Permit #2014100433
Permit Details
Status: FINAL
| Subdivision: 2148 - TOWN CENTER PHASE 8 |
| Job Phone: 407-741-8500 |
| Location Address: 455 LANDING BLVD |
| Type: TLR - TEMPORARY TRAILER -OFFICE/ CONSTRUCTION |
| Issue Date: 11/05/2014 |
| NOC: Unknown |
| Applicant name: SCOTT W CULP |
| Owner: FLORIDA LANDMARK COMMUNITIES LLC |
|
Address 145 CITY PLACE PALM COAST, FL 32164 |
|
Address SUITE 300 PALM COAST, FL 32164 |
| Contracted Stated Job Value: ¤2,000.00 |
| Job Description: TEMPORARY CONSTRUCTION OFFICE TRAILER |
| Type: CN |
Contractor
CPG CONSTRUCTION LLP
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
200 E CANTON AVE # 102 WINTER PARK, FL 32789 |
CGC1512998 (Exp: 08/31/2016) | 407-741-8500 | 407-643-2551 |
Sub Contractors
RANCE F BORDERICK
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
430 WEST DRIVE ALTAMONTE SPRINGS, FL 32714 |
EC0000981 (Exp: 08/31/2026) | (407)788-3500 | 407-788-2007 |
Inspection History
| Type | Request Date | Result | Inspector |
| ELECTRIC - EARLY POWER | 11/25/2014 | APPROVED - AS NOTED | CMINI |
| Note: Inspection Resulted at 11/25/2014 2:33:31 PM CALLED FPL TO RELEASE POWER AT 225, SPOKE WITH SUSAN | |||
| ELECTRIC FINAL | 11/10/2014 | APPROVED | CMINI |
| FINAL | 11/10/2014 | FINAL APPROVED | CMINI |
Review History
| Department | Status | Date In | Date Out |
| ZON | COMPLETE | 10/30/2014 | 11/04/2014 |
| DSD | COMPLETE | 10/30/2014 | 11/04/2014 |
| ELEC | COMPLETE | 10/30/2014 | 10/31/2014 |
| ZON | HOLD | 10/17/2014 | 10/20/2014 |
| Note: Per Section 4.19 Construction trailers must following the following standards: A. Pedestrian access must be provided from the parking area to the office. Update construction staging sheet accordingly. B. A fence or similar barrier shall be provided to prevent visitors and customer from entering the construction area. Update construction staging sheet accordingly. C. If an identification sign is proposed, only one identification sign is permitted. The sign area shall not exceed six square feet. Please update construction staging plan accordingly. The trailer shall be removed within three working days following the acceptance of the construction completion. | |||
| BLD | COMPLETE | 10/17/2014 | 10/21/2014 |
| DSD | HOLD | 10/17/2014 | 10/20/2014 |
| Note: Per Section 4.19 Construction trailers must following the following standards: A. Pedestrian access must be provided from the parking area to the office. Update construction staging sheet accordingly. B. A fence or similar barrier shall be provided to prevent visitors and customer from entering the construction area. Update construction staging sheet accordingly. C. If an identification sign is proposed, only one identification sign is permitted. The sign area shall not exceed six square feet. Please update construction staging plan accordingly. The trailer shall be removed within three working days following the acceptance of the construction completion. | |||
| ELEC | HOLD | 10/17/2014 | 10/22/2014 |
| Note: 1. Provide an electrical service riser. J. Hindman 986-3784. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADMIN COMMERCIAL | ¤60.00 | 11/05/2014 |
| INSPECTION - COMMERCIAL ACCESS | ¤50.00 | 11/05/2014 |
| ELECTRIC FEE | ¤61.20 | 11/05/2014 |
| PLAN CHECK FEE | ¤100.00 | 11/05/2014 |
| SITE PLAN 20 | ¤20.00 | 11/05/2014 |
| SURCHARGE FS 533.721 | ¤3.32 | 11/05/2014 |
| SURCHARGE - FS 468.631 | ¤3.32 | 11/05/2014 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤297.84 |