I want to search for...

Permit #2016030534

Permit Details

Status: COED

Parcel Id: 48-11-31-1700-00000-0200
CONDITIONED SPACE: 3549 sqft
GARAGE: 780 sqft
OPENED PORCH (WITH ROOF) : 787 sqft
OPENED PORCH (WITH ROOF) : 85 sqft
Total Square Footage: 5201 sqft
Block: 00000
Subdivision: 2086 - ESTATES AT GRAND HAVEN PHASE I
Job Phone: 386-445-4747
Location Address: 19 NATIVE OAK CT
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 03/31/2016
NOC: RECORDED
Applicant name: WILLIAM VALENTINE GROFF
Owner: JENNINGS, KAREN K

Address

TRUSTEE

GRATHAM, NH 03753

Address

PO BOX 738

GRATHAM, NH 03753

Lot: 0200
Contracted Stated Job Value: ¤371,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

OCEANSIDE HOMES & REMODELING LLL
Status Location Address State License Number Phone Fax
CANCEL

4440 N OCEANSHORE BLVD SUITE 101

PALM COAST, FL 32137

CBC1256262 (Exp: 08/31/2020) 386-445-4747 386-445-5955

Sub Contractors

MARK JOHN LUTCZA
Status Location Address State License Number Phone
ACTIVE

26 ROYAL LEAF LANE

PALM COAST, FL 32164

EC13005145 (Exp: 08/31/2026) 386-586-0770
GARY LLOYD SHEFFIELD
Status Location Address State License Number Phone Fax
CANCEL

2 HARGROVE GRADE

PALM COAST, FL 32136

CAC048127 (Exp: 08/31/2018) 386-445-5023 386-446-4614
THOMAS WALTER ALBANO
Status Location Address State License Number Phone Fax
INACTIVE

P. O. BOX 352075

Palm Coast, FL 32135

CFC045991 (Exp: 08/31/2024) 386-437-2795 (386)437-2781
SANTOS L HERNANDEZ
Status Location Address State License Number Phone Fax
ACTIVE

946 SHADDICK DRIVE

ORANGE CITY, FL 32763

CCC1328011 (Exp: 08/31/2026) 386-218-4942 386-218-4937
GEORGE F AYLSWORTH JR
Status Location Address State License Number Phone Fax
DECEASED

2680 S US HIGHWAY 17

CRESCENT CITY, FL 32112

00714 (Exp: 08/31/2021) 386-698-1033 386-698-1077

Inspection History

Type Request Date Result Inspector
U -UTILITY RESIDENTIAL FINAL 06/21/2017 FINAL APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION
U -UTILITY RESIDENTIAL FINAL 06/20/2017 Disapproved -FEE REQUIRED LFITZGERALD
Note: per contractor Only 1 sewer cleanout is required,please cut,cap and bury the 4inch cleanout ,the 6inch cleanout is perferred.
FINAL APRON (AFTER POUR/DRIVEWAY) 06/19/2017 APPROVED RGROSS
Note: APPROVED
ROW FINAL 06/19/2017 APPROVED RGROSS
Note: APPROVED
BLD - BUILDING FINAL 06/14/2017 FINAL APPROVED CMINI
Note: THIS IS A REINSPECTION
BLD - BUILDING FINAL 06/13/2017 CANCELLED BY APPLICANT DROCKWELL
FINAL SURVEY (OFFICE USE ONLY) 05/16/2017 APPROVED FREODICA
ELECTRIC - EARLY POWER 04/25/2017 APPROVED - AS NOTED RMARTIN
Note: SPOKE TO DELL FPL RELEASED EARLY POWER 3:00
PRE-APRON (PRE-POUR/DRIVEWAY) 04/04/2017 APPROVED - AS NOTED CTROHA
Note: THIS IS A REINSPECTION THE BASE IS IN PLACE AND COMPACTED NOTE: HEAVY RAIN AT TIME OF INSPECTION IT IS THE BUILDERS RESPONSIBILITY TO MAINTAIN COMPACTION AND MAKE AND CORRECTIONS BEFORE LAYING PAVERS
U - SEWER TIE IN 02/20/2017 APPROVED JNICHOLS
GRAVITY SEWER TEST 02/20/2017 APPROVED CMINI
PRE-APRON (PRE-POUR/DRIVEWAY) 02/17/2017 PARTIALLY APPROVED GLALIMA
Note: WILL HAVE TO CALL IN A PRE POUR WHEN PAVER BASE IS ON SITE. READY TO POUR CONCRETE
LATH/BRICK/ WATER BARRIER 10/31/2016 APPROVED LMILLER
INSULATION 09/28/2016 APPROVED DROCKWELL
Note: THIS IS A REINSPECTION
INSULATION 09/27/2016 Disapproved -FEE REQUIRED LMILLER
Note: THIS IS A REINSPECTION REVISED ENERGY CALCS CALL FOR R-38 UNDER ATTIC (R-30 BATTS USED) DEPTH MARKERS (FOR BLOWN OR SPRAYED INSULATION) R303.1.1.2.1
INSULATION 09/26/2016 Disapproved -FEE REQUIRED LMILLER
Note: GAS PRESSURE AND BONDING OK..... BAFFLES REQUIRED 26 IN ACCORDANCE WITH FBC ENERGY CONSERVATION R303.2.1 AND MANUFACTURER SPECS. (CHANGES IN CEILING HIGHT). ALSO MASTER SHOWER DROP NEEDS BATTS (NO ACCESS AFTER CEILING IS INSTALLED)
ALL ROUGH 09/19/2016 APPROVED - AS NOTED LMILLER
Note: WILL CHECK FOR GAS BONDING AND PRESSURE TEST ON INSULATION INSPECTION (TAG WITH PRESSURE APPLIED FOR INSPECTION)
ELECTRIC-TUG 08/03/2016 APPROVED - AS NOTED RMARTIN
Note: SPOKE TO DELL FPL RELEASED TUG 3:25
ROOF SHEATHING / BRACES/TIES/DOWN CELL 08/01/2016 APPROVED CMINI
ROOF SHEATHING 07/22/2016 APPROVED - AS NOTED LMILLER
Note: OK TO COVER KNEE WALL AT FRONT ENTRY, ALL STTRAPS AND TIES IN THAT AREA WERE OBSERVED AT THIS INSPECTION
TIE BEAM / LINTEL 06/16/2016 APPROVED LMILLER
Note: THIS IS A REINSPECTION
TIE BEAM / LINTEL 06/15/2016 Disapproved -FEE REQUIRED LMILLER
Note: Inspection Resulted at 6/15/2016 12:14:00 PM DOWN CELLS R609.1.4, ALL CELLS CONTAINING REINFORCEMENT SHALL BE GROUTED SOLID (CLEAN OUT SOIL AND DEBRIS FROM DOWNCELLS)..... OVERBEND DOWEL BAR FBC R606.13.3 EXCEPTION….. WITH A VERTICAL CELL NOT MORE THAN 1” OF HORIZONTAL DISPLACEMENT TO 6” OF VERTICAL BAR LENGTH (BACK PORCH MIDDLE COLLUMN, FRONT ENTRY COLLUMNS).....
ELEV CERT-FOUNDATION APPROVAL 06/15/2016 APPROVED DRAMIREZ
Note: Per Denise Bevan and my review all looks good to release.
FOUND SURVEY APPROVED (OFFICE) 06/14/2016 APPROVED DREWIS
MONOLITHIC SLAB 05/26/2016 APPROVED - AS NOTED LMILLER
Note: Inspection Resulted at 5/26/2016 10:30:58 AM OBTAIN REVISION TO SHOW PROPER DETAILS FOR FOOTINGS IN LOCATIONS WITH RAISED WALL BY ALL ROUGH. (CONTRACTOR STATES THAT HEY ARE BUILT CORRECTLY BUT PLANS HAVE A DEFFERENT DETAIL MARKED AT THESE LOCATIONS, CONTRACTOR MAY POUR AT HIS RISK HOWEVER, PLANS MUST MATCH CONDITIONS B Y ALL ROUGH).
PLUMBING 1ST ROUGH UNDERGROUND 05/24/2016 APPROVED LMILLER
Note: THIS IS A REINSPECTION
PLUMBING 1ST ROUGH UNDERGROUND 04/28/2016 Disapproved -FEE REQUIRED LMILLER
Note: Inspection Resulted at 4/28/2016 12:27:39 PM INCOMPLETE INSPECTION, CONDITIONS AT SITE DO NOT MATCH APPROVED PLANS, (WALLS MOVED, PLUMBING MOVED, PLUMBING ADDED, ETC INSPECTION STOPPED NEED REVISION..) (10 FOOT OF HEAD PASSED, WATER PRESSURE TEST PASSED), OBTAIN APPROVED REVISION

Review History

Department Status Date In Date Out
PLFM COMPLETE 05/16/2017 05/17/2017
SW1 COMPLETE 05/15/2017 05/16/2017
Note: Released By: FREODICA final s
BLD COMPLETE 06/22/2016 06/23/2016
PLFM COMPLETE 06/14/2016 06/15/2016
Note: Per Denise Bevan and my review elevation cert is good.
SW1 COMPLETE 06/13/2016 06/14/2016
Note: Released By: DREWIS foundation s
BLD COMPLETE 06/06/2016 06/13/2016
ZON COMPLETE 05/20/2016 05/20/2016
SW1 COMPLETE 05/20/2016 05/20/2016
MECH COMPLETE 05/20/2016 05/20/2016
Note: Revision: changed energy calculations due to change in energy use from gas to electric water heater.
MECH COMPLETE 05/20/2016 05/20/2016
Note: Released By: FREODICA Revision: changed energy calculations due to chnage from gas water heater to electric.
SW1 COMPLETE 05/19/2016 05/20/2016
Note: Released By: DREWIS
ZON COMPLETE 05/19/2016 05/20/2016
Note: Released By: TCHILDS
PLUM COMPLETE 05/19/2016 05/20/2016
Note: Revision: changed water heater from gas to electric, enlarged shower at master bathroom & relocated sink.
ELEC COMPLETE 05/19/2016 05/19/2016
BLD COMPLETE 05/19/2016 05/19/2016
PLUM COMPLETE 03/29/2016 03/29/2016
ELEC COMPLETE 03/29/2016 03/29/2016
MECH COMPLETE 03/23/2016 03/24/2016
BLD COMPLETE 03/23/2016 03/28/2016
PLUM HOLD 03/23/2016 03/24/2016
Note: The pipe size 3/4 inch CSST serving water heater with 200,000 BTUH at 65 ft does not comply with FBCFG 5th edition,Table 402.4(32). F.N.Reodica -386-986-4734.
ELEC HOLD 03/23/2016 03/24/2016
Note: GFCIs need to be added to long kitchen counter top per NEC 2011 210.52 C. -DC. Rewis 986-4736
BLD HOLD 03/17/2016 03/17/2016
Note: 1. Provide the roof truss layout from the truss engineer. 5th ed. FBC 107.3.5.J. Hindman 986-3784.
ELEC HOLD 03/17/2016 03/17/2016
Note: Please provide a sign and sealed copy of electrical floor plan or electrical contractor signature accompanied by license number on submitted copy. Please add a GFCI to master bathroom vanity, NEC 2011 210.52 D. -DC. Rewis 986-4736
ENGIN1 COMPLETE 03/17/2016 03/17/2016
Note: Road is designed with curb and gutter. No swale plan is required.
MECH HOLD 03/17/2016 03/18/2016
Note: Conditioned floor area (4245 SF) on energy calculations does not match with those area shown on floor plan (3549 SF). Coordinate for clarity per FBC 5th ed. 107.2.1. F.N.Reodica -386-986-4734.
PLUM HOLD 03/17/2016 03/17/2016
Note: 1. Provide the gas consumption in BTU/hr of gas water heater to verify the required pipe size on gas riser diagram per FBCFG 5th ed. 402. F.N.Reodica - 386-986-4734. 2. Provide the size and location of gas tank and specify if it is aboveground or underground per FBC 5th ed. 107.2.1/NFPA 58 ch 6. F.N.Reodica -386-986 -4734.
SW1 COMPLETE 03/17/2016 03/17/2016
UD1 COMPLETE 03/17/2016 03/17/2016
Note: See Notes
ZON COMPLETE 03/17/2016 03/18/2016
PLFM COMPLETE 03/17/2016 03/17/2016
URB COMPLETE 03/17/2016 03/18/2016

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 06/20/2017
REINSPECTION FEE ¤40.00 06/12/2017
REINSPECTION FEE ¤40.00 06/12/2017
REINSPECTION FEE ¤40.00 06/12/2017
REINSPECTION FEE ¤40.00 06/12/2017
REVISION ¤40.00 06/12/2017
REVISION ¤40.00 06/12/2017
REVISION ¤40.00 06/12/2017
REVISION ¤40.00 06/12/2017
SITE PLAN 20 ¤20.00 03/31/2016
SURCHARGE FS 533.721 ¤32.53 03/31/2016
SURCHARGE - FS 468.631 ¤32.53 03/31/2016
STORM WATER PERMIT FEES ¤80.00 03/31/2016
3% TRANS IMPACT FEE CREDIT (¤85.71) 03/31/2016
ADMIN FEE ¤20.00 03/31/2016
ELECTRIC FEE ¤336.60 03/31/2016
3% FIRE IMPACT FEE CREDIT (¤5.84) 03/31/2016
IMPACT FEE FIRE NONRESIDENTIAL ¤194.56 03/31/2016
IMPACT FEE PARKS ¤776.46 03/31/2016
IMPACT FEE SCHOOL ¤3,291.48 03/31/2016
IMPACT FEE TRANSPORTATION ¤2,856.89 03/31/2016
MECHANICAL FEE ¤336.60 03/31/2016
3% PARKS IMPACT FEE CREDIT (¤23.29) 03/31/2016
PLAN CHECK FEE ¤184.40 03/31/2016
PLUMBING FEE ¤336.60 03/31/2016
NEW RESIDENTIAL INSPECTIONS ¤922.00 03/31/2016
Fees Total Due: ¤0.00 Total Paid: ¤9,665.81