I want to search for...
Permit #2015090332
Permit Details
Status: CANCEL
| Parcel Id: 07-11-31-7033-00370-0110 |
| Block: 00370 |
| Subdivision: 2184 - SECTION 33-ROYAL PALMS |
| Job Phone: 407-871-2020 |
| Location Address: 3 RENWORTH PL |
| Type: PO - POOL |
| Issue Date: 10/13/2015 |
| NOC: Unknown |
| Applicant name: JOHN NICHOLAS WATTS |
| Owner: POTETE RICKY L & JUDITH K H&W |
|
Address 3 RENWORTH PLACE PALM COAST, FL 32164 |
| Lot: 0110 |
| Contracted Stated Job Value: ¤38,476.00 |
| Job Description: POOL WITH SPA & SCREEN ENCLOSURE |
| Type: CN |
Contractor
ALL SEASONS POOL SERVICE INC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
185 E AIRPORT BLVD GENEVA , FL 32732 |
CPC023576 (Exp: 08/31/2026) | 407-871-2020 | 407-321-5404 |
Sub Contractors
BRIAN KEITH MILLER
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
685 S RONALD REAGAN BLVD LONGWOOD, FL 32750 |
EC13001686 (Exp: 08/31/2026) | (386)668-4222 | (386)668-8222 |
Inspection History
| Type | Request Date | Result | Inspector |
| POOL FINAL | 05/04/2016 | FINAL APPROVED | DROCKWELL |
| FINAL SURVEY (OFFICE USE ONLY) | 05/03/2016 | APPROVED | DREWIS |
| ELECTRIC AND ALARM | 03/31/2016 | APPROVED | LMILLER |
| Note: THIS IS A REINSPECTION | |||
| ELECTRIC AND ALARM | 03/30/2016 | Disapproved -FEE REQUIRED | RMARTIN |
| Note: Inspection Resulted at 3/30/2016 9:44:59 AM NOT READY, ELECTRICIAN JUST ARRIVED WHEN I DID | |||
| POOL DECK | 03/10/2016 | APPROVED | DROCKWELL |
| Note: THIS IS A REINSPECTION | |||
| POOL DECK | 03/09/2016 | Disapproved -FEE REQUIRED | DROCKWELL |
| Note: Inspection Resulted at 3/9/2016 10:07:31 AM MISSING ALL POST FOOTERS W/STEEL/CLEAN-UP PERIMETER FOOTING DAMAGED BY STANDING WATER/35LBS OF PRESSURE IS REQUIRED ON PLUMBING/RE-INSTALL SAFETY BARRIER | |||
| STEEL AND GROUND | 01/13/2016 | APPROVED | DROCKWELL |
| Note: THIS IS A REINSPECTION | |||
| STEEL AND GROUND | 01/12/2016 | Disapproved - NO FEE | DROCKWELL |
| Note: THIS IS A REINSPECTION Inspection Resulted at 1/12/2016 11:48:06 AM STILL WORKING ON CORRECTING THE PROBLEM | |||
| STEEL AND GROUND | 01/08/2016 | Disapproved -FEE REQUIRED | DROCKWELL |
| Note: THIS IS A REINSPECTION Inspection Resulted at 1/8/2016 10:36:22 AM POOL WALL FAILED.NO CLEARANCE FOR STEEL | |||
| STEEL AND GROUND | 01/06/2016 | Disapproved -FEE REQUIRED | DROCKWELL |
| Note: THIS IS A REINSPECTION Inspection Resulted at 1/6/2016 10:06:42 AM POOL CAGE DAMAGED BY RAIN | |||
| STEEL AND GROUND | 12/31/2015 | Disapproved -FEE REQUIRED | LMILLER |
| Note: Inspection Resulted at 12/31/2015 9:23:26 AM PRESSURE TEST , R4501.12.1 ALL POOL PIPING SHALL BE TESTED AND PROVED TIGHT TO THE ADMINISTRATIVE AUTHORITY, UNDER A STATIC WATER OR AIR PRESSURE TEST OF NOT LESS THAN 35(PSI) FOR 15 MINUTES (PRESSURE TEST ON SPA PIPE). EQUIPOTENTIAL BONDING NEC. 680.26. (ADD BONDING PER BONDING DETAIL - SHEET 3 OF 5 APPROVED PLANS), STEEL MUST BE PALCED UNDER MAIN DRAINS PER DETAIL DRAWINGS SHEET 1 OF 5. | |||
| PROJECT STATUS (OFFICE USE) | 12/02/2015 | Disapproved - NO FEE | LMILLER |
| Note: Inspection Resulted at 12/2/2015 1:23:25 PM NO WORK HAS STARTED, ALL SEASONS SIGN IN YARD. UNDERGROUND UTILITIES MARKED | |||
| ROW DAMAGE | |||
| U -UTILITY RESIDENTIAL FINAL |
Review History
| Department | Status | Date In | Date Out |
| SW1 | COMPLETE | 05/03/2016 | 05/03/2016 |
| Note: Released By: DREWIS final survey | |||
| BLD | COMPLETE | 12/11/2015 | 12/15/2015 |
| ZON | COMPLETE | 12/11/2015 | 12/11/2015 |
| BLD | COMPLETE | 10/09/2015 | 10/12/2015 |
| BLD | HOLD | 10/06/2015 | 10/07/2015 |
| Note: 1.On the TDH form provide the correct gpm (120gpm) in the "determine simplified Tdh " lines 2 and 3 not 181 and 146.and "determine pipe size' boxes not 88, 181 and 146. 120gpm is your system flow rate. J. Hindman 986-3784. | |||
| ZON | COMPLETE | 09/21/2015 | 09/21/2015 |
| BLD | HOLD | 09/21/2015 | 09/22/2015 |
| Note: 1. Provide the correct gpm (120gpm) in the "determine simplified Tdh " and "determine pipe size' boxes. J. Hindman 986-3784. | |||
| BLD | HOLD | 09/14/2015 | 09/17/2015 |
| Note: 1. Provide a barrier that complies with the 5th edition of the Florida building code residential 4502.17. 2. Provide a TDH form with the correct values in the determine pipe sizes. The maximum system flow rate of 120gpm needs to be used to determine the correct pipe sizes. J.Hindman 986-3784. | |||
| SW1 | COMPLETE | 09/14/2015 | 09/15/2015 |
| ZON | HOLD | 09/14/2015 | 09/16/2015 |
| Note: Pool must be enclosed by fence or screen enclosure. T. Childs 986-2473 |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 03/30/2016 |
| REINSPECTION FEE | ¤40.00 | 03/10/2016 |
| REINSPECTION FEE | ¤40.00 | 01/11/2016 |
| REINSPECTION FEE | ¤40.00 | 01/06/2016 |
| REINSPECTION FEE | ¤40.00 | 01/04/2016 |
| REVISION | ¤40.00 | 12/18/2015 |
| SITE PLAN 20 | ¤20.00 | 10/13/2015 |
| SURCHARGE FS 533.721 | ¤3.30 | 10/13/2015 |
| SURCHARGE - FS 468.631 | ¤3.30 | 10/13/2015 |
| STORM WATER PERMIT FEES | ¤80.00 | 10/13/2015 |
| ADMIN FEE | ¤20.00 | 10/13/2015 |
| PERMIT FEE | ¤160.00 | 10/13/2015 |
| PLAN CHECK FEE | ¤40.00 | 10/13/2015 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤566.60 |