I want to search for...

Permit #2017081007

Permit Details

Status: COED

Parcel Id: 33-11-31-3061-00030-0040
CONDITIONED SPACE: 2443 sqft
CONDITIONED SPACE: 269 sqft
GARAGE: 764 sqft
OPENED PORCH (WITH ROOF) : 442 sqft
OPENED PORCH (WITH ROOF) : 91 sqft
Total Square Footage: 4009 sqft
Block: 00030
Subdivision: 2108 - Hidden Lakes- Phase II-Toscana
Job Phone: 863-420-2100
Location Address: 6 NEW OAK LEAF DR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 10/12/2017
NOC: RECORDED
Applicant name: YUVAL BOTANSKY
Owner: APPLIED BUILDING DEVELOPMENT OF ORLANDO - PC INC

Address

131 CHADWICK DRIVE

DAVENPORT, FL 33837

Lot: 0040
Contracted Stated Job Value: ¤250,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

APPLIED BUILDING DEVELOPMENT COMPANY - OAKHILLS IN
Status Location Address State License Number Phone Fax
ACTIVE

131 CHADWICK DRIVE

DAVENPORT, FL 33837

CRC1330762 (Exp: 08/31/2026) 863-420-2100 386-517-6865

Sub Contractors

TERRY HILE BURD
Status Location Address State License Number Phone Fax
INACTIVE

PO Box 180308

CASSELBERRY, FL 32707

CAC1814423 (Exp: 08/31/2024) (407) 831-3600 (407)831-2893
JONATHAN M PEARSON
Status Location Address State License Number Phone Fax
ACTIVE

209 N FORSYTH ST

BUNNELL, FL 32110

CFC1425941 (Exp: 08/31/2026) 386-597-0944 386-437-4996
SANTOS L HERNANDEZ
Status Location Address State License Number Phone Fax
ACTIVE

946 SHADDICK DRIVE

ORANGE CITY, FL 32763

CCC1328011 (Exp: 08/31/2026) 386-218-4942 386-218-4937
JOSEPH H STRADA JR
Status Location Address State License Number Phone
CANCEL

3400 ST JOHNS PKWY

SANFORD, FL 32771

EC13003715 (Exp: 08/31/2022) 877-906-1113

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 09/05/2018 FINAL APPROVED CMINI
U-CROSS CONNECTION 09/04/2018 APPROVED LFITZGERALD
BLD - BUILDING FINAL 09/04/2018 Disapproved -FEE REQUIRED CMINI
Note: CONDENSATE LINES SHALL DISCHARGE AT LEAST 1 FOOT AWAY FROM STRUCTURE SIDEWALL FBC R318.5 A/C condensor pad needs to have min 3" clearance from earth.M1305.1.4.1 Ground clearance. missing part of soffit in rear. missing disposal switch
ROW - FINAL APRON (AFTER POUR) 09/04/2018 APPROVED KHOWELL
ROW - FINAL INSPECTION 09/04/2018 FINAL APPROVED KHOWELL
U -UTILITY RESIDENTIAL FINAL 09/04/2018 FINAL APPROVED LFITZGERALD
Note: As discussed and agreed by Mason, re-use meter pit will be brought up to finish grade,(as much as possible by adjusting grades around) and will add some soils to north side of water meter pit so as to flush with sorrounding grades.
FINAL SURVEY (OFFICE USE ONLY) 08/30/2018 APPROVED JHINDMAN
TIE BEAM / LINTEL 08/22/2018 APPROVED - AS NOTED CMINI
Note: pool wall complete
TUB SET 08/08/2018 APPROVED JGIBSON
ELECTRIC - EARLY POWER 07/27/2018 APPROVED - AS NOTED RMARTIN
Note: SPOKE TO SUSAN FPL RELEASED EARLY POWER 3:50
ELECTRIC - EARLY POWER 07/25/2018 Disapproved -FEE REQUIRED RMARTIN
Note: EXTERIOR OUTLETS NEED TO BE INSTALLED, NEED TO BE SAFED OFF FOR INSPECTION
ROW- PRE-APRON (PRE-POUR) 07/25/2018 APPROVED KHOWELL
ROW- PRE-APRON (PRE-POUR) 07/18/2018 PARTIALLY APPROVED KHOWELL
Note: APRON AND SIDEWALK ONLY PAVER DRIVEWAY
U - SEWER TIE IN 06/08/2018 APPROVED LFITZGERALD
GRAVITY SEWER TEST 06/08/2018 APPROVED CMINI
INSULATION 05/21/2018 APPROVED CMINI
LATH/BRICK/ WATER BARRIER 04/26/2018 APPROVED CMINI
INSULATION 04/18/2018 Disapproved -FEE REQUIRED CMINI
Note: insulation does not match approved energy calculations, needs to be a vented attic.
ALL ROUGH 04/11/2018 APPROVED - AS NOTED CMINI
Note: phase out hot white conductors in panel, nail plates needed on electric and plumbing in kitchen area. need to anchor arch windows
ELECTRIC-TUG 03/16/2018 APPROVED - AS NOTED RMARTIN
Note: SPOKE TO SUSAN FPL RELEASED TUG 3:30
ROOF VALLEY & METAL 02/09/2018 APPROVED CMINI
ROOF SHEATHING / BRACES/TIES/DOWN CELL 02/08/2018 APPROVED CMINI
Note: THIS IS A REINSPECTION
ROOF SHEATHING / BRACES/TIES/DOWN CELL 02/07/2018 Disapproved -FEE REQUIRED CMINI
Note: missing tapcons on straps at front entry, missing nails in sp4s on bearing wall, missing 1 bolt in 4 ply truss
ROOF SHEATHING 01/23/2018 APPROVED CMINI
TIE BEAM / LINTEL 01/03/2018 APPROVED CMINI
FOUND SURVEY APPROVED (OFFICE) 12/22/2017 APPROVED JHINDMAN
ELECTRIC TEMP POLE 12/14/2017 APPROVED - AS NOTED RMARTIN
Note: spoke to dell fpl released temp pole 3:00
MONOLITHIC SLAB 12/14/2017 APPROVED CMINI
ELECTRIC TEMP POLE 12/08/2017 APPROVED - AS NOTED CMINI
Note: called fpl to release power at 230pm, spoke to Dell
PLUMBING 1ST ROUGH UNDERGROUND 12/07/2017 APPROVED - AS NOTED JGIBSON
Note: NEED REVISION TO SHOW PLUMBING RISER COMING OUT OF BUILDING TWICE INSTEAD OF ONCE
FOOTER 11/07/2017 APPROVED CMINI

Review History

Department Status Date In Date Out
SW1 COMPLETE 08/29/2018 08/30/2018
Note: Released By: JHINDMAN
SW1 HOLD 08/24/2018 08/29/2018
Note: Held By: JHINDMAN FINAL Survey .does not show minimum fall on right side of house 1.Lots shall be graded to drain surface water away from foundation walls. The grade shall fall a minimum of 6 inches (152 mm) within the first 10 feet per 6th ed. Florida Building Code 401.3.
MECH COMPLETE 05/18/2018 05/18/2018
Note: Released By: FREODICA Correction to revision: changed energy calculations.
MECH HOLD 05/15/2018 05/17/2018
Note: Held By: FREODICA Revision correction to energy calculations 1. Provide signature of owner/agent on energy code compliance certification per FBCEC 5th ed. R405.3. 2. Provide signature of builder on energy performance level (EPL) display card per FBCEC 5th ed. R405.4.3. F.Reodica -386-986-4734.
MECH HOLD 05/04/2018 05/08/2018
Note: Held By: FREODICA Enegy calculations shall be based on 2014 (5th edition) as the code was still in effect at the time of permit application. F.Reodica -386-986-4734.
MECH HOLD 04/24/2018 04/27/2018
Note: Held By: FREODICA Revison : Enegy calculations 1. Enegy performance level (EPL) display card shall be signed by the builder per FBCEC 6th ed. R401.3. 2. The capacity of selected hvac units shall not be more than 1.15 times greater than the total calculated cooling load per FBCEC 6th ed. R403.7.1.1. F.Reodica - 386-986-4734.
BLD COMPLETE 01/25/2018 01/29/2018
Note: Released By: JHINDMAN
SW1 COMPLETE 12/22/2017 12/22/2017
Note: Released By: JHINDMAN foundation survey
PLUM COMPLETE 12/15/2017 12/19/2017
Note: Released By: JHINDMAN
MECH COMPLETE 10/12/2017 10/12/2017
Note: Released By: FREODICA Address of new home located on top of page.
ZON COMPLETE 10/03/2017 10/04/2017
Note: Released By: TAWILLIAMS
URB COMPLETE 10/03/2017 10/04/2017
Note: Released By: JBEAUDET
MECH HOLD 10/03/2017 10/10/2017
Note: Held By: FREODICA Repeat comment for item 1: Held By: FREODICA 1. Energy performance level (EPL) display card shall be completed with date and address of the new house per FBC 5th ed. 107.2.1.
BLD COMPLETE 10/03/2017 10/10/2017
Note: Released By: JHINDMAN
URB HOLD 08/29/2017 09/05/2017
Note: Held By: JBEAUDET 9/5/17 (JB) NEED TO TRADE THE MAPLE TREE RIGHT FRONT FOR A ELM STREET TREE.
BLD HOLD 08/28/2017 09/05/2017
Note: Held By: FREODICA Provide manufacturer's specifications and installation instructions of spray foam insulation per FBCR 5th ed. R 316. F.Reodica -386-986-4734.
ELEC COMPLETE 08/28/2017 09/08/2017
Note: Released By: JHINDMAN
ENGIN1 COMPLETE 08/28/2017 08/29/2017
Note: Released By: TBAKER
MECH HOLD 08/28/2017 09/05/2017
Note: Held By: FREODICA 1. Energy performance level (EPL) display card shall completed with date and address of the new house per FBC 5th ed. 107.2.1. 2. The energy calculation shows 10 ft ceiling height but floor plan shows 12 ft. Coordinate per FBC 5th ed. 107.2.1. F.Reodica -386-986-4734.
PLUM COMPLETE 08/28/2017 09/05/2017
Note: Released By: FREODICA
SW1 COMPLETE 08/28/2017 09/19/2017
Note: Released By: JHINDMAN
UD1 COMPLETE 08/28/2017 08/30/2017
Note: Released By: MBACON This is a Gravity sewer, the Sewer Tie-in Inspection is a visual inspection it must be called in the day before the tie-in is to be made. The morning of the tie-in the inspector should be contacted to coordinate the time of the tie-in so he can witness the tie-in and help prevent failed inspections due to cave in or mud/water preventing the visual inspection. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap.
ZON HOLD 08/28/2017 08/29/2017
Note: Held By: TAWILLIAMS Survey appears to have the wrong address (street should be New Oak Leaf)

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 09/05/2018
REINSPECTION FEE ¤40.00 09/05/2018
REINSPECTION FEE ¤40.00 09/05/2018
REVISION ¤40.00 09/05/2018
REVISION ¤40.00 02/07/2018
REVISION ¤40.00 02/07/2018
REINSPECTION FEE ¤40.00 02/07/2018
SITE PLAN 20 ¤20.00 10/12/2017
SURCHARGE FS 533.721 ¤17.07 10/12/2017
SURCHARGE - FS 468.631 ¤25.60 10/12/2017
STORM WATER PERMIT FEES ¤80.00 10/12/2017
3% TRANS IMPACT FEE CREDIT (¤93.74) 10/12/2017
NEW RESIDENTIAL INSPECTIONS ¤708.00 10/12/2017
ADMIN FEE ¤20.00 10/12/2017
ELECTRIC FEE ¤272.40 10/12/2017
3% FIRE IMPACT FEE CREDIT (¤6.56) 10/12/2017
IMPACT FEE FIRE NONRESIDENTIAL ¤218.79 10/12/2017
IMPACT FEE PARKS ¤849.24 10/12/2017
IMPACT FEE SCHOOL ¤3,600.00 10/12/2017
IMPACT FEE TRANSPORTATION ¤3,124.67 10/12/2017
MECHANICAL FEE ¤272.40 10/12/2017
3% PARKS IMPACT FEE CREDIT (¤25.48) 10/12/2017
PLAN CHECK FEE ¤141.60 10/12/2017
PLUMBING FEE ¤272.40 10/12/2017
Fees Total Due: ¤0.00 Total Paid: ¤9,776.39