I want to search for...

Permit #2016070512

Permit Details

Status: FINAL

Subdivision: 2161 - RIGHT OF WAY/STREETS/PATHS
Job Phone: (386)322-8700
Location Address: 10000 UNIVERSAL TRL
Type: ROW - RIGHT OF WAY
Issue Date: 08/01/2016
NOC: Unknown
Applicant name: MARC ALLEN HAZEN
Owner: CITY OF PALM COAST
Job Description: 134 UNIVERSAL TRAIL - SEWER LATERAL TO CONNECT TO CITY SEWER
Type: CN

Contractor

HAZEN CONSTRUCTION LLC.
Status Location Address State License Number Phone Fax
ACTIVE

2417 TOMOKA FARMS ROAD

PORT ORANGE, FL 32128

CUC1223713 (Exp: 08/31/2026) (386)322-8700 (386)756-0000

Inspection History

Type Request Date Result Inspector
PROJECT STATUS (OFFICE USE) 09/07/2016 APPROVED DSPENCER
Note: THIS IS A REINSPECTION
ROW DAMAGE 09/07/2016 APPROVED DSPENCER
ROW FINAL 09/07/2016 APPROVED DSPENCER
PROJECT STATUS (OFFICE USE) 09/07/2016 APPROVED DSPENCER
Note: THIS IS A REINSPECTION
UC-MOT MAINTENANCE OF TRAFFIC 09/07/2016 APPROVED DSPENCER
Note: THIS IS A REINSPECTION
UC-ASPHALT PRE PLACEMENT 09/07/2016 APPROVED DSPENCER
Note: THIS IS A REINSPECTION
UC-SUBSTANTIAL WALK-THRU 09/07/2016 APPROVED DSPENCER
UC-FINAL SITE INSPECTION 09/07/2016 FINAL APPROVED DSPENCER
PROJECT STATUS (OFFICE USE) 09/06/2016 PARTIALLY APPROVED DSPENCER
Note: THIS IS A REINSPECTION road was closed with a storm with heavy rain and wind kept blowing over signs contacted contractor to secure signs road was opened for the weekend with base brought to road surface and signs layed down
PROJECT STATUS (OFFICE USE) 09/02/2016 PARTIALLY APPROVED DSPENCER
Note: THIS IS A REINSPECTION lateral was installed to the property line road base was installed to road to prevent ponding before asphalt for rain event
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 09/02/2016 APPROVED DSPENCER
UC-MOT MAINTENANCE OF TRAFFIC 09/02/2016 PARTIALLY APPROVED DSPENCER
Note: THIS IS A REINSPECTION MOT in place correct for road closed with detour
PROJECT STATUS (OFFICE USE) 09/02/2016 PARTIALLY APPROVED DSPENCER
Note: road remains closed thru rain event lateral is completed and swale is graded
U-GRAVITY SEWER INSTALL/TESTING 09/02/2016 APPROVED DSPENCER
Note: THIS IS A REINSPECTION
U-GRAVITY SEWER INSTALL/TESTING 09/01/2016 CANCELLED BY APPLICANT AIRS WEB
Note: THIS IS A REINSPECTION
UC-ASPHALT PRE PLACEMENT 09/01/2016 PARTIALLY APPROVED DSPENCER
Note: dencity reports look good filled to top with road base to last thru storm will be cut back down for asphalt when ready
PROJECT STATUS (OFFICE USE) 08/31/2016 PARTIALLY APPROVED JNICHOLS
Note: THIS IS A REINSPECTION. 8-30 dug down and installed a lateral in the sewer main. did some backfilling and had to get dry dirt there to backfill with.
PROJECT STATUS (OFFICE USE) 08/30/2016 PARTIALLY APPROVED JNICHOLS
Note: digging down in the road,
U-GRAVITY SEWER INSTALL/TESTING 08/30/2016 PARTIALLY APPROVED JNICHOLS
Note: installing a service from sewer main.
UC-MOT MAINTENANCE OF TRAFFIC 08/30/2016 PARTIALLY APPROVED JNICHOLS
Note: new service installed.

Review History

Department Status Date In Date Out
ENGIN1 COMPLETE 07/19/2016 07/19/2016
UD1 COMPLETE 07/19/2016 07/20/2016

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADMIN FEE ¤20.00 08/01/2016
STORM WATER PERMIT FEES ¤80.00 08/01/2016
Fees Total Due: ¤0.00 Total Paid: ¤100.00