I want to search for...
Permit #2016070499
Permit Details
Status: COED
| Parcel Id: 42-10-30-3210-00000-3390 |
| CONDITIONED SPACE: 2471 sqft |
| GARAGE: 449 sqft |
| OPENED PORCH (WITH ROOF) : 250 sqft |
| OPENED PORCH (WITH ROOF) : 36 sqft |
| Total Square Footage: 3206 sqft |
| Block: 00000 |
| Subdivision: 2094 - CONSERVATORY AT HAMMOCK BEACH |
| Job Phone: (386)383-0376 |
| Location Address: 248 CONSERVATORY DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 08/08/2016 |
| NOC: RECORDED |
| Applicant name: ANTHONY CRAIG GUCCIONE |
| Owner: OCHITWA, DONALD W & GINETTE |
|
Address 115 SEMINOLE DR NORTH BARRINGTON, IL 60010 |
| Lot: 3390 |
| Contracted Stated Job Value: ¤300,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
GOLD COAST HOME BUILDERS INC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
P.O. BOX 354707 PALM COAST, FL 32137 |
CGC1507791 (Exp: 08/31/2026) | 386-313-6221 |
Sub Contractors
BERT S MCLAUGHLIN
| Status | Location Address | State License Number | Phone |
| ACTIVE |
131 MAGNOLIA AVE DAYTONA BEACH, FL 32114 |
EC13006455 (Exp: 08/31/2026) | 386-265-2687 |
GARY LLOYD SHEFFIELD
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
2 HARGROVE GRADE PALM COAST, FL 32136 |
CAC048127 (Exp: 08/31/2018) | 386-445-5023 | 386-446-4614 |
JOHN BRADLEY WINFREY JR
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
1685 S. CLARA AVE Deland, FL 32720 |
CFC054901 (Exp: 08/31/2026) | 386-734-0154 | 386-734-2751 |
SANTOS L HERNANDEZ
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
946 SHADDICK DRIVE ORANGE CITY, FL 32763 |
CCC1328011 (Exp: 08/31/2026) | 386-218-4942 | 386-218-4937 |
Inspection History
| Type | Request Date | Result | Inspector |
| ROW - FINAL INSPECTION | 04/28/2017 | APPROVED - AS NOTED | RGROSS |
| Note: THIS IS A REINSPECTION. IN THE FUTURE ALL SET BACK AREAS OF THE POND MUST REMAIN NATURAL VEGETATION OR COVERED WITH SPARTINA PLANTS IF AREA IS DISTURBED. | |||
| U -UTILITY RESIDENTIAL FINAL | 04/28/2017 | FINAL APPROVED | DSPENCER |
| ROW - FINAL APRON (AFTER POUR) | 04/27/2017 | APPROVED - AS NOTED | RGROSS |
| Note: SUGGESTED THAT THE PAVERS SURROUNDING THE BRASS SEWER CLEANOUT BE GRINDED DOWN TO ELIMINATE THAT SHARP DEEP EDGE AROUND THE CAP | |||
| BLD - BUILDING FINAL | 04/27/2017 | FINAL APPROVED | CMINI |
| ROW - FINAL INSPECTION | 04/27/2017 | Disapproved -FEE REQUIRED | RGROSS |
| Note: NEED BAHIA SOD ALONG REAR BANK ON BOTH SIDES OF THE PROPERTY LINE TO AVOID A WASHOUT. ALSO NEED BAHIA SOD NEAR THE END OF THE SIDEWALK WHERE SEDIMENT CAN WASH OUT ONTO THE SIDEWALK AND MIAMI CURB. ON SITE WITH SUPER. | |||
| FINAL SURVEY (OFFICE USE ONLY) | 04/26/2017 | APPROVED | FREODICA |
| U - SEWER TIE IN | 02/24/2017 | APPROVED | JNICHOLS |
| ROW- PRE-APRON (PRE-POUR) | 02/15/2017 | APPROVED | GLALIMA |
| Note: READY FOR PAVERS. IF ANY ISSUES CALL GARY LA LIMA. 585-0286 | |||
| ELECTRIC - EARLY POWER | 02/10/2017 | APPROVED - AS NOTED | CMINI |
| Note: CALLED FPL TO RELEASE POWER, SPOKE WITH SUSAN | |||
| LATH/BRICK/ WATER BARRIER | 12/19/2016 | APPROVED | JCOLASANTI |
| INSULATION | 12/15/2016 | APPROVED | CMINI |
| Note: THIS IS A REINSPECTION | |||
| INSULATION | 12/14/2016 | Disapproved -FEE REQUIRED | LMILLER |
| Note: FIREBLOCKING R302.11 1-6 (MARKED BELOW ON STUDS WITH GREEN PAINT) FIREBLOCKING R302.11 (4) PIPES, DUCTS, CABLES, AND WIRES AT CEILING AND FLOOR LEVEL (WITH APPROVED MATERIAL) | |||
| ALL ROUGH | 12/08/2016 | APPROVED | CMINI |
| ROOF VALLEY & METAL | 11/17/2016 | APPROVED | CMINI |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 11/09/2016 | APPROVED | CMINI |
| Note: THIS IS A REINSPECTION | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 11/08/2016 | CANCELLED BY APPLICANT | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 11/07/2016 | Disapproved -FEE REQUIRED | CMINI |
| Note: missing straps on trusses and continuous load path, circled on roof plan | |||
| ELECTRIC-TUG | 10/27/2016 | APPROVED - AS NOTED | RMARTIN |
| Note: SPOKE TO SUSAN FPL RELEASED TUG 2:05 | |||
| TIE BEAM / LINTEL | 09/30/2016 | APPROVED | CMINI |
| Note: THIS IS A REINSPECTION | |||
| TIE BEAM / LINTEL | 09/29/2016 | Disapproved -FEE REQUIRED | LMILLER |
| Note: 1. CLEARANCE FROM MASONRY R606.13.4 MINIMUM WALL REINFORCING STEEL COVERAGE NOT MET 2. OVERBEND DOWEL BAR FBC R606.13.3 EXCEPTION 26.. WITH A VERTICAL CELL NOT MORE THAN 1 1D OF HORIZONTAL DISPLACEMENT TO 6 1D OF VERTICAL BAR LENGTH. 3. DOWN CELLS R609.1.4, ALL CELLS CONTAINING REINFORCEMENT SHALL BE GROUTED SOLID (clean out openings) (ALL CIRCLED ON PLANS) | |||
| FOUND SURVEY APPROVED (OFFICE) | 09/28/2016 | APPROVED | DREWIS |
| MONOLITHIC SLAB | 09/01/2016 | APPROVED - AS NOTED | JCOLASANTI |
| Note: need density test sticker in boxfor next inspection | |||
| GRAVITY SEWER TEST | 08/24/2016 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 08/24/2016 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| GRAVITY SEWER TEST | 08/23/2016 | Disapproved - NO FEE | CMINI |
| Note: need to cut stack down to 10' for test or fill entire pipe to top. can not tell if DWV is holding fbc P2503.5.1 | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 08/23/2016 | Disapproved -FEE REQUIRED | CMINI |
| Note: need to cut stack down to 10' for test or fill entire pipe to top. can not tell if DWV is holding fbc P2503.5.1 |
Review History
| Department | Status | Date In | Date Out |
| SW1 | COMPLETE | 04/26/2017 | 04/26/2017 |
| Note: Released By: FREODICA final s | |||
| SW1 | COMPLETE | 09/28/2016 | 09/28/2016 |
| Note: Released By: DREWIS foundation s | |||
| ENGIN1 | COMPLETE | 08/09/2016 | 08/09/2016 |
| Note: Conservatory Drive is designed with curb and gutter; therefore, a swale plan is not required. | |||
| ZON | COMPLETE | 08/09/2016 | 08/11/2016 |
| ELEC | COMPLETE | 07/21/2016 | 07/22/2016 |
| MECH | COMPLETE | 07/21/2016 | 07/22/2016 |
| PLUM | COMPLETE | 07/21/2016 | 07/22/2016 |
| BLD | COMPLETE | 07/18/2016 | 07/18/2016 |
| ELEC | HOLD | 07/18/2016 | 07/19/2016 |
| Note: Provide the following receptacles: Exterior wall in front room by master bath, NEC 2011 201.52 A. Hallway between guest bath and kitchen, NEC 210.52 H. Please provide a disconnect for the AHU, NEC 440.14. Please provide load calculations per NEC 2011 220. -DC. Rewis 986-4736 | |||
| ENGIN1 | COMPLETE | 07/18/2016 | 07/18/2016 |
| Note: Conservatory Drive is designed with curb and gutter; therefore, a swale plan is not required. | |||
| MECH | HOLD | 07/18/2016 | 07/19/2016 |
| Note: Energy performance level (EPL) display card shall be signed by the builder per FBCAEC 5th ed. R401.3. F.Reodica-386-986-4734. | |||
| PLUM | HOLD | 07/18/2016 | 07/19/2016 |
| Note: Provide sanitary riser diagram per FBC 5th ed. 107.2.1. F.Reodica -386-986-4734. | |||
| SW1 | COMPLETE | 07/18/2016 | 07/19/2016 |
| UD1 | COMPLETE | 07/18/2016 | 07/20/2016 |
| ZON | COMPLETE | 07/18/2016 | 07/20/2016 |
| URB | COMPLETE | 07/18/2016 | 07/19/2016 |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 05/01/2017 |
| REINSPECTION FEE | ¤40.00 | 05/01/2017 |
| REINSPECTION FEE | ¤40.00 | 05/01/2017 |
| REINSPECTION FEE | ¤40.00 | 05/01/2017 |
| REINSPECTION FEE | ¤40.00 | 05/01/2017 |
| NEW RESIDENTIAL INSPECTIONS | ¤608.00 | 08/08/2016 |
| SITE PLAN 20 | ¤20.00 | 08/08/2016 |
| SURCHARGE FS 533.721 | ¤22.45 | 08/08/2016 |
| SURCHARGE - FS 468.631 | ¤22.45 | 08/08/2016 |
| STORM WATER PERMIT FEES | ¤80.00 | 08/08/2016 |
| 3% TRANS IMPACT FEE CREDIT | (¤93.74) | 08/08/2016 |
| ADMIN FEE | ¤20.00 | 08/08/2016 |
| ELECTRIC FEE | ¤242.40 | 08/08/2016 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.43) | 08/08/2016 |
| IMPACT FEE FIRE NONRESIDENTIAL | ¤214.29 | 08/08/2016 |
| IMPACT FEE PARKS | ¤849.24 | 08/08/2016 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 08/08/2016 |
| IMPACT FEE TRANSPORTATION | ¤3,124.67 | 08/08/2016 |
| MECHANICAL FEE | ¤242.40 | 08/08/2016 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 08/08/2016 |
| PLAN CHECK FEE | ¤121.60 | 08/08/2016 |
| PLUMBING FEE | ¤242.40 | 08/08/2016 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤9,484.25 |