Permit #2017071036
Permit Details
Status: COED
| Parcel Id: 33-11-31-3061-00030-0070 |
| CONDITIONED SPACE: 2632 sqft |
| GARAGE: 492 sqft |
| OPENED PORCH (WITH ROOF) : 331 sqft |
| OPENED PORCH (WITH ROOF) : 72 sqft |
| Total Square Footage: 3527 sqft |
| Block: 00030 |
| Subdivision: 2108 - Hidden Lakes- Phase II-Toscana |
| Job Phone: 863-420-2100 |
| Location Address: 12 NEW OAK LEAF DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 08/23/2017 |
| NOC: RECORDED |
| Applicant name: YUVAL BOTANSKY |
| Owner: APPLIED BUILDING DEVELOPMENT OF ORLANDO - PC INC |
|
Address 131 CHADWICK DRIVE DAVENPORT, FL 33837 |
|
Address 1 DAVENPORT, FL 33837 |
| Lot: 0070 |
| Contracted Stated Job Value: ¤500,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
APPLIED BUILDING DEVELOPMENT COMPANY - OAKHILLS IN
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
131 CHADWICK DRIVE DAVENPORT, FL 33837 |
CRC1330762 (Exp: 08/31/2026) | 863-420-2100 | 386-517-6865 |
Sub Contractors
TERRY HILE BURD
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
PO Box 180308 CASSELBERRY, FL 32707 |
CAC1814423 (Exp: 08/31/2024) | (407) 831-3600 | (407)831-2893 |
JONATHAN M PEARSON
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
209 N FORSYTH ST BUNNELL, FL 32110 |
CFC1425941 (Exp: 08/31/2026) | 386-597-0944 | 386-437-4996 |
SANTOS L HERNANDEZ
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
946 SHADDICK DRIVE ORANGE CITY, FL 32763 |
CCC1328011 (Exp: 08/31/2026) | 386-218-4942 | 386-218-4937 |
JOSEPH H STRADA JR
| Status | Location Address | State License Number | Phone |
| CANCEL |
3400 ST JOHNS PKWY SANFORD, FL 32771 |
EC13003715 (Exp: 08/31/2022) | 877-906-1113 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 06/12/2018 | FINAL APPROVED | DROCKWELL |
| ROW - FINAL APRON (AFTER POUR) | 06/12/2018 | APPROVED | KHOWELL |
| ROW - FINAL INSPECTION | 06/12/2018 | FINAL APPROVED | KHOWELL |
| U -UTILITY RESIDENTIAL FINAL | 06/11/2018 | FINAL APPROVED | LFITZGERALD |
| ROW - FINAL INSPECTION | 06/11/2018 | Disapproved - NO FEE | KHOWELL |
| Note: SEED AND STRAW DISTURBED AREA ON REAR VACANT LOT AND FINAL SURVEY MUST BE IN DOC BOX FOR FINAL INSPECTION | |||
| ROW - FINAL APRON (AFTER POUR) | 06/11/2018 | Disapproved -FEE REQUIRED | KHOWELL |
| Note: REPAIR PAVERS AND RESTRAINT ON UPPER LEFT SIDE OF DRIVEWAY | |||
| U-CROSS CONNECTION | 06/11/2018 | APPROVED | LFITZGERALD |
| BLD - BUILDING FINAL | 06/11/2018 | Disapproved -FEE REQUIRED | WMILLER |
| Note: 1. WEATHER STRIPPING NEEDS TO BE INSTALLED R 612.1 FBC GARAGE AND FRONT DOORS 2. TEST CAPS ON FUTURE DWV 26. P3005.1.5 PROVISIONS FOR FUTURE FIXTURES. REPLACE TEST CAPS WITH PERMANENT PLUG OR CAP FITTING (SCHEDULE 40) 3. MISSING AC REGISTER IN BEDROOM 4. VENT STACKS/PIPES FBC, R, P3103.1 MUST TERMINATE NOT LESS THAN 6 INCHES ABOVE THE ROOF | |||
| FINAL SURVEY (OFFICE USE ONLY) | 06/08/2018 | APPROVED | DREWIS |
| ROW- PRE-APRON (PRE-POUR) | 05/25/2018 | APPROVED - AS NOTED | KHOWELL |
| Note: CONTRACTOR SAID HOMEOWNER WANTED TO EXTEND THE DRIVEWAY, TOLD HIM HE WOULD NEED TO GET REVISION AND IF IT WAS NOT APPROVED IT WOULD BE REQUIRED TO BE REMOVED | |||
| ROW- PRE-APRON (PRE-POUR) | 05/22/2018 | PARTIALLY APPROVED | KHOWELL |
| Note: APRON AND SIDEWALK ONLY, PAVER UPPER DRIVEWAY | |||
| ROW- PRE-APRON (PRE-POUR) | 05/21/2018 | CANCELLED BY APPLICANT | KHOWELL |
| Note: MASON CALLED AND CANCELLED INSPECTION DUE TO RAIN | |||
| U - SEWER TIE IN | 05/14/2018 | APPROVED | LFITZGERALD |
| GRAVITY SEWER TEST | 05/14/2018 | APPROVED | JGIBSON |
| TUB SET | 05/14/2018 | APPROVED | JGIBSON |
| ELECTRIC - EARLY POWER | 05/11/2018 | APPROVED - AS NOTED | RMARTIN |
| Note: SPOKE TO SUSAN FPL RELEASED EARLY POWER 3:00 | |||
| ELECTRIC - EARLY POWER | 05/08/2018 | Disapproved -FEE REQUIRED | RMARTIN |
| Note: MICROWAVE, DISPOSAL OUTLET AND 3 GANG IN BED ROOM NEEDS TO BE SAFED OFF FOR INSPECTION | |||
| ELECTRIC-TUG | 05/02/2018 | APPROVED - AS NOTED | RMARTIN |
| Note: SPOKE TO DELL FPL RELEASED TUG POWER 4:00 | |||
| LATH/BRICK/ WATER BARRIER | 04/05/2018 | APPROVED | CMINI |
| ELECTRIC-TUG | 03/28/2018 | CANCELLED BY APPLICANT | RMARTIN |
| INSULATION | 03/09/2018 | APPROVED | CMINI |
| ELECTRIC-TUG | 03/09/2018 | Disapproved -FEE REQUIRED | RMARTIN |
| Note: NEED TO HAVE APPROVED PLANS ON SITE FOR INSPECTION, NEED TO HAVE BOTH MAIN BREAKERS INSTALLED AT THIS INSPECTION, UN-USED OPENINGS IN METER DISCONNECT NEC 110.12A | |||
| INSULATION | 03/08/2018 | Disapproved -FEE REQUIRED | DROCKWELL |
| Note: Fireblock dropped soffits at wall between living and master also dining area soffit/ Penetrations thru top plates into attic space must use rated foam if white is rated show can to verify. | |||
| ALL ROUGH | 03/02/2018 | APPROVED - AS NOTED | CMINI |
| Note: fireblocking, 10'head pressure | |||
| ROOF VALLEY & METAL | 02/09/2018 | APPROVED | CMINI |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 02/07/2018 | APPROVED | CMINI |
| Note: THIS IS A REINSPECTION | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 01/17/2018 | Disapproved -FEE REQUIRED | CMINI |
| Note: missing all engineering braces | |||
| ROOF SHEATHING | 01/09/2018 | APPROVED - AS NOTED | CMINI |
| Note: roof nailing only | |||
| TIE BEAM / LINTEL | 12/05/2017 | APPROVED | CMINI |
| FOUND SURVEY APPROVED (OFFICE) | 12/01/2017 | APPROVED | DREWIS |
| MONOLITHIC SLAB | 10/27/2017 | APPROVED | CMINI |
| PROJECT STATUS (OFFICE USE) | 10/23/2017 | CANCELLED BY INSPECTOR | BBEMBRY |
| Note: THis is a test - please respond if you receive this to bbembry@palmcoastgov.com Testing for email notifications. | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 10/20/2017 | APPROVED | JGIBSON |
| FOOTER | 09/20/2017 | APPROVED | CMINI |
Review History
| Department | Status | Date In | Date Out |
| SW1 | COMPLETE | 06/06/2018 | 06/08/2018 |
| Note: Released By: DREWIS final s | |||
| ELEC | COMPLETE | 05/01/2018 | 05/01/2018 |
| Note: Released By: DREWIS | |||
| ELEC | HOLD | 04/19/2018 | 04/23/2018 |
| Note: Held By: DREWIS Electrical contractor must register with the City of Palm Coast. Daniel Rewis 986-4736 | |||
| ELEC | HOLD | 04/02/2018 | 04/03/2018 |
| Note: Held By: DREWIS Revised riser depicts two 200amp panels to be fed by the new 300amp main. Daniel Rewis 986-4736 | |||
| SW1 | COMPLETE | 11/30/2017 | 12/01/2017 |
| Note: Released By: DREWIS foundation survey | |||
| PLENV | COMPLETE | 08/22/2017 | 08/23/2017 |
| Note: Released By: DBEVAN The provided gopher tortoise assessment has satisfied the comments. | |||
| ZON | COMPLETE | 08/17/2017 | 08/17/2017 |
| Note: Released By: TAWILLIAMS | |||
| PLENV | HOLD | 08/17/2017 | 08/18/2017 |
| Note: Held By: DBEVAN The following comment entered on 08-07-17 has not been addressed. Gopher tortoise are known to inhabit the habitat on and in the vicinity of the subject property. Provide a gopher tortoise survey by a qualified environmental professional that a burrow does not exist on or within 25 feet of the proposed construction activities. Please note that an active list of professionals determined to have met QEP criteria is currently maintained by the City’s Environmental Planner and available upon request. Contact of Environmental Planner: Denise Bevan, dbevan@palmcoastgov.com 386-986-2458. | |||
| PLENV | HOLD | 08/01/2017 | 08/07/2017 |
| Note: Held By: DBEVAN Gopher tortoise are known to inhabit the habitat on and in the vicinity of the subject property. Provide a gopher tortoise survey by a qualified environmental professional that a burrow does not exist on or within 25 feet of the proposed construction activities. Please note that an active list of professionals determined to have met QEP criteria is currently maintained by the City’s Environmental Planner and available upon request. Contact of Environmental Planner: Denise Bevan, dbevan@palmcoastgov.com 386-986-2458. | |||
| URB | COMPLETE | 08/01/2017 | 08/02/2017 |
| Note: Released By: JBEAUDET | |||
| BLD | COMPLETE | 07/31/2017 | 08/08/2017 |
| Note: Released By: JHINDMAN | |||
| ELEC | COMPLETE | 07/31/2017 | 08/07/2017 |
| Note: Released By: JHINDMAN | |||
| ENGIN1 | COMPLETE | 07/31/2017 | 08/01/2017 |
| Note: Released By: TBAKER | |||
| MECH | COMPLETE | 07/31/2017 | 08/04/2017 |
| Note: Released By: FREODICA | |||
| PLUM | COMPLETE | 07/31/2017 | 08/04/2017 |
| Note: Released By: FREODICA | |||
| SW1 | COMPLETE | 07/31/2017 | 08/07/2017 |
| Note: Released By: JHINDMAN | |||
| UD1 | COMPLETE | 07/31/2017 | 08/01/2017 |
| Note: Released By: MBACON This is a Gravity sewer, the Sewer Tie-in Inspection is a visual inspection it must be called in the day before the tie-in is to be made. The morning of the tie-in the inspector should be contacted to coordinate the time of the tie-in so he can witness the tie-in and help prevent failed inspections due to cave in or mud/water preventing the visual inspection. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap. | |||
| ZON | HOLD | 07/31/2017 | 08/01/2017 |
| Note: Held By: TAWILLIAMS Flood map panel number needs to be corrected on plot plan. The one listed doesn't match . |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 06/11/2018 |
| REINSPECTION FEE | ¤40.00 | 06/11/2018 |
| REINSPECTION FEE | ¤40.00 | 05/08/2018 |
| REVISION | ¤40.00 | 05/08/2018 |
| REINSPECTION FEE | ¤40.00 | 03/09/2018 |
| REINSPECTION FEE | ¤40.00 | 03/08/2018 |
| REINSPECTION FEE | ¤40.00 | 03/08/2018 |
| SITE PLAN 20 | ¤20.00 | 08/23/2017 |
| SURCHARGE FS 533.721 | ¤23.20 | 08/23/2017 |
| SURCHARGE - FS 468.631 | ¤34.80 | 08/23/2017 |
| STORM WATER PERMIT FEES | ¤80.00 | 08/23/2017 |
| 3% TRANS IMPACT FEE CREDIT | (¤93.74) | 08/23/2017 |
| ADMIN FEE | ¤20.00 | 08/23/2017 |
| ELECTRIC FEE | ¤360.00 | 08/23/2017 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.56) | 08/23/2017 |
| IMPACT FEE FIRE NONRESIDENTIAL | ¤218.79 | 08/23/2017 |
| IMPACT FEE PARKS | ¤849.24 | 08/23/2017 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 08/23/2017 |
| IMPACT FEE TRANSPORTATION | ¤3,124.67 | 08/23/2017 |
| MECHANICAL FEE | ¤360.00 | 08/23/2017 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 08/23/2017 |
| PLAN CHECK FEE | ¤200.00 | 08/23/2017 |
| PLUMBING FEE | ¤360.00 | 08/23/2017 |
| NEW RESIDENTIAL INSPECTIONS | ¤1,000.00 | 08/23/2017 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤10,404.92 |