I want to search for...
Permit #2016010283
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7058-00720-0070 |
| GARAGE: 270 sqft |
| Total Square Footage: 270 sqft |
| Block: 00720 |
| Subdivision: 2215 - SECTION 58-SEMINOLE PARK |
| Job Phone: 386-503-0906 |
| Location Address: 4 SECKEL CT |
| Type: BA - BUILDING ADDITION |
| Issue Date: 01/25/2016 |
| NOC: RECORDED |
| Applicant name: ANTHONY FALLONE |
| Owner: BAUMANN, DONALD E |
|
Address 1133 MAIN STREET PITTSTON, PA 18640 |
| Lot: 0070 |
| Contracted Stated Job Value: ¤14,000.00 |
| Job Description: GARAGE ADDITION |
| Type: CN |
Contractor
FONTANA CONSTRUCTION, INC.
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
P.O. BOX 351222 PALM COAST, FL 32137 |
CBC1250596 (Exp: 08/31/2022) | 386-503-0906 | (386)986-1305 |
Sub Contractors
MICHELE TAUSCHER
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
843 NORTH DIXIE FREEWAY NEW SMYRNA, FL 32168 |
CCC1329155 (Exp: 08/31/2026) | 386-423-0656 | 386-423-0676 |
RICHARD R EDWARDS
| Status | Location Address | State License Number | Phone |
| CANCEL |
P. O. Box 1637 Bunnell, FL 32110 |
ER0011603 (Exp: 08/31/2022) | (386) 437-1537 |
Inspection History
| Type | Request Date | Result | Inspector |
| U -UTILITY RESIDENTIAL FINAL | 06/10/2016 | FINAL APPROVED | MBACON |
| BLD - BUILDING FINAL | 06/08/2016 | FINAL APPROVED | DROCKWELL |
| FINAL SURVEY (OFFICE USE ONLY) | 05/17/2016 | APPROVED | DREWIS |
| ALL ROUGH | 04/20/2016 | APPROVED | DROCKWELL |
| TIE BEAM / LINTEL | 04/18/2016 | APPROVED - AS NOTED | DROCKWELL |
| Note: Inspection Resulted at 4/18/2016 1:34:32 PM THRU WALL CUT-OUT FOR ENTRY | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 03/31/2016 | APPROVED - AS NOTED | DROCKWELL |
| Note: Inspection Resulted at 3/31/2016 2:00:44 PM FYI CANNOT USE 15LB FELT FOR DRY-IN.USE APPROVED MATERIAL | |||
| TIE BEAM / LINTEL | 03/31/2016 | CANCELLED BY INSPECTOR | DROCKWELL |
| TIE BEAM / LINTEL | 03/21/2016 | APPROVED | DROCKWELL |
| FOUND SURVEY APPROVED (OFFICE) | 03/18/2016 | APPROVED | DREWIS |
| MONOLITHIC SLAB | 02/15/2016 | APPROVED | DROCKWELL |
| Note: THIS IS A REINSPECTION Inspection Resulted at 2/15/2016 2:06:57 PM CALL IN A GAS ROUGH INSPECTION.HAVE GAUGE ON LINE TAGGED WITH STATED PRESSURE | |||
| MONOLITHIC SLAB | 02/05/2016 | Disapproved -FEE REQUIRED | DROCKWELL |
| Note: Inspection Resulted at 2/5/2016 11:12:48 AM GAS LINE HAS BEEN INSTALLED UNDER SLAB.NEW TANK INSTALLED AND HOOKED UP TO LINE WITH NO INSPECTION.NO PERMIT.FOR THIS. TOTAL COMFORT IS THE CONTRACTOR |
Review History
| Department | Status | Date In | Date Out |
| SW1 | COMPLETE | 05/17/2016 | 05/17/2016 |
| Note: Released By: DREWIS final s | |||
| SW1 | COMPLETE | 03/18/2016 | 03/18/2016 |
| Note: Released By: DREWIS foundation s | |||
| ZON | COMPLETE | 01/20/2016 | 01/21/2016 |
| ENGIN1 | COMPLETE | 01/20/2016 | 01/20/2016 |
| Note: No work in COPC right-of-way | |||
| BLD | COMPLETE | 01/20/2016 | 01/21/2016 |
| ENGIN1 | HOLD | 01/14/2016 | 01/14/2016 |
| Note: Plans do not indicate a driveway. Please show proposed access to new garage. | |||
| BLD | HOLD | 01/14/2016 | 01/15/2016 |
| Note: 1. Provide new opening detail in concrete block as referenced on the floor plan. 2. Provide roof truss layout from the truss engineer. 5th ed. FBC 107.2.1. J. Hindman 986-3784. | |||
| SW1 | COMPLETE | 01/14/2016 | 01/15/2016 |
| ZON | HOLD | 01/14/2016 | 01/14/2016 |
| Note: Site plan must show required driveway out of allowed material (and include dimensions) leading to proposed garage addition. | |||
| ELEC | COMPLETE | 01/14/2016 | 01/15/2016 |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 06/09/2016 |
| REMODEL/ADDITION/ACCES INSPECT | ¤40.00 | 01/25/2016 |
| SITE PLAN 20 | ¤20.00 | 01/25/2016 |
| SURCHARGE FS 533.721 | ¤2.53 | 01/25/2016 |
| SURCHARGE - FS 468.631 | ¤2.53 | 01/25/2016 |
| STORM WATER PERMIT FEES | ¤80.00 | 01/25/2016 |
| ADMIN FEE | ¤20.00 | 01/25/2016 |
| ELECTRIC FEE | ¤68.40 | 01/25/2016 |
| PLAN CHECK FEE | ¤40.00 | 01/25/2016 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤313.46 |