| Type |
Request Date |
Result |
Inspector |
|
PROJECT STATUS (OFFICE USE) |
09/07/2016 |
APPROVED |
DSPENCER |
|
Note: THIS IS A REINSPECTION
|
|
ROW DAMAGE |
09/07/2016 |
APPROVED |
DSPENCER |
|
ROW FINAL |
09/07/2016 |
APPROVED |
DSPENCER |
|
PROJECT STATUS (OFFICE USE) |
09/07/2016 |
APPROVED |
DSPENCER |
|
Note: THIS IS A REINSPECTION
|
|
UC-MOT MAINTENANCE OF TRAFFIC |
09/07/2016 |
APPROVED |
DSPENCER |
|
Note: THIS IS A REINSPECTION
|
|
UC-ASPHALT PRE PLACEMENT |
09/07/2016 |
APPROVED |
DSPENCER |
|
Note: THIS IS A REINSPECTION
|
|
UC-SUBSTANTIAL WALK-THRU |
09/07/2016 |
APPROVED |
DSPENCER |
|
UC-FINAL SITE INSPECTION |
09/07/2016 |
FINAL APPROVED |
DSPENCER |
|
PROJECT STATUS (OFFICE USE) |
09/06/2016 |
PARTIALLY APPROVED |
DSPENCER |
|
Note: THIS IS A REINSPECTION road was closed with a storm with heavy rain and wind kept blowing over signs contacted contractor to secure signs road was opened for the weekend with base brought to road surface and signs layed down
|
|
PROJECT STATUS (OFFICE USE) |
09/02/2016 |
PARTIALLY APPROVED |
DSPENCER |
|
Note: THIS IS A REINSPECTION lateral was installed to the property line road base was installed to road to prevent ponding before asphalt for rain event
|
|
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR |
09/02/2016 |
APPROVED |
DSPENCER |
|
UC-MOT MAINTENANCE OF TRAFFIC |
09/02/2016 |
PARTIALLY APPROVED |
DSPENCER |
|
Note: THIS IS A REINSPECTION MOT in place correct for road closed with detour
|
|
PROJECT STATUS (OFFICE USE) |
09/02/2016 |
PARTIALLY APPROVED |
DSPENCER |
|
Note: road remains closed thru rain event lateral is completed and swale is graded
|
|
U-GRAVITY SEWER INSTALL/TESTING |
09/02/2016 |
APPROVED |
DSPENCER |
|
Note: THIS IS A REINSPECTION
|
|
U-GRAVITY SEWER INSTALL/TESTING |
09/01/2016 |
CANCELLED BY APPLICANT |
AIRS WEB |
|
Note: THIS IS A REINSPECTION
|
|
UC-ASPHALT PRE PLACEMENT |
09/01/2016 |
PARTIALLY APPROVED |
DSPENCER |
|
Note: dencity reports look good filled to top with road base to last thru storm will be cut back down for asphalt when ready
|
|
PROJECT STATUS (OFFICE USE) |
08/31/2016 |
PARTIALLY APPROVED |
JNICHOLS |
|
Note: THIS IS A REINSPECTION. 8-30 dug down and installed a lateral in the sewer main. did some backfilling and had to get dry dirt there to backfill with.
|
|
PROJECT STATUS (OFFICE USE) |
08/30/2016 |
PARTIALLY APPROVED |
JNICHOLS |
|
Note: digging down in the road,
|
|
U-GRAVITY SEWER INSTALL/TESTING |
08/30/2016 |
PARTIALLY APPROVED |
JNICHOLS |
|
Note: installing a service from sewer main.
|
|
UC-MOT MAINTENANCE OF TRAFFIC |
08/30/2016 |
PARTIALLY APPROVED |
JNICHOLS |
|
Note: new service installed.
|