I want to search for...

Permit #2014110129

Permit Details

Status: COED

CONDITIONED SPACE: 1530 sqft
GARAGE: 1438 sqft
OPENED PORCH (WITH ROOF) : 239 sqft
OPENED PORCH (WITH ROOF) : 237 sqft
Total Square Footage: 3444 sqft
Subdivision: 2148 - TOWN CENTER PHASE 8
Job Phone: 407-741-8500
Location Address: 427 LANDING BLVD BLDG 6
Type: BM - BUILDING MULTI - APARTMENT
Issue Date: 11/25/2014
NOC: RECORDED
Applicant name: SCOTT W CULP
Owner: FLORIDA LANDMARK COMMUNITIES LLC

Address

145 CITY PLACE

PALM COAST, FL 32164

Address

SUITE 300

PALM COAST, FL 32164

Contracted Stated Job Value: ¤224,025.00
Job Description: BUILDING 6 - 2 UNIT APARTMENT OVER 4 GARAGES
Type: CN

Contractor

CPG CONSTRUCTION LLP
Status Location Address State License Number Phone Fax
CANCEL

200 E CANTON AVE # 102

WINTER PARK, FL 32789

CGC1512998 (Exp: 08/31/2016) 407-741-8500 407-643-2551

Sub Contractors

CHARLES H KULP
Status Location Address State License Number Phone Fax
CANCEL

5401 ENERGY AIR CT

ORLANDO, FL 32810

CAC018270 (Exp: 08/31/2022) 407-886-3729 407-886-7580
RANCE F BORDERICK
Status Location Address State License Number Phone Fax
ACTIVE

430 WEST DRIVE

ALTAMONTE SPRINGS, FL 32714

EC0000981 (Exp: 08/31/2026) (407)788-3500 407-788-2007
DAVID A CROSON
Status Location Address State License Number Phone
CANCEL

31550 COUNTY ROAD 437

SORRENTO, FL 32776

CFC1426109 (Exp: 08/31/2022) 352-729-7100
JOSEPH RICHARD CASSIDY JR
Status Location Address State License Number Phone Fax
CANCEL

17304 PHIL C PETERS RD

WINTER GARDEN, FL 34787

CCC1327385 (Exp: 08/31/2020) 407-654-4426 (407)654-4307

Inspection History

Type Request Date Result Inspector
U - UTILITY COMMERCIAL FINAL 06/09/2015 APPROVED DSPENCER
Note: THIS IS A REINSPECTION
FIRE FINAL 06/08/2015 FINAL APPROVED JHINDMAN
U - UTILITY COMMERCIAL FINAL 06/08/2015 PARTIALLY APPROVED DSPENCER
Note: Inspection Resulted at 6/8/2015 3:04:16 PM MOVING PLANT BY METER PIT
PLUMBING FINAL 06/08/2015 APPROVED CMINI
HVAC FINAL 06/08/2015 APPROVED CMINI
ELECTRIC FINAL 06/08/2015 FINAL APPROVED RMARTIN
BUILDING FINAL 06/08/2015 FINAL APPROVED CMINI
LDSC- LANDSCAPE FINAL 05/29/2015 APPROVED - AS NOTED WBUTLER
Note: Stage 3 of Project-Buildings 4 (2014110127), 5 (2014110128) and 6 (2014110129) 1. Need downspout extensions to direct roof drainage to either a turf area or a paved surface. Will be checked with the Site Development Permit inspection. 2. The disturbed area off-site to the south of the development needs to be stabilized with either seeding and mulching or hydroseeding. 3. Building 6 needs to finish installing the pavers in the front of the building and raising the two holly trees so the top of the rootball is slightly higher than the adjacent pavement. 4. Zone 21 drip zone needs to have a flush valve installed at the location that was discussed in the field. 5. Need a revised card in the irrigation controller that indicates what zone operates what area of the site. Make sure zone numbering agrees with the numbering on the as-built. 6. Need to submit landscape and irrigation as-builts for the project and after they are approved, and all other comments addressed, call in to the Building Department for the final inspection. The above items will need to be completed prior to the approval of the Site Development Permit number 2014090561.
ELECTRIC - EARLY POWER 05/14/2015 APPROVED RMARTIN
Note: Inspection Resulted at 5/14/2015 2:28:08 PM SPOKE TO SUSAN RELEASED POWER METERS A/B
INSULATION 04/06/2015 APPROVED CMINI
FIREWALL 04/02/2015 APPROVED DROCKWELL
ALL ROUGH 04/02/2015 APPROVED DROCKWELL
ROOF SHEATHING / BRACE / TIE DOWN 03/27/2015 APPROVED DROCKWELL
Note: THIS IS A REINSPECTION
ROOF SHEATHING / BRACE / TIE DOWN 03/26/2015 CANCELLED BY APPLICANT DROCKWELL
WINDOW NAILING 03/13/2015 APPROVED JHINDMAN
EXTERIOR WALL SHEATHING / SHEARWALL 03/06/2015 APPROVED DROCKWELL
ROOF SHEATHING / BRACE / TIE DOWN 03/04/2015 APPROVED - AS NOTED DROCKWELL
Note: Inspection Resulted at 3/4/2015 11:53:13 AM ROOF SHEATHING ONLY
GRAVITY SEWER 01/29/2015 APPROVED CMINI
U - SEWER TIE IN 01/29/2015 APPROVED DSPENCER
ELECTRIC 1ST ROUGH 01/23/2015 APPROVED - AS NOTED DROCKWELL
Note: Inspection Resulted at 1/23/2015 11:09:55 AM UNDERGROUND CONDUIT
PLUMBING 1ST ROUGH 01/15/2015 APPROVED - AS NOTED DROCKWELL
Note: Inspection Resulted at 1/15/2015 11:42:27 AM THIS WAS A REPAIR TO A SANITARY LINE AND A RE-TEST
MONOLITHIC SLAB 01/14/2015 APPROVED - AS NOTED DROCKWELL
Note: Inspection Resulted at 1/14/2015 11:13:22 AM DUMPSTER PADS W/REINFORCED BLOCK WALLS-APPROVED
PLUMBING 1ST ROUGH 01/06/2015 APPROVED CMINI

Review History

Department Status Date In Date Out
ELEC COMPLETE 06/03/2015 06/08/2015
ELEC COMPLETE 05/26/2015 05/29/2015
MECH COMPLETE 05/26/2015 06/02/2015
Note: Revision 3 dated 5-11-15.
BLD COMPLETE 03/05/2015 03/09/2015
BLD COMPLETE 02/19/2015 02/23/2015
ELEC COMPLETE 02/19/2015 02/20/2015
MECH COMPLETE 02/19/2015 02/23/2015
Note: Rev.2 (owner's rev.) - deleted garage exhaust fans.
PLUM COMPLETE 02/19/2015 02/23/2015
Note: Revision 2 (owner's rev.) - relocated drywell away from condenser units.
BLD COMPLETE 01/12/2015 01/12/2015
BLD COMPLETE 11/20/2014 11/21/2014
ZON COMPLETE 11/20/2014 11/20/2014
BLD HOLD 11/07/2014 11/13/2014
Note: 1. Provide florida product approval worksheet andthe roof and floor truss layouts per 2010 FBC 107.2.1. J. Hindman 986-3784.
ELEC COMPLETE 11/07/2014 11/12/2014
ENGIN1 COMPLETE 11/07/2014 11/10/2014
FI1 COMPLETE 11/07/2014 11/12/2014
MECH COMPLETE 11/07/2014 11/12/2014
PLUM COMPLETE 11/07/2014 11/12/2014
UD1 COMPLETE 11/07/2014 11/10/2014
ZON HOLD 11/07/2014 11/18/2014
Note: 1. Please revise sheet A0.2 to provide the building square footages in the data table for the garages, breezeways, and fire riser closet on the first and/or second floors. (Similar to the revision provided on Sheet A0.2 attached to building permit 2014070535.) 2. Please Revise sheet A6.1 and any other affected elevation drawing to provide a note notifying the contractor to refer to the approved color elevations attached to the Site Plan Development Order for building colors and color locations.

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REVISION ¤40.00 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION (¤40.00) 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION (¤40.00) 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION (¤40.00) 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION (¤40.00) 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION (¤40.00) 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION (¤40.00) 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION (¤40.00) 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION (¤40.00) 06/09/2015
REVISION ¤40.00 06/09/2015
REVISION (¤40.00) 06/09/2015
REVISION ¤40.00 06/09/2015
SURCHARGE FS 533.721 ¤35.29 11/25/2014
SURCHARGE - FS 468.631 ¤35.29 11/25/2014
3% TRANS IMPACT FEE CREDIT (¤168.96) 11/25/2014
ADMIN COMMERCIAL ¤60.00 11/25/2014
ELECTRIC FEE ¤210.00 11/25/2014
3% FIRE IMPACT FEE CREDIT (¤12.67) 11/25/2014
IMPACT FEE FIRE NONRESIDENTIAL ¤422.22 11/25/2014
IMPACT FEE PARKS ¤1,698.48 11/25/2014
FIRE PLANS REVIEW ¤34.44 11/25/2014
IMPACT FEE TRANSPORTATION ¤5,632.14 11/25/2014
MECHANICAL FEE ¤210.00 11/25/2014
PERMIT FEE ¤1,375.00 11/25/2014
3% PARKS IMPACT FEE CREDIT (¤50.95) 11/25/2014
PLAN CHECK FEE ¤287.50 11/25/2014
PLUMBING FEE ¤210.00 11/25/2014
Fees Total Due: ¤0.00 Total Paid: ¤10,337.78