMES INC.
Status Location Address Mailing Address State License Number Phone Fax
CANCEL

399 SW PALM COAST PKWY

PALM COAST, FL 32137

STE5

PALM COAST, FL 32137

CRC1327024 (Exp: 08/31/2018) (386)445-9055 (386)445-9056

Sub Contractors

CHARLES K DAVIS
Status Location Address State License Number Phone
ACTIVE

3000 E MOODY BLVD BLDG 2

BUNNELL , FL 32110

EC13004270 (Exp: 08/31/2026) 386-931-6614
PAUL S AIELLO
Status Location Address State License Number Phone Fax
CANCEL

PO BOX 351926

PALM COAST, FL 32137

CAC1815808 (Exp: 08/31/2016) (386)239-0053 (386)323-1955
HEATH EDWARD SANFORD
Status Location Address State License Number Phone Fax
ACTIVE

1351 HAZELNUT ST

BUNNELL, FL 32110

CFC1427527 (Exp: 08/31/2026) 386-445-2532 386-445-5575
SANTOS L HERNANDEZ
Status Location Address State License Number Phone Fax
ACTIVE

946 SHADDICK DRIVE

ORANGE CITY, FL 32763

CCC1328011 (Exp: 08/31/2026) 386-218-4942 386-218-4937

Inspection History

Type Request Date Result Inspector
U -UTILITY RESIDENTIAL FINAL 10/02/2015 FINAL APPROVED MBACON
BLD - BUILDING FINAL 09/30/2015 FINAL APPROVED CMINI
FINAL APRON (AFTER POUR/DRIVEWAY) 09/29/2015 APPROVED GLALIMA
Note: THIS IS A REINSPECTION
ROW FINAL 09/29/2015 FINAL APPROVED GLALIMA
Note: THIS IS A REINSPECTION
ROW FINAL 09/28/2015 CANCELLED BY APPLICANT GLALIMA
Note: NO SURVEY OR SWALE ON SITE
FINAL APRON (AFTER POUR/DRIVEWAY) 09/28/2015 CANCELLED BY APPLICANT GLALIMA
Note: WORKING ON SWALE SHEET AND FINAL SURVEY
FINAL SURVEY (OFFICE USE ONLY) 09/24/2015 APPROVED DREWIS
ELECTRIC - EARLY POWER 09/15/2015 APPROVED - AS NOTED LMILLER
Note: Inspection Resulted at 9/15/2015 3:05:32 PM CALLED FPL AND SPOKE TO: SUSAN AT 2:56
PRE-APRON (PRE-POUR/DRIVEWAY) 08/20/2015 APPROVED - AS NOTED RGROSS
Note: THIS IS A REINSPECTION Ground still soft from hard rains, double check elevations before pouring. Fill and compact any small washout areas.
PRE-APRON (PRE-POUR/DRIVEWAY) 08/17/2015 Disapproved -FEE REQUIRED CTROHA
Note: per contractor GRADES OUT OF TOLERANCE CHECK ELEVATIONS
LATH/BRICK/ WATER BARRIER 06/10/2015 APPROVED CMINI
Note: THIS IS A REINSPECTION
INSULATION 06/04/2015 APPROVED CMINI
GRAVITY SEWER TEST 05/21/2015 APPROVED CMINI
U - SEWER TIE IN 05/21/2015 APPROVED MBACON
ALL ROUGH 05/20/2015 APPROVED JCOLASANTI
Note: THIS IS A REINSPECTION
ALL ROUGH 05/15/2015 Disapproved -FEE REQUIRED DROCKWELL
Note: Inspection Resulted at 5/15/2015 2:48:20 PM NO HEAD TEST ON SANITAERY PLUMBING/SHOWER PAN PER FBC312.2/NAIL PLATE AT 3IN PIPE TOP PLATE MASTER BATH/CHASE PIPE IN PANTRY/FLEX DUCT THRU FLOOR NOT PERMITTED PER FBC-MECH 603.7/WIRE IN WALL CAVITY ABOVE UP BATH SINK??
LATH/BRICK/ WATER BARRIER 05/11/2015 PARTIALLY APPROVED CMINI
Note: THIS IS A REINSPECTION
LATH/BRICK/ WATER BARRIER 05/06/2015 PARTIALLY APPROVED CMINI
Note: Inspection Resulted at 5/6/2015 8:57:39 AM PARTIAL ON BLOCK ONLY
ELECTRIC-TUG 04/29/2015 APPROVED - AS NOTED CMINI
Note: Inspection Resulted at 4/29/2015 2:56:47 PM CALLED FPL TO RELEASE POWER AT 3PM,SPOKE WITH SUSAN
WINDOW NAILING 04/29/2015 APPROVED CMINI
WALL SHEATHING 04/29/2015 APPROVED CMINI
ROOF SHEATHING / BRACES/TIES/DOWN CELL 02/18/2015 APPROVED CMINI
TIE BEAM / LINTEL 12/19/2014 APPROVED CMINI
FOUND SURVEY APPROVED (OFFICE) 12/08/2014 APPROVED JHINDMAN
MONOLITHIC SLAB 11/19/2014 APPROVED CMINI
PLUMBING 1ST ROUGH UNDERGROUND 11/13/2014 APPROVED JCOLASANTI

Review History

Department Status Date In Date Out
SW1 COMPLETE 09/24/2015 09/24/2015
Note: Released By: DREWIS final survey
ELEC COMPLETE 05/14/2015 05/14/2015
SW1 COMPLETE 12/08/2014 12/08/2014
Note: Released By: JHINDMAN foundation survey
BLD COMPLETE 11/14/2014 11/19/2014
ENGIN1 COMPLETE 09/08/2014 09/11/2014
BLD COMPLETE 09/08/2014 09/09/2014
ELEC COMPLETE 08/22/2014 08/26/2014
ZON COMPLETE 08/22/2014 08/25/2014
ENGIN1 HOLD 08/22/2014 08/25/2014
Note: Provide benchmark per technical manual. The benchmark must be maintained throughout the construction cycle. Scott Bombardier 986-3756
BLD HOLD 08/22/2014 08/25/2014
Note: Held By: RLEE 1. Provide roof and floor truss layout page with connection details. 2010 FBC 107.2.1. 2. Truss layout sheet and notes not legible
BLD HOLD 08/14/2014 08/14/2014
Note: 1. Provide roof and floor truss layout page with connection details. 2010 FBC 107.2.1. 2. Provide gaurdrailing detail 2010 FBC 312. J. Hindman 986-3784.
ELEC HOLD 08/14/2014 08/14/2014
Note: 1. Provide receptacle wall spacing at bedroom 3 per 2008 NEC 210.52. 2. Provide generator transfer switch and panel details.2008 NEC art 702. J. Hindman 986-3784.
ENGIN1 HOLD 08/14/2014 08/14/2014
Note: Provide benchmark per technical manual. Scott Bombardier 986-3756
MECH COMPLETE 08/14/2014 08/14/2014
SW1 COMPLETE 08/14/2014 08/15/2014
UD1 COMPLETE 08/14/2014 08/14/2014
Note: See comments in the general notes Keith King 386-9318009
URB COMPLETE 08/14/2014 08/18/2014
Note: Prior to construction all saved trees will require a barricade.
ZON HOLD 08/14/2014 08/14/2014
Note: 1. Foundation plantings required for rear of home facing saltwater canals. 2. Please remove lower arc of circular driveway from easement.
PLUM COMPLETE 08/14/2014 08/14/2014

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
CONTRACTOR CHANGE ¤40.00 10/02/2015
REVISION ¤40.00 10/02/2015
REVISION ¤40.00 10/02/2015
REINSPECTION FEE ¤40.00 10/02/2015
REINSPECTION FEE ¤40.00 10/02/2015
NEW RESIDENTIAL INSPECTIONS ¤792.00 09/26/2014
ADMIN FEE ¤20.00 09/26/2014
SITE PLAN 20 ¤20.00 09/26/2014
SURCHARGE FS 533.721 ¤27.95 09/26/2014
SURCHARGE - FS 468.631 ¤27.95 09/26/2014
STORM WATER PERMIT FEES ¤80.00 09/26/2014
3% TRANS IMPACT FEE CREDIT (¤90.51) 09/26/2014
ELECTRIC FEE ¤297.60 09/26/2014
3% FIRE IMPACT FEE CREDIT (¤6.33) 09/26/2014
IMPACT FEE FIRE NONRESIDENTIAL ¤211.11 09/26/2014
IMPACT FEE SCHOOL ¤3,600.00 09/26/2014
IMPACT FEE TRANSPORTATION ¤3,017.05 09/26/2014
MECHANICAL FEE ¤297.60 09/26/2014
PARKS IMPACT FEE ¤849.24 09/26/2014
3% PARKS IMPACT FEE CREDIT (¤25.48) 09/26/2014
PLAN CHECK FEE ¤158.40 09/26/2014
PLUMBING FEE ¤297.60 09/26/2014
Fees Total Due: ¤0.00 Total Paid: ¤9,774.18