Permit #2015060958
Permit Details
Status: COED
| Parcel Id: 07-11-31-7007-00270-0160 |
| CONDITIONED SPACE: 3039 sqft |
| GARAGE: 776 sqft |
| OPENED PORCH (WITH ROOF) : 466 sqft |
| OPENED PORCH (WITH ROOF) : 124 sqft |
| Total Square Footage: 4405 sqft |
| Block: 00270 |
| Subdivision: 2185 - SECTION 7-FLORIDA PARK |
| Job Phone: (386)446-5161 |
| Location Address: 26 FREEMAN LN |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 08/17/2015 |
| NOC: RECORDED |
| Applicant name: HUGO A CAMACHO |
| Owner: FRANCIS RUDOLPH & NORMA C H&W |
|
Address 42 HABITAT LANE BLOOMFIELD, CT 06002 |
| Lot: 0160 |
| Contracted Stated Job Value: ¤350,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
IDEAL HOMES AT PALM COAST, INC.
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
PO BOX 353639 PALM COAST, FL 32137 |
CBC1250774 (Exp: 08/31/2026) | (386)446-5161 | (386)447-0238 |
Sub Contractors
WILLIAM FRANK DUDLEY JR.
| Status | Location Address | State License Number | Phone |
| ACTIVE |
P.O. BOX 978 Bunnell, FL 32110 |
EC0003177 (Exp: 08/31/2026) | (386)437-3068 |
PAUL S AIELLO
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
PO BOX 351926 PALM COAST, FL 32137 |
CAC1815808 (Exp: 08/31/2016) | (386)239-0053 | (386)323-1955 |
JONATHAN M PEARSON
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
209 N FORSYTH ST BUNNELL, FL 32110 |
CFC1425941 (Exp: 08/31/2026) | 386-597-0944 | 386-437-4996 |
JOANNA S REELEY
| Status | Location Address | State License Number | Phone |
| INACTIVE |
2 MARKET PLACE D PALM COAST, FL 32137 |
CCC1327485 (Exp: 08/31/2020) | 386-445-7945 |
Inspection History
| Type | Request Date | Result | Inspector |
| U -UTILITY RESIDENTIAL FINAL | 06/29/2016 | FINAL APPROVED | JNICHOLS |
| Note: utility final is approved but i can not close. | |||
| BLD - BUILDING FINAL | 06/28/2016 | FINAL APPROVED | CMINI |
| PRE-APRON (PRE-POUR/DRIVEWAY) | 06/22/2016 | APPROVED | CTROHA |
| FINAL APRON (AFTER POUR/DRIVEWAY) | 06/22/2016 | APPROVED | CTROHA |
| Note: OK | |||
| ROW FINAL | 06/22/2016 | APPROVED - AS NOTED | CTROHA |
| Note: SPOKE TO HUGO ABOUT ADDING SOME SEED AND STRAW TO WHAT WAS AREADY THERE | |||
| ELEV CERT-FOUNDATION APPROVAL | 06/22/2016 | CANCELLED BY APPLICANT | AIRS WEB |
| FINAL SURVEY (OFFICE USE ONLY) | 06/09/2016 | APPROVED | DREWIS |
| ELECTRIC - EARLY POWER | 04/19/2016 | APPROVED - AS NOTED | RMARTIN |
| Note: Inspection Resulted at 4/19/2016 3:29:43 PM SPOKE TO SUSAN FPL RELEASED EARLY POWER 3:15 | |||
| PRE-APRON (PRE-POUR/DRIVEWAY) | 03/22/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION PARTIALLY APPROVED. READY TO POUR CONCRETE OVER PIPE ONLY. PAVER DRIVEWAY. | |||
| PRE-APRON (PRE-POUR/DRIVEWAY) | 03/18/2016 | CANCELLED BY APPLICANT | CTROHA |
| Note: NOT READY TO POUR DUE TO WEATHER | |||
| GRAVITY SEWER TEST | 02/19/2016 | APPROVED | LMILLER |
| Note: THIS IS A REINSPECTION | |||
| GRAVITY SEWER TEST | 02/18/2016 | Disapproved - NO FEE | LMILLER |
| Note: THIS IS A REINSPECTION Inspection Resulted at 2/18/2016 11:27:36 AM UNCOVER WORK TO BE INSPECTED..FBC...P2503.2 (NEED TO UNCOVER BELL HUB ON PIPE AS WELL) | |||
| GRAVITY SEWER TEST | 02/10/2016 | Disapproved -FEE REQUIRED | LMILLER |
| Note: Inspection Resulted at 2/10/2016 11:27:24 AM UNCOVER WORK TO BE INSPECTED..FBC...P2503.2 | |||
| U - SEWER TIE IN | 02/10/2016 | APPROVED | MBACON |
| INSULATION | 01/14/2016 | APPROVED | LMILLER |
| ALL ROUGH | 01/11/2016 | APPROVED | CMINI |
| LATH/BRICK/ WATER BARRIER | 12/31/2015 | APPROVED | CMINI |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 12/09/2015 | APPROVED | CMINI |
| Note: THIS IS A REINSPECTION | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 12/01/2015 | Disapproved -FEE REQUIRED | LMILLER |
| Note: Inspection Resulted at 12/1/2015 12:10:03 PM COMPLETE CONTINUOUS LOAD PATH PER DETAILS | |||
| ELECTRIC-TUG | 10/19/2015 | APPROVED - AS NOTED | RMARTIN |
| Note: Inspection Resulted at 10/19/2015 2:18:54 PM SPOKE TO SUSAN FPL RELEASED TUG 2:17 | |||
| TIE BEAM / LINTEL | 10/16/2015 | APPROVED | LMILLER |
| Note: THIS IS A REINSPECTION | |||
| TIE BEAM / LINTEL | 10/15/2015 | Disapproved -FEE REQUIRED | LMILLER |
| Note: Inspection Resulted at 10/15/2015 11:15:54 AM DWV VENT PIPES; JOINTS AND CONNECTIONS IN THE DWV SYSTEM SHALL BE GAS TIGHT AND WATER TIGHT FOR THE INTENDED USE OR PRESSURE REQUIRED BY TEST FBC 312, TIE STEEL IN LENTALS WHERE CIRCLED ON PLANS | |||
| FOUND SURVEY APPROVED (OFFICE) | 10/14/2015 | APPROVED | DREWIS |
| MONOLITHIC SLAB | 09/30/2015 | APPROVED | CMINI |
| PLUMBING 1ST ROUGH UNDERGROUND | 09/28/2015 | APPROVED | CMINI |
Review History
| Department | Status | Date In | Date Out |
| SW1 | COMPLETE | 06/07/2016 | 06/09/2016 |
| Note: Released By: DREWIS final s | |||
| BLD | COMPLETE | 01/07/2016 | 01/08/2016 |
| ELEC | COMPLETE | 01/07/2016 | 01/08/2016 |
| SW1 | COMPLETE | 10/14/2015 | 10/14/2015 |
| Note: Released By: DREWIS foundation survey | |||
| ZON | COMPLETE | 08/14/2015 | 08/14/2015 |
| SW1 | COMPLETE | 07/14/2015 | 07/14/2015 |
| ZON | HOLD | 07/14/2015 | 07/15/2015 |
| Note: REPEAT ORIGINAL COMMENT: Pending receipt of complete, recorded Binding Lot Agreement. | |||
| URB | COMPLETE | 07/14/2015 | 07/14/2015 |
| BLD | COMPLETE | 07/14/2015 | 07/14/2015 |
| BLD | HOLD | 06/29/2015 | 06/30/2015 |
| Note: 1. Identify the lintel sizes at the master bedroom and family room windows. 2010 FBC 107.2.1. | |||
| ELEC | COMPLETE | 06/29/2015 | 06/29/2015 |
| ENGIN1 | COMPLETE | 06/29/2015 | 07/13/2015 |
| MECH | COMPLETE | 06/29/2015 | 06/30/2015 |
| PLUM | COMPLETE | 06/29/2015 | 06/30/2015 |
| SW1 | HOLD | 06/29/2015 | 06/29/2015 |
| Note: Please provide proposed survey measurements for lot 16 side of home showing positive storm water flow as existing measurements would be higher than proposed foundation. | |||
| UD1 | COMPLETE | 06/29/2015 | 06/30/2015 |
| Note: See Notes | |||
| ZON | HOLD | 06/29/2015 | 06/30/2015 |
| Note: Pending receipt of complete, recorded Binding Lot Agreement. | |||
| URB | HOLD | 06/29/2015 | 06/30/2015 |
| Note: Need to trade 2 of the understory trees for shade type trees. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 07/05/2016 |
| REINSPECTION FEE | ¤40.00 | 07/05/2016 |
| REINSPECTION FEE | ¤40.00 | 07/05/2016 |
| REVISION | ¤40.00 | 07/05/2016 |
| SITE PLAN 20 | ¤20.00 | 08/17/2015 |
| SURCHARGE FS 533.721 | ¤27.76 | 08/17/2015 |
| SURCHARGE - FS 468.631 | ¤27.76 | 08/17/2015 |
| STORM WATER PERMIT FEES | ¤80.00 | 08/17/2015 |
| 3% TRANS IMPACT FEE CREDIT | (¤91.51) | 08/17/2015 |
| NEW RESIDENTIAL INSPECTIONS | ¤786.00 | 08/17/2015 |
| ADMIN FEE | ¤20.00 | 08/17/2015 |
| ELECTRIC FEE | ¤295.80 | 08/17/2015 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.38) | 08/17/2015 |
| IMPACT FEE FIRE NONRESIDENTIAL | ¤212.80 | 08/17/2015 |
| IMPACT FEE PARKS | ¤849.24 | 08/17/2015 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 08/17/2015 |
| IMPACT FEE TRANSPORTATION | ¤3,050.24 | 08/17/2015 |
| MECHANICAL FEE | ¤295.80 | 08/17/2015 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 08/17/2015 |
| PLAN CHECK FEE | ¤157.20 | 08/17/2015 |
| PLUMBING FEE | ¤295.80 | 08/17/2015 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤9,755.03 |