Permit #2015090674
Permit Details
Status: COED
| Parcel Id: 41-11-31-4975-00000-0010 |
| Block: 00000 |
| Subdivision: 2272 - ISLAND WALK AT PALM COAST |
| Job Phone: 727-938-9719 |
| Location Address: 250 PALM COAST PKWY NE |
| Type: CSD - COMMERCIAL SITE DEVELOPMENT |
| Issue Date: 10/20/2015 |
| NOC: RECORDED |
| Applicant name: MICHAEL S BEAUSIR |
| Owner: BRANCH ISLAND WALK ASSOCIATES LP |
|
Address 3340 PEACHTREE ROAD NE ATLANTA, GA 30326 |
|
Address SUITE 600 ATLANTA, GA 30326 |
| Lot: 0010 |
| Contracted Stated Job Value: ¤1,280,000.00 |
| Job Description: SITE STAGE 5 & 6 |
| Type: CN |
Contractor
HAWKINS CONSTRUCTION INC
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
1430 L AND R INDUSTRIAL BLVD TARPON SPRINGS, FL 34689 |
CGC061198 (Exp: 08/31/2018) | 727-938-9719 | 727-938-3208 |
Inspection History
| Type | Request Date | Result | Inspector |
| FINAL INSPECTION | 08/18/2016 | FINAL APPROVED | DSCHRAGER |
| Note: all work for this permit complete | |||
| FINAL SURVEY (COMM - OFFICE USE ONLY) | 08/12/2016 | APPROVED | DRAMIREZ |
| Note: The complete As-Builts were approved as part of application #3126. | |||
| BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS | 06/24/2016 | APPROVED | CMINI |
| BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS | 06/21/2016 | APPROVED | CMINI |
| Note: THIS IS A REINSPECTION per contractor | |||
| BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS | 06/08/2016 | Disapproved -FEE REQUIRED | CMINI |
| Note: Inspection Resulted at 6/8/2016 11:16:04 AM COULD NOT LOCATE PLANS, FIRE RISER ROOM LOCKED, NO ONE ON SITE. FORMED RAMP DOES NOT HAVE ANY INDICATIONS OF SLOPE AT MATRESS FIRM PARKING LOT | |||
| MOT - MAINT OF TRAFFIC | 05/26/2016 | APPROVED | DSCHRAGER |
| LDSC- LANDSCAPE FINAL | 05/02/2016 | APPROVED - AS NOTED | WBUTLER |
| Note: THIS IS A REINSPECTION WMB 5-2-16 A landscape bond has been received in the amount of $77,000 plus to cover the unfinished landscape and irrigation work on this final phase. | |||
| LDSC- LANDSCAPE / IRRIGATION AS-BUILT | 04/26/2016 | APPROVED | WBUTLER |
| LDSC- LANDSCAPE FINAL | 04/26/2016 | PARTIALLY APPROVED | WBUTLER |
| Note: 4/26/16 WMB 1) Cannot final the landscape until the landscaping and irrigation around the loading dock behind building A-2 has been done. | |||
| TRAFFIC SIGNAGE/PAVEMENT MARKING FINAL | 04/20/2016 | APPROVED | GLALIMA |
| Note: PER PHASE 3 /4 5 | |||
| FINAL DRAINAGE | 04/20/2016 | APPROVED | GLALIMA |
| Note: PER PHASE | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 04/20/2016 | APPROVED | DSPENCER |
| U-WATER MAIN DISINFECTION | 04/20/2016 | APPROVED | DSPENCER |
| U-WATER MAIN DISINFECTION SAMPLING | 04/20/2016 | APPROVED | DSPENCER |
| U - UTILITY COMMERCIAL FINAL | 04/20/2016 | APPROVED | DSPENCER |
| EROSION CONTROL / INLET PROTECTION/SILT FENCE | 04/20/2016 | APPROVED | GLALIMA |
| Note: | |||
| PROJECT STATUS (OFFICE USE) | 04/20/2016 | APPROVED | GLALIMA |
| Note: WORKING ON PERMIT INSPECTIONS FOR THIS PHASE 3 AND 4 AND 5 AND 6 | |||
| CONSTRUCTION ENTRANCE | 04/20/2016 | APPROVED | GLALIMA |
| RETENTION /DETENTION STABILIZATION | 04/20/2016 | APPROVED | GLALIMA |
| BLD - ADA COMPLIANT | 04/20/2016 | APPROVED - AS NOTED | GLALIMA |
| Note: ALL A.D.A. WAS INSTALLED AS PER ONSITE PLANS . ON SITE INSPECTION DON S GARY L | |||
| CONSTRUCTION ENTRANCE | 03/24/2016 | CANCELLED BY APPLICANT | GLALIMA |
| PIPE INSTALLATION | 03/24/2016 | APPROVED | GLALIMA |
| Note: THIS IS A REINSPECTION | |||
| DRAINAGE PIPE PLACEMENT | 03/17/2016 | APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION ALL STORMWATER PIPE HAS NOW BEEN PLACED. APPROVED | |||
| FORM BOARD | 03/16/2016 | APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION APPROVED | |||
| DRAINAGE STRUCTURE PLACEMENT | 03/16/2016 | APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION FINAL STRUCTURE HAS BEEN PLACED. APPROVED | |||
| CURBING AND GUTTER | 03/16/2016 | APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION FINAL CURB AND GUTTER COMPLETED. APPROVED | |||
| BLD - UNDERGROUND SITE LIGHTING CONDUITS | 03/15/2016 | APPROVED | RMARTIN |
| Note: THIS IS A REINSPECTION | |||
| BLD - SITE LIGHTING-POLE SET/FIXTURE | 03/15/2016 | APPROVED | RMARTIN |
| BLD - SITE LIGHTING-CONDUCTORS/CONNECTORS | 03/15/2016 | APPROVED | RMARTIN |
| Note: THIS IS A REINSPECTION | |||
| LDSC-SITE LIGHTING / SHIELDING | 03/15/2016 | APPROVED | WBUTLER |
| Note: per angie | |||
| CURBING AND GUTTER | 03/14/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION PARTIALLY APPROVED | |||
| CURBING AND GUTTER | 03/08/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION PARTIALLY APPROVED | |||
| CURBING AND GUTTER | 03/04/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION PARTIALLY APPROVED DUE TO ONGOING CURB AND GUTTER CONSTRUCTION | |||
| CURBING AND GUTTER | 03/03/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION PARTIALLY APPROVED. ONGOING CURB AND GUTTER CONSTRUCTION. | |||
| CURBING AND GUTTER | 03/02/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION PARTIALLY APPROVE DUE TO ONGOING CURB AND GUTTER CONSTRUCTION | |||
| CURBING AND GUTTER | 03/01/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION PARTIALLY APPROVED. ONGOING CURB AND GUTTER CONSTRUCTION | |||
| BLD - UNDERGROUND SITE LIGHTING CONDUITS | 03/01/2016 | PARTIALLY APPROVED | RMARTIN |
| Note: THIS IS A REINSPECTION Inspection Resulted at 3/1/2016 3:21:34 PM POLES CONDUIT STILL NEED SIGN EAST SIDE | |||
| DRAINAGE PIPE PLACEMENT | 02/29/2016 | CANCELLED BY APPLICANT | RGROSS |
| Note: THIS IS A REINSPECTION NO PIPE PLACEMENT TODAY | |||
| CURBING AND GUTTER | 02/29/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION PARTIALLY APPROVED. ONGOING CURB AND GUTTER CONSTRUCTION. | |||
| DRAINAGE PIPE PLACEMENT | 02/18/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION PARTIALLY APPROVED. ONGOING PIPE PLACEMENT. ON SITE WITH GM. FILTER FABRIC USED ON JOINTS. | |||
| FORM BOARD | 02/18/2016 | PARTIALLY APPROVED | RGROSS |
| Note: CURB AND GUTTER FORMED CORRECTLY. PARTIALLY APPROVED...ONGOING CONSTRUCTION OF CURB AND GUTTER. | |||
| CURBING AND GUTTER | 02/12/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION PARTIAL PASS. ONGOING SIDEWALK CONTRUCTION. | |||
| CURBING AND GUTTER | 02/10/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION PARTIAL APPROVAL. ONGOING CURB AND GUTTER WORK. | |||
| CURBING AND GUTTER | 02/09/2016 | PARTIALLY APPROVED | RGROSS |
| Note: ONLY PARTIALLY APPROVED DUE TO ONGOING CURB AND GUTTER AND OTHER CONSTRUCTION. | |||
| DRAINAGE PIPE PLACEMENT | 02/04/2016 | CANCELLED BY APPLICANT | RGROSS |
| Note: THIS IS A REINSPECTION | |||
| DRAINAGE PIPE PLACEMENT | 02/03/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION FILTER FABRIC USED ON PIPE JOINTS | |||
| DRAINAGE STRUCTURE PLACEMENT | 02/02/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION STRUCTURE IN PLACE | |||
| DRAINAGE PIPE PLACEMENT | 02/01/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION PIPE JOINTS SEALED AND FABRIC USED. | |||
| DRAINAGE PIPE PLACEMENT | 01/29/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION DRAINAGE PIPES PROPERLY SEALED AND FILTER FABRIC USED ON JOINTS | |||
| DRAINAGE STRUCTURE PLACEMENT | 01/29/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION STRUCTURES IN PLACE. ATTACHED DRAINAGE PIPES PROPERLY SEALED. | |||
| DRAINAGE PIPE PLACEMENT | 01/28/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION PIPE INSTALL IN PROCESS UPON INSPECTION. FILTER FABRIC ON SITE AND BEING USED. | |||
| DRAINAGE PIPE PLACEMENT | 01/27/2016 | CANCELLED BY APPLICANT | RGROSS |
| Note: THIS IS A REINSPECTION CANCELLED BY APP. HEAVY RAINS. | |||
| DRAINAGE PIPE PLACEMENT | 01/26/2016 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION On site with GM for inspection. Box pipe joints mudded properly. Pipe joint felt material in place. | |||
| DRAINAGE PIPE PLACEMENT | 01/22/2016 | Disapproved -FEE REQUIRED | GLALIMA |
| Note: THIS IS A REINSPECTION UNCOVER THE LAST 4 D / BOXES THAT YOU INSTALLED AND ALL PIPE. AS I TOLD YOU AT LAST INSPECTION . C O HOLD WILL BE PLACED ON THIS PERMIT . IF AN ISSUE CALL GARY LA LIMA 386 - 585 -087 | |||
| DRAINAGE PIPE PLACEMENT | 01/21/2016 | Disapproved -FEE REQUIRED | GLALIMA |
| Note: THIS IS A REINSPECTION NO FELT OVER / AROUND PIPE RE-INSPECTION ON FRIDAY 9 : 00 A:M | |||
| DRAINAGE PIPE PLACEMENT | 01/20/2016 | PARTIALLY APPROVED | GLALIMA |
| Note: ON GOING INSPECTION | |||
| DRAINAGE STRUCTURE PLACEMENT | 01/19/2016 | PARTIALLY APPROVED | GLALIMA |
| BLD - SITE LIGHTING-CONDUCTORS/CONNECTORS | 01/14/2016 | PARTIALLY APPROVED | RMARTIN |
| Note: Inspection Resulted at 1/14/2016 12:38:02 PM MARKED ON PLAN | |||
| LDSC-SITE LIGHT STAKE LOCATE | 01/13/2016 | APPROVED - AS NOTED | WBUTLER |
| Note: 1-13-16 WMB 1) In discussing the location of the light pole in front of Aimee's Hallmark the contractor thought he was going to have to move the location of the staked pole due to the existing oak tree there. Actually, this tree gets removed and an understory holly gets planted. Need to make sure the light pole gets installed in the eastern end of the parking lot island (not in the middle) to allow room to plant the holly tree in the island. Without the new curbline staked it was impossible to determine if the staked location was in the exact correct location. Prior to setting the pole, need to stake out the curb. | |||
| DRAINAGE PIPE PLACEMENT | 01/13/2016 | PARTIALLY APPROVED | GLALIMA |
| Note: BOX AND PIPE 25' FEET ON GOING WORK | |||
| BLD - UNDERGROUND SITE LIGHTING CONDUITS | 01/13/2016 | PARTIALLY APPROVED | RMARTIN |
| Note: Inspection Resulted at 1/13/2016 12:31:23 PM UNDERGROUND CONDUIT FOR SITE LIGHTING | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 01/12/2016 | PARTIALLY APPROVED | DSPENCER |
| Note: psi testing was good no loss POC to END | |||
| DRAINAGE PIPE PLACEMENT | 12/07/2015 | PARTIALLY APPROVED | DSPENCER |
| Note: Inspection Resulted at 12/7/2015 11:35:15 AM OK SO FAR | |||
| PIPE INSTALLATION | 12/03/2015 | CANCELLED BY APPLICANT | CMINI |
| LDSC-TREE BARRICADE | 11/19/2015 | APPROVED - AS NOTED | WBUTLER |
| Note: Per the contractor, only the northern portion of this phase of development is being done, so no tree barricades needed at this time. No work south of the proposed location for the loop road will be done at this time. |
Review History
| Department | Status | Date In | Date Out |
| PLLA | COMPLETE | 09/29/2015 | 10/06/2015 |
| SW1 | COMPLETE | 09/29/2015 | 09/29/2015 |
| UD1 | COMPLETE | 09/29/2015 | 09/30/2015 |
| ZON | COMPLETE | 09/29/2015 | 09/30/2015 |
| BLD | COMPLETE | 09/29/2015 | 09/29/2015 |
| DSD | COMPLETE | 09/29/2015 | 09/29/2015 |
| ENGIN1 | COMPLETE | 09/29/2015 | 09/29/2015 |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 06/20/2016 |
| REINSPECTION FEE | ¤40.00 | 05/25/2016 |
| REINSPECTION FEE | ¤40.00 | 05/25/2016 |
| INSPECTION 40 | ¤840.00 | 10/20/2015 |
| PERMIT FEE | ¤125.00 | 10/20/2015 |
| SITE PLAN 20 | ¤20.00 | 10/20/2015 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤1,105.00 |