Permit #2017080991

Permit Details

Status: COED

Parcel Id: 07-11-31-7059-00180-0170
CONDITIONED SPACE: 1967 sqft
OPENED PORCH (WITH ROOF) : 147 sqft
OPENED PORCH (WITH ROOF) : 33 sqft
GARAGE: 671 sqft
Total Square Footage: 2818 sqft
Block: 00180
Subdivision: -
Job Phone: 386-236-4133
Location Address: 33 SEATTLE TR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 10/24/2017
NOC: RECORDED
Applicant name: LEONARDO CIRO SANCLEMENTE
Owner: SOMERA ADELINE B

Address

8340 N CALLIE UNIT 203

MORTON GROVE, IL 60053

Lot: 0170
Contracted Stated Job Value: ¤252,733.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

INTERVEST CONSTRUCTION, INC.
Status Location Address State License Number Phone
CANCEL

2379 BEVILLE RD

DAYTONA BEACH, FL 32119

CBC1261237 (Exp: 08/31/2020) 386-236-4133

Sub Contractors

STEPHEN COURTEAUX
Status Location Address State License Number Phone Fax
ACTIVE

85 North Yonge Street

Ormond Beach, FL 32174

EC13001748 (Exp: 08/31/2026) (386) 672-4900 386-676-7472
ROBERT CRAIG KULP
Status Location Address State License Number Phone
CANCEL

5401 ENERGY AIR CT

ORLANDO, FL 32810

CAC1816317 (Exp: 08/31/2022) 407-886-3729
JEFFREY DALE KNIGHT
Status Location Address State License Number Phone Fax
INACTIVE

923 ASHMEADE CT

PORT ORANGE, FL 32127

CFC057351 (Exp: 08/31/2026) 386-345-3857 386-345-4443
BARRY D MARTIN
Status Location Address State License Number Phone Fax
CANCEL

1650 N STATE STREET

Bunnell, FL 32110

CCC033728 (Exp: 08/31/2020) (386) 437-7700 (386)437-7701

Inspection History

Type Request Date Result Inspector
ROW - FINAL APRON (AFTER POUR) 05/01/2018 CANCELLED BY APPLICANT AIRS WEB
ROW - FINAL INSPECTION 05/01/2018 APPROVED - AS NOTED CTROHA
Note: REMOVE DEBRIS FROM REAR ADJ PROPERTY
ROW - FINAL APRON (AFTER POUR) 04/27/2018 APPROVED KHOWELL
Note: THIS IS A REINSPECTION
BLD - BUILDING FINAL 04/27/2018 FINAL APPROVED WMILLER
FINAL SURVEY (OFFICE USE ONLY) 04/26/2018 APPROVED DREWIS
U -UTILITY RESIDENTIAL FINAL 04/26/2018 FINAL APPROVED MBACON
ROW - FINAL APRON (AFTER POUR) 04/26/2018 Disapproved - NO FEE KHOWELL
Note: REPAIR VOIDS IN THE CONCRETE AT THE EDGES OF THE PIPE ON THE MITERED END SECTIONS, AND REMOVE PAPER MATERIAL FROM AROUND THE THE SAME AREA WHERE WORK NEEDS TO BE DONE
U - SEWER TIE IN 04/13/2018 APPROVED MBACON
GRAVITY SEWER TEST 04/13/2018 APPROVED JGIBSON
ROW- PRE-APRON (PRE-POUR) 04/09/2018 APPROVED CTROHA
Note: READY TO POUR It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete. THIS IS A REINSPECTION
ROW- PRE-APRON (PRE-POUR) 04/06/2018 Disapproved -FEE REQUIRED CTROHA
Note: CULVERET PIPE BELOW TOLERANCE
ROW- PRE-APRON (PRE-POUR) 04/06/2018 Disapproved -FEE REQUIRED CTROHA
Note: AT THE REQUEST OF THE BUILDER I WENT BACK FOR A SAME DAY INSPECTION AND THE CULVERT SHOT AT THE SAME ELVATION ALSO THE CULVERT DOWN STREAM IS AT A 23.45 SO YOUR CULVERT NEEDS TO BE BELOW OR AT 23.6O AND ABOVE A 23.45
ROW- PRE-APRON (PRE-POUR) 04/02/2018 Disapproved -FEE REQUIRED KHOWELL
Note: DRIVEWAY NOT FORMED PER APPROVED SITE PLAN, CULVERT PIPE OVER 8 FEET OFF THE EDGE OF PAVEMENT NO EDGE OF PAVEMENT FORM.
ELECTRIC - EARLY POWER 03/26/2018 APPROVED - AS NOTED RMARTIN
Note: SPOKE TO FPL RELEASED EARLY POWER ON FRIDAY WHEN TUG WAS CALLED
ELECTRIC-TUG 03/23/2018 APPROVED - AS NOTED RMARTIN
Note: SPOKE TO DELL FPL RELEASED EARLY POWER 3:30 NOT TUG
LATH/BRICK/ WATER BARRIER 01/30/2018 APPROVED DROCKWELL
INSULATION 01/25/2018 APPROVED DROCKWELL
ALL ROUGH 01/22/2018 APPROVED DROCKWELL
ROOF VALLEY & METAL 01/17/2018 APPROVED DROCKWELL
ROOF SHEATHING / BRACES/TIES/DOWN CELL 01/11/2018 APPROVED DROCKWELL
Note: THIS IS A REINSPECTION
ROOF SHEATHING / BRACES/TIES/DOWN CELL 01/09/2018 Disapproved -FEE REQUIRED DROCKWELL
Note: Complete fireblocking perimeter walls/Provide solid blocking between trusses to nail sheathing above entry top and bottom/Strap truss above slider/secure knee wall to trusses below both sides at entry
TIE BEAM / LINTEL 12/08/2017 APPROVED DROCKWELL
FOUND SURVEY APPROVED (OFFICE) 12/07/2017 APPROVED DREWIS
MONOLITHIC SLAB 11/21/2017 APPROVED DROCKWELL
PLUMBING 1ST ROUGH UNDERGROUND 11/17/2017 APPROVED JGIBSON

Review History

Department Status Date In Date Out
SW1 COMPLETE 04/26/2018 04/26/2018
Note: Released By: DREWIS
ZON COMPLETE 02/20/2018 02/20/2018
Note: Released By: AMOBLEY
ENGIN1 COMPLETE 02/20/2018 02/23/2018
Note: Released By: TBAKER
BLD COMPLETE 02/07/2018 02/08/2018
Note: Released By: JHINDMAN
SW1 COMPLETE 12/06/2017 12/07/2017
Note: Released By: DREWIS foundation s
SW1 COMPLETE 10/16/2017 10/20/2017
Note: Released By: DREWIS
ENGIN1 COMPLETE 10/16/2017 10/18/2017
Note: Released By: TBAKER
ZON COMPLETE 10/16/2017 10/16/2017
Note: Released By: AMOBLEY
SW1 HOLD 09/27/2017 09/28/2017
Note: Held By: DREWIS Please provide additional proposed survey measurements in accordance with FBC R401.3 for: North and East sides. Third request. D. Rewis 986-4736
ELEC COMPLETE 09/27/2017 09/28/2017
Note: Released By: DREWIS
ENGIN1 COMPLETE 09/27/2017 09/28/2017
Note: Released By: TBAKER
MECH COMPLETE 09/15/2017 09/19/2017
Note: Released By: FREODICA
ENGIN1 COMPLETE 09/15/2017 09/19/2017
Note: Released By: TBAKER Held By: TBAKER Survey benchmark elevation seems to be an error.
SW1 HOLD 09/15/2017 09/19/2017
Note: Held By: JHINDMAN 1. Provide a grade with a minimum fall of 6" within the first 10 feet from the house. 5th ed. FBC R403.1. 2nd request
ELEC HOLD 09/15/2017 09/19/2017
Note: Held By: JHINDMAN 1. Provide a legible electrical plan. It is to light to read. 5th ed. FBC 107.3.5. 2nd request
BLD COMPLETE 08/25/2017 08/29/2017
Note: Released By: FREODICA
ELEC HOLD 08/25/2017 09/01/2017
Note: Held By: JHINDMAN 1. Provide a legible electrical plan. It is to light to read. 5th ed. FBC 107.3.5.
ENGIN1 COMPLETE 08/25/2017 08/30/2017
Note: Released By: TBAKER Held By: TBAKER Elevations on survey do not agree with benchmark elevation
MECH HOLD 08/25/2017 08/29/2017
Note: Held By: FREODICA Provide signature and license number of hvac contractor on hvac plan per FBC 5th ed. 105.3.1.2. F.Reodica-386-986-4734.
PLUM COMPLETE 08/25/2017 08/29/2017
Note: Released By: FREODICA
SW1 HOLD 08/25/2017 09/01/2017
Note: Held By: JHINDMAN 1. Provide a grade with a minimum fall of 6" within the first 10 feet from the house. 5th ed. FBC R403.1.
UD1 COMPLETE 08/25/2017 08/28/2017
Note: Released By: LFITZGERALD Gravity Sewer new homes This is a Gravity sewer, the Sewer Tie-in Inspection is a visual inspection it must be called in the day before the tie-in is to be made. The morning of the tie-in the inspector should be contacted to coordinate the time of the tie-in so he can witness the tie-in and help prevent failed inspections due to cave in or mud/water preventing the visual inspection. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap. The NFPA Clear Zone distance there can be no obstacles in front of the Hydrant and 7.5’ on the sides or 4’ behind.
ZON COMPLETE 08/25/2017 08/25/2017
Note: Released By: AMOBLEY

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 05/01/2018
REINSPECTION FEE ¤40.00 05/01/2018
REINSPECTION FEE ¤40.00 05/01/2018
REINSPECTION FEE ¤40.00 05/01/2018
REVISION ¤40.00 05/01/2018
SITE PLAN 20 ¤20.00 10/24/2017
SURCHARGE FS 533.721 ¤12.83 10/24/2017
SURCHARGE - FS 468.631 ¤19.24 10/24/2017
STORM WATER PERMIT FEES ¤80.00 10/24/2017
3% TRANS IMPACT FEE CREDIT (¤93.74) 10/24/2017
NEW RESIDENTIAL INSPECTIONS ¤506.00 10/24/2017
ADMIN FEE ¤20.00 10/24/2017
ELECTRIC FEE ¤211.80 10/24/2017
3% FIRE IMPACT FEE CREDIT (¤6.56) 10/24/2017
IMPACT FEE FIRE NONRESIDENTIAL ¤218.79 10/24/2017
IMPACT FEE PARKS ¤849.24 10/24/2017
IMPACT FEE SCHOOL ¤3,600.00 10/24/2017
IMPACT FEE TRANSPORTATION ¤3,124.67 10/24/2017
MECHANICAL FEE ¤211.80 10/24/2017
3% PARKS IMPACT FEE CREDIT (¤25.48) 10/24/2017
PLAN CHECK FEE ¤101.20 10/24/2017
PLUMBING FEE ¤211.80 10/24/2017
Fees Total Due: ¤0.00 Total Paid: ¤9,261.59