Permit #2016120625
Permit Details
Status: COED
| CONDITIONED SPACE: 3150 sqft |
| GARAGE: 604 sqft |
| OPENED PORCH (WITH ROOF) : 578 sqft |
| OPENED PORCH (WITH ROOF) : 62 sqft |
| Total Square Footage: 4394 sqft |
| Subdivision: 2087 - ESTATES AT GRAND HAVEN PHASE II |
| Job Phone: 386-236-4133 |
| Location Address: 5 TURKEY OAK LN |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 01/27/2017 |
| NOC: RECORDED |
| Applicant name: LEONARDO CIRO SANCLEMENTE |
| Owner: LAUSIER, LUC M & JACQUELINE L |
|
Address 6326 KARMICH ST FAIRFAX STATION, VA 22039 |
| Lot: 131 |
| Contracted Stated Job Value: ¤399,736.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
INTERVEST CONSTRUCTION, INC.
| Status | Location Address | State License Number | Phone |
| CANCEL |
2379 BEVILLE RD DAYTONA BEACH, FL 32119 |
CBC1261237 (Exp: 08/31/2020) | 386-236-4133 |
Sub Contractors
STEPHEN COURTEAUX
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
85 North Yonge Street Ormond Beach, FL 32174 |
EC13001748 (Exp: 08/31/2026) | (386) 672-4900 | 386-676-7472 |
CHARLES H KULP
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
5401 ENERGY AIR CT ORLANDO, FL 32810 |
CAC018270 (Exp: 08/31/2022) | 407-886-3729 | 407-886-7580 |
GARY WAYNE EVERS
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 740106 ORANGE CITY, FL 32763 |
CFC050566 (Exp: 08/31/2026) | 386-775-0909 | 386-775-0918 |
SANTOS L HERNANDEZ
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
946 SHADDICK DRIVE ORANGE CITY, FL 32763 |
CCC1328011 (Exp: 08/31/2026) | 386-218-4942 | 386-218-4937 |
KEN DEPRINZIO
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
325 WALKER STREET HOLLY HILL, FL 32117 |
11351 (Exp: 08/31/2026) | 386-672-8494 | 386-673-7856 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 08/21/2017 | FINAL APPROVED | CMINI |
| ROW - FINAL APRON (AFTER POUR) | 08/21/2017 | APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION. APPROVED | |||
| ROW - FINAL INSPECTION | 08/21/2017 | APPROVED | RGROSS |
| Note: APPROVED | |||
| FINAL SURVEY (OFFICE USE ONLY) | 08/17/2017 | APPROVED | FREODICA |
| U -UTILITY RESIDENTIAL FINAL | 08/11/2017 | FINAL APPROVED | JNICHOLS |
| ROW - FINAL APRON (AFTER POUR) | 08/11/2017 | CANCELLED BY APPLICANT | RGROSS |
| Note: cancelled | |||
| U-CROSS CONNECTION | 08/01/2017 | APPROVED | LFITZGERALD |
| ELECTRIC - EARLY POWER | 07/24/2017 | APPROVED - AS NOTED | RMARTIN |
| Note: SPOKE TO SUSAN FPL RELEASED EARLY POWER 10:50 | |||
| ROW- PRE-APRON (PRE-POUR) | 06/23/2017 | PARTIALLY APPROVED | RGROSS |
| Note: APPROVED FOR APRON POUR. PAVER DRIVEWAY. NOTE THAT MIAMI CURB DAMAGE SHOULD BE CUT OUT AND REPAIRED DURING THE POUR. BASE ON SITE. | |||
| INSULATION | 05/31/2017 | APPROVED | CMINI |
| GAS ROUGH | 05/31/2017 | APPROVED | CMINI |
| LATH/BRICK/ WATER BARRIER | 05/26/2017 | APPROVED | CMINI |
| ALL ROUGH | 05/25/2017 | APPROVED | CMINI |
| U - SEWER TIE IN | 05/16/2017 | APPROVED | LFITZGERALD |
| GRAVITY SEWER TEST | 05/04/2017 | APPROVED | JGIBSON |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 04/26/2017 | APPROVED | LMILLER |
| ROOF VALLEY & METAL | 04/26/2017 | APPROVED | LMILLER |
| Note: THIS IS A REINSPECTION | |||
| WALL SHEATHING | 04/24/2017 | APPROVED | DROCKWELL |
| ROOF VALLEY & METAL | 04/19/2017 | PARTIALLY APPROVED | LMILLER |
| Note: LOOKED AT ROOF SHEATHING ONLY.... SUPER TRIED TO CALL IN ROOF SHEATHING BUT COULD NOT GET THE SYSTEM TO ADD IT. ROOF SHEATHING ONLY APPROVED | |||
| ELECTRIC-TUG | 04/06/2017 | APPROVED | RMARTIN |
| Note: SPOKE TO DELL FPL RELEASED TUG POWER 3:10 | |||
| ELEV CERT-FOUNDATION APPROVAL | 04/06/2017 | APPROVED | DRAMIREZ |
| TIE BEAM / LINTEL | 04/05/2017 | APPROVED | LMILLER |
| Note: THIS IS A REINSPECTION | |||
| TIE BEAM / LINTEL | 04/04/2017 | Disapproved -FEE REQUIRED | LMILLER |
| Note: CHANGES IN HEIGHT R609.2.5 AND FIGURE 609.2.5 UPPER AND LOWER BONDBEAMS MUST BE CONTINUOUSE, HAVE VERTICLE STEEL AND GROUTED SOLID AND MUST HAVE A FILLED CELL UNDER EACH CELL ADJOINING CHANGES IN HEIGHT | |||
| FOUND SURVEY APPROVED (OFFICE) | 03/30/2017 | APPROVED | JHINDMAN |
| MONOLITHIC SLAB | 03/17/2017 | APPROVED | LMILLER |
| PLUMBING 1ST ROUGH UNDERGROUND | 03/14/2017 | APPROVED | JGIBSON |
Review History
| Department | Status | Date In | Date Out |
| PLFM | COMPLETE | 08/23/2017 | 08/23/2017 |
| Note: Released By: DBEVAN Comments have been addressed. | |||
| PLFM | HOLD | 08/17/2017 | 08/18/2017 |
| Note: Held By: DBEVAN 1. For Section C2 a) through h), all elevation should be to the tenth decimal place. The previously provided elevation certificate dated 08-04-17 reflected this standard. For example C2 a) was 11.6; the submitted certificate C2 a) is 11.57. Also, update the sign-seal dates; both certificates reflect 08-04-17. 2. The final survey note #5 reflects FIRM MAP NO. 12035C0137D. The elevation certificate reflects FIRM MAP NO. 12035C0141D which is correct according to City resources. Provide an amended survey with the correct panel information. | |||
| SW1 | COMPLETE | 08/16/2017 | 08/17/2017 |
| Note: Released By: FREODICA final survey correction | |||
| PLFM | HOLD | 08/09/2017 | 08/10/2017 |
| Note: Held By: DRAMIREZ A-8 (a), (b) and (c) should be N/A and not "0" . B-9 -Base Flood Elevation of 9.0 is missing the foot mark. The base flood elevation should be 9.0'. | |||
| SW1 | HOLD | 08/07/2017 | 08/11/2017 |
| Note: Held By: JHINDMAN FINAL Survey drainage does not flow per approved plan. J. Hindman 986-3784. | |||
| SW1 | COMPLETE | 06/28/2017 | 06/28/2017 |
| Note: Released By: FREODICA FOUNDATION S (revised) | |||
| PLFM | COMPLETE | 04/05/2017 | 04/06/2017 |
| PLFM | HOLD | 03/30/2017 | 04/03/2017 |
| Note: Section A7 of the elevation certificate should reflect 1A, not 1B based on conversations conducted with certifying surveyor. | |||
| SW1 | COMPLETE | 03/30/2017 | 03/30/2017 |
| Note: Released By: JHINDMAN FOUNDATION S | |||
| PLFM | COMPLETE | 01/23/2017 | 01/24/2017 |
| Note: Elevation certificate at the "construction" stage has been deemed complete and previous comments addressed. | |||
| BLD | COMPLETE | 01/23/2017 | 01/26/2017 |
| PLFM | HOLD | 01/06/2017 | 01/06/2017 |
| Note: The provided construction plans indicate that an attached garage is being proposed. Complete Section A9 of the elevation certificate and resubmit an amended certificate. A proposed elevation was provided for Section C2.d) which dually indicates the plans for an attached garage. After review of the remaining sections, no additional errors were identified. | |||
| ELEC | COMPLETE | 01/06/2017 | 01/17/2017 |
| BLD | HOLD | 01/06/2017 | 01/17/2017 |
| Note: 1. On sheet A-3 Provide attic vent calculations that comply with 5th ed. FBC R 806.2. J. Hindman 986-3784. (50 percent is the maximum of the upper cross ventilation allowed with a 1/300 factor). | |||
| BLD | HOLD | 12/15/2016 | 12/21/2016 |
| Note: 1. On sheet A-3 Provide attic vent calculations that comply with 5th ed. FBC R 806.2. J. Hindman 986-3784. | |||
| ELEC | HOLD | 12/15/2016 | 12/21/2016 |
| Note: 1. Provide electrical load calculations per 2011 nec 220. 2. Receptacles missing in bedroom 2 and 5 on wall next to entry door with switches. 2011 NEC 210.52. J. Hindman 986-3784. | |||
| ENGIN1 | COMPLETE | 12/15/2016 | 12/15/2016 |
| MECH | COMPLETE | 12/15/2016 | 12/20/2016 |
| PLUM | COMPLETE | 12/15/2016 | 12/20/2016 |
| SW1 | COMPLETE | 12/15/2016 | 12/21/2016 |
| UD1 | COMPLETE | 12/15/2016 | 12/19/2016 |
| ZON | COMPLETE | 12/15/2016 | 12/15/2016 |
| PLFM | HOLD | 12/15/2016 | 12/19/2016 |
| Note: 1. Within Section D in the “Place Seal Here” box, the certifying professional must also sign and date on top of the seal. 2. Include Section E and G as part of resubmittal. Section G (page 4) is necessary for processing permit reviews and accommodating possible future community comments. Informational: The provided elevation certificate has been deemed sufficient at this time. Please note that an additional elevation certificate will be required at two (2) future stages: 1) Building Under Construction (at foundation) and 2) Finished Construction (final) |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 08/22/2017 |
| NEW RESIDENTIAL INSPECTIONS | ¤800.00 | 01/27/2017 |
| SITE PLAN 20 | ¤20.00 | 01/27/2017 |
| SURCHARGE FS 533.721 | ¤28.50 | 01/27/2017 |
| SURCHARGE - FS 468.631 | ¤28.50 | 01/27/2017 |
| STORM WATER PERMIT FEES | ¤80.00 | 01/27/2017 |
| 3% TRANS IMPACT FEE CREDIT | (¤93.74) | 01/27/2017 |
| ADMIN FEE | ¤20.00 | 01/27/2017 |
| ELECTRIC FEE | ¤300.00 | 01/27/2017 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.43) | 01/27/2017 |
| IMPACT FEE FIRE NONRESIDENTIAL | ¤214.29 | 01/27/2017 |
| IMPACT FEE PARKS | ¤849.24 | 01/27/2017 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 01/27/2017 |
| IMPACT FEE TRANSPORTATION | ¤3,124.67 | 01/27/2017 |
| MECHANICAL FEE | ¤300.00 | 01/27/2017 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 01/27/2017 |
| PLAN CHECK FEE | ¤160.00 | 01/27/2017 |
| PLUMBING FEE | ¤300.00 | 01/27/2017 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤9,739.55 |