Permit #2018040155
Permit Details
Status: FINAL
| Parcel Id: 22-11-30-5545-00000-0020 |
| Block: 00000 |
| Subdivision: - |
| Job Phone: 386-437-3122 |
| Location Address: 4490 US HWY 1 N |
| Type: CSD - COMMERCIAL SITE DEVELOPMENT |
| Issue Date: 04/20/2018 |
| NOC: RECORDED |
| Applicant name: TERRY MARTIN MCNITT JR |
| Owner: TEAROC OF FLORIDA |
|
Address 4490 N US 1 STE 111 BUNNELL, FL 32110 |
| Lot: 0020 |
| Contracted Stated Job Value: ¤600,000.00 |
| Job Description: SITE WORK AND PAD WORK - PHASE 2 ALAMO STORAGE |
| Type: CN |
Contractor
VERDEGO LLC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 789 BUNNELL, FL 32110 |
CGC1506752 (Exp: 08/31/2026) | 386-437-3122 | 386-437-6883 |
Inspection History
| Type | Request Date | Result | Inspector |
| LDSC- LANDSCAPE / IRRIGATION AS-BUILT | 07/28/2020 | APPROVED | BDAWSON |
| Note: THIS IS A REINSPECTION ADDED ON 4/8/2020 2:18:12 PM | |||
| LDSC- LANDSCAPE FINAL | 07/21/2020 | APPROVED | BDAWSON |
| Note: THIS IS A REINSPECTION ADDED ON 7/9/2020 3:40:56 PM - All planting beds need to be weeded. - Replace any dead plants. Please note that some plants are declining. If they die prior to calling in the reinspection they will need to be replaced. - Remulch areas of bare dirt in landscape beds. | |||
| LDSC- LANDSCAPE FINAL | 07/09/2020 | Disapproved - NO FEE | BDAWSON |
| Note: - All planting beds need to be weeded. - Replace any dead plants. Please note that some plants are declining. If they die prior to calling in the reinspection they will need to be replaced. - Remulch areas of bare dirt in landscape beds. | |||
| LDSC- LANDSCAPE FINAL | 07/08/2020 | Disapproved - NO FEE | BDAWSON |
| Note: Provide final as-built prints for final landscape inspection. No permit box/as-builts on site. | |||
| IRRIGATION AFFIDAVIT | 07/08/2020 | APPROVED | BDAWSON |
| LDSC-IRRIGATION FINAL | 07/08/2020 | CANCELLED BY INSPECTOR | BDAWSON |
| Note: Affidavit provided. | |||
| U - UTILITY COMMERCIAL FINAL | 07/02/2020 | FINAL APPROVED | LFITZGERALD |
| UC-FINAL SITE INSPECTION | 07/01/2020 | FINAL APPROVED | LFITZGERALD |
| PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY | 06/23/2020 | APPROVED | LFITZGERALD |
| Note: Approved under app 4381 | |||
| MAINT BOND ACCEPTANCE (OFFICE) | 06/19/2020 | APPROVED | DRAMIREZ |
| BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS | 06/02/2020 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Truncated Domes (ADA Mats) Missing. Called contractor (Josh 586-8992) and left message. Didn't return my call. Domes installed as per ADA. | |||
| UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) | 06/02/2020 | FINAL APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION no wheeel stops and no 6in white thermo for FDOT shoulders at Exit/Entrance | |||
| BLD- ADA PARKING | 05/29/2020 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION Re-Schedule with sidewak and ramps. | |||
| UC-SUBSTANTIAL WALK-THRU | 05/11/2020 | APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION no as-builts | |||
| UC- PRELIMINARY AS-BUILTS | 05/11/2020 | APPROVED | LFITZGERALD |
| ROW - FINAL INSPECTION | 04/27/2020 | APPROVED | LFITZGERALD |
| Note: any minor issues to be captured with other inspectiomns or on the substantial punch list | |||
| UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) | 04/23/2020 | CANCELLED BY APPLICANT | LFITZGERALD |
| Note: no wheeel stops and no 6in white thermo for FDOT shoulders at Exit/Entrance | |||
| UROW - FINAL DRAINAGE | 04/23/2020 | APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION | |||
| UC-SUBSTANTIAL WALK-THRU | 04/23/2020 | CANCELLED BY APPLICANT | LFITZGERALD |
| Note: no as-builts | |||
| BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS | 04/23/2020 | Disapproved -FEE REQUIRED | FWILLIS |
| Note: THIS IS A REINSPECTION Truncated Domes (ADA Mats) Missing. Called contractor (Josh 586-8992) and left message. Didn't return my call. | |||
| BLD- ADA PARKING | 04/23/2020 | Disapproved - NO FEE | FWILLIS |
| Note: Re-Schedule with sidewak and ramps. | |||
| LDSC- SUBSTANTIAL COMPLETE (OFFICE USE) | 04/09/2020 | APPROVED - AS NOTED | MBACON |
| Note: 1. Rake mulch away from base of trees/shrubs 2. Establish tree wells as needed. 3. Install 7 Viburnum in front of south side water meter and back flow preventers for required screening. 4. Add 1 Podocarpus Hedge on south side of south storage units. | |||
| LDSC- LANDSCAPE / IRRIGATION AS-BUILT | 04/09/2020 | CANCELLED BY APPLICANT | BDAWSON |
| LDSC-TREE BARRICADE | 04/08/2020 | CANCELLED BY INSPECTOR | BDAWSON |
| U-WATER METER INSTALLATION/VERIFICATION | 04/08/2020 | APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 04/08/2020 | APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION | |||
| LDSC-PRE-PLANTING TREE QUALITY | 03/24/2020 | APPROVED - AS NOTED | BDAWSON |
| Note: Inspection completed with photos provided by installer. Not all trees were shown. At time of landscape substantial complete inspection it may be determined that the trees not shown with photographs may not meet fl grades and standards for FL #1 OR BETTER and may need replacing. | |||
| U-PUMP STATION START-UP | 03/23/2020 | APPROVED | LFITZGERALD |
| U - SEWER TIE IN | 03/18/2020 | APPROVED - AS NOTED | JGIBSON |
| Note: THIS INSPECTION WAS DONE , I PERSONALLY SAW CONNECTION TO SEWER | |||
| UROW -FINAL GRADE PRIOR SOD | 03/17/2020 | APPROVED | LFITZGERALD |
| UROW - FINAL DRAINAGE | 03/17/2020 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 03/17/2020 | APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 03/13/2020 | APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION | |||
| U-WATER METER INSTALLATION/VERIFICATION | 10/04/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-both retail store front meters now verified to their proper tie in to the appropriate backflow devices. | |||
| CONCRETE FORM | 08/19/2019 | APPROVED | JDELBONIS |
| BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS | 08/14/2019 | CANCELLED BY APPLICANT | MWILLIAMS |
| Note: not ready called in wrong inspection. | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 08/14/2019 | APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-sidewalks for both building 1/2 satisfatory for concrete placement. | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 08/02/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-silt fence now installed along bottom toe of US1 ditch line | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 07/30/2019 | Disapproved - NO FEE | LFITZGERALD |
| Note: THIS IS A REINSPECTION- This is just an accoutability disapproval regarding the front slopes that run into the US1 ROW drainage ditch where the front areas have been stripped to bare earth and sod or silt fence is pending. Josh with JW White is aware to stabilize bare soils or install silt fence where needed but there has been a time laspe of several days and this needs to be addressed with in the next 72 hours. Also,all disturbed areas along north side of property requires seed and staw. | |||
| UROW- CURBING & GUTTER | 07/30/2019 | APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-D curb all now installed | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 07/30/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-concrete collars now placed for gate valve tap and check valve vault | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 07/30/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-concrete collars now placed for 2 gate tap valves and all other valves | |||
| UC-DRAINAGE STRUCT PLACMNT | 07/30/2019 | APPROVED | LFITZGERALD |
| Note: last MES placed by Greco | |||
| UC-DRAINAGE STRUCT PLACMNT | 07/29/2019 | CANCELLED BY INSPECTOR | LFITZGERALD |
| Note: THIS IS A REINSPECTION | |||
| UC-DRAINAGE STRUCT PLACMNT | 07/26/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-entrance on US1 -2 Mitered end sections placed | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 07/26/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-wire tone test pass for water fire line by Ed Stockely | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 07/26/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-wire tone test passed for 2inc poly FM by Ed. | |||
| UROW - FINAL DRAINAGE | 07/26/2019 | CANCELLED BY APPLICANT | LFITZGERALD |
| Note: wrong inspection called in at tthis time. Should be storm water structure | |||
| UROW- CURBING & GUTTER | 07/26/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: Geco concrete now starting to place D curbing | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 07/22/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-point of connection gate valve body and check valve vault now installed properly | |||
| UC-CONSTRUCTION ENTRANCE | 07/22/2019 | APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-entrance now paved | |||
| UC-MOT MAINTENANCE OF TRAFFIC | 07/18/2019 | APPROVED | LFITZGERALD |
| U-SEWER FORCE MAIN INSTALL/TESTING | 07/18/2019 | CANCELLED BY APPLICANT | LFITZGERALD |
| Note: THIS IS A REINSPECTION | |||
| UC-ASPHALT PRE PLACEMENT | 07/16/2019 | APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-sp-9.5 asphalt now being placed | |||
| UC-ASPHALT PRE PLACEMENT | 06/26/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-stabilized sub-grade and crushed concrete base along west side of retail shops continuing to be placed and compacted | |||
| UC-ASPHALT PRE PLACEMENT | 06/20/2019 | CANCELLED BY APPLICANT | MBACON |
| Note: THIS IS A REINSPECTION per contractor Canceled inspection based on weater conditions from prvious days rain | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 04/25/2019 | CANCELLED BY APPLICANT | LFITZGERALD |
| Note: THIS IS A REINSPECTION-wrong inspection called in for dumpster pads. Manny,owner informed that a seperate permit is required for these dumpster inclosures per the building department after speaking to Demaris. | |||
| U-WATER METER INSTALLATION/VERIFICATION | 04/23/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 12 new 1 inch meters now istalled-6 at north end and 6 at south end of property.: Sensus 85274454,85274453,85274450,85274455,85274470,85274452 for retail store numbers 201 thru 206 respectively. 85274448,85274451,85274449,85274471,85274466,85274467 for retail stores 101 thru 106 respectively no water used thru meter except 10.0 gallons used in testing meter at factory as registered on each meter. Retail stores not yet constructed with just blue poly stubs. at building locations for each set of 6-one set at north end and one set at south end. | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 04/09/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-3in by 2in wet tap on existing pep main performed by Action Brothers. 2in conduit connected to corp. stop and bundled with another 2in stub for future tie in to proposed check valve | |||
| UROW-RETENT/DETENT STABILI | 04/05/2019 | APPROVED | LFITZGERALD |
| UC-ASPHALT PRE PLACEMENT | 03/29/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: stabilization along with crushed concrete (as approved by the EOR) now being placed from east to west along project between aready poured storage slabs | |||
| UC-DRAINAGE STRUCT PLACMNT | 03/01/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: Mitered end sections now starting to be formed and placed with concrete-MES along west side of pond(parking area outfall) now complete | |||
| UC-CONSTRUCTION ENTRANCE | 02/25/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION | |||
| UROW-RETENT/DETENT STABILI | 02/25/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: areas except part of South East portion sodded | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 02/25/2019 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | 02/22/2019 | PARTIALLY APPROVED | DSPENCER |
| Note: forms not completed yet | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 02/04/2019 | Disapproved - NO FEE | LFITZGERALD |
| Note: THIS IS A REINSPECTION-some areas of silt fence failures with soil erosions from previous heavy rains. Ares aong north and east lot lines and at entrance culvert ends. Contractor contacted and agrees to correct as soon as posssible . | |||
| U-WATER MAIN DISINFECTION | 12/06/2018 | APPROVED - AS NOTED | LFITZGERALD |
| Note: this inspection not applicable to this project | |||
| U-WATER MAIN DISINFECTION SAMPLING | 12/06/2018 | APPROVED - AS NOTED | LFITZGERALD |
| Note: not applicable to this project | |||
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | 11/13/2018 | APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-culvert ERCP now completed across entrance. MES'S to follow later. | |||
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | 11/09/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: ERCP(12X18IN) NOW STARTING TO BE INSTALLED ACROSS THE ENTRANCE ALONG US1 ROW. FDOT INSPECTOR-WALDO IS ALSO INSPECTING | |||
| U-GRAVITY SEWER INSTALL/TESTING | 11/08/2018 | APPROVED - AS NOTED | JGIBSON |
| Note: THIS WAS A TEST FOR UNDER GROUND MAIN SEWER LINE TO LIFT STATION | |||
| U-PUMP STATION PRE-INSTALLATION | 11/08/2018 | APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-valves manifold now installed to private can lift ststion | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 11/08/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: approx. 175 feet of 2inch greem poly with trace wire and locate tape now in proposed trenh area, to be back filled.Connection to valve manifold and tap on 3inch pep main along US1 still to be perfromed. | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | 11/07/2018 | CANCELLED BY APPLICANT | WEB |
| U-SEWER FORCE MAIN INSTALL/TESTING | 11/07/2018 | CANCELLED BY APPLICANT | WEB |
| U-GRAVITY SEWER INSTALL/TESTING | 11/07/2018 | APPROVED - AS NOTED | JGIBSON |
| Note: LOOKED AT UNDERGROUND INSTALLATION AND SPOKE WITH MIKE FROM TOMOKA CONSTRUCTION, GAVE HIM OK TO BURY LINE BUT INFORMED A 5' WATER HEAD TEST WAS NEEDED PER PLUMBING CODE | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 10/17/2018 | PARTIALLY APPROVED | DSPENCER |
| Note: two water service 2" gate valve and romex tapping saddles installed and tapped also 6" gate valve installed and tapped on fire line to existing system main for hydrants | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 10/03/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-Silt fence where eroded soils have penetrated along north side of project(adjacent to open field-parcel) now has a another row set about 10 ft. to the north and was told from Manny-Alamo owner-that the site contractor has permission to be on this property. | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 09/17/2018 | Disapproved - NO FEE | LFITZGERALD |
| Note: THIS IS A REINSPECTION- failure at NWCorner area where soils have eroded into vacant lot(at lay down arae). aLSO , MAYJOR CONCERN WHERE ALONG NORTH SIDE AT PROPERTY LINE, BUILDING PADS HAVE BEEN FILLED UP TO ABOUT 4FT. ABOVE THE SILT FENCING RIGHT NEXT TO THE SILT FENCE. Spoke with Josh of concerns iof serious erosions and he is attempting to eresolve asap .Advised him of up coming rain forcasted this week. | |||
| UC-CONSTRUCTION ENTRANCE | 09/07/2018 | Disapproved - NO FEE | LFITZGERALD |
| Note: THIS IS A REINSPECTION Construction entrance now fouled excessive soils and needs to be recharged. Will reinspect on Monday, 9/10 when corrected | |||
| U-WATER SERVICE INSTALLATION | 08/30/2018 | CANCELLED BY INSPECTOR | DSPENCER |
| Note: questions about fire main and inpections holding for clearifications Damaris project manager checking with EOR and building dept. may need fire permit. | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 08/28/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-water for fire now backfilled with locate wire and warning tape installed. A conflict resolution has to be done for the fire water/sanitary discharge lines where they run into each other at the area where the 2 RWGV's are. | |||
| U-PUMP STATION PRE-INSTALLATION | 08/24/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: sanitary pump station container now set with formed -rebar base slab. Cocrete to be placed tomorrow. | |||
| UC-CONSTRUCTION ENTRANCE | 08/24/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-clean sandy soil now placed as an approach on the exit side of cstr. entrance which is helping aid the cstr rock entrance. Soils in travel lane now minimunized. FDOT inspector-Waldo-ok with since soils now just staining asphalt surface along US1 | |||
| UC-CONSTRUCTION ENTRANCE | 08/23/2018 | Disapproved - NO FEE | LFITZGERALD |
| Note: THIS IS A REINSPECTION-cstr entrance now not funtioning due to filled in with wet site soils from rains and fill trucks existing site. Josh informed and site crews working on restoring entrance and remove soils on travel lane of US1. A reinspection will be performed by end of the day . | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 08/23/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-6inch WM now installed with 2 RWGV and 2 FIRE HYDRANTS. WM trench in process of being completely backfilled | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | 08/22/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: 6in fire-WM now being installed, no tap yet just laying pipe with 2 hydrants | |||
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | 08/21/2018 | APPROVED - AS NOTED | LFITZGERALD |
| Note: All pipe placed and backfilled up to subgrade, any remaining deficiencies if , will be covered in the punch list. | |||
| UC-DRAINAGE STRUCT PLACMNT | 08/21/2018 | APPROVED - AS NOTED | LFITZGERALD |
| Note: All rcp drainage strucuures now installed to subgrade. Remaining aspects will be inspected and if any deficiences , will be covered in the punch list. | |||
| UC-DRAINAGE STRUCT PLACMNT | 08/10/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-all RCP structures now properely set wth all on min. 12in. beding stone. Te-ins to their respective pipe runs and backfilling to be yet completed. | |||
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | 08/10/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-all RCP pipe now installed. Mudding into structures and backfilling to be comleted. | |||
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | 07/27/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: Now placing RCP from MES-A to storm inlet E-11 | |||
| UC-DRAINAGE STRUCT PLACMNT | 07/27/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: Mes-A now set , inlet E-11 next | |||
| UC-CONSTRUCTION ENTRANCE | 07/25/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-entrance observed full of soils with some tracking onto US1. Josh with JW called and more rock aded over original and tracked soils removed from US1. | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 07/16/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION-silt fence that was in disrepair along back of proposed pond,SEarea, now repaired correctly. PLEASE: monitor the back of pond where the silt fencing is installed since the berm for the pond is steep and very close to the proprety boundrary and this is where erosions are most likely to occur from rain events | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 05/03/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: walked silt fence line with Barry and showed him some areas where some improvements needed to be made. The east side where the proposed pond will be constructed and areas along US 1 Swale are the more crtical areas and asked Barry to reinforce the pond area to protect against future potential erosions and areas along the US1 Swale should be reinforced as well. As with all silt fence, the site contractor will need to keep a constant watch,especially after rain events and is responsible for the functioning value of this barrier protection. This will be an on going inspection and repairs noted /observed need to be corrected ASAP. | |||
| UC-CONSTRUCTION ENTRANCE | 05/03/2018 | PARTIALLY APPROVED | LFITZGERALD |
| Note: spoke with JW reps. Jerry yesterday and Barry today who spoke with Josh where I stated this entrance will probably require high maintanence due to close proximity to US 1 and small nature of the site especially the wet areas.It was stated at the preconstruction meeting held yesterday that the use of cattle gates or the like would benefit ,and that Josh was planning on trying to use.Possibly at both ends of the construction entrance would be helpfull Also,some more rock as discussed with Barry on site would help as well. It will be the responsibility of the site contractor to keep a constant watch and maintain accordingly. Also, please make sure none of the constuction rock gets onto US 1 roadway. This will be an on going inspection and requires to be functionalat all times and repaired if necessary ASAP. | |||
| PLAN - PRE-CON 386-986-3750 | 05/02/2018 | APPROVED | LFITZGERALD |
| UC-CONSTRUCTION ENTRANCE | 05/01/2018 | CANCELLED BY INSPECTOR | DSPENCER |
| Note: This project has not had a preconstruction meeting contact Damaris Ramirez 386-986-3750 to coordinate scheduling of procon. | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | 05/01/2018 | CANCELLED BY INSPECTOR | DSPENCER |
| Note: This project has not had a preconstruction meeting contact Damaris Ramirez 386-986-3750 to coordinate scheduling of procon. | |||
| UC-CONSTRUCTION ENTRANCE | 04/30/2018 | CANCELLED BY APPLICANT | AIRS WEB |
Review History
| Department | Status | Date In | Date Out |
| UD1 | COMPLETE | 04/19/2018 | 04/19/2018 |
| Note: Released By: CJOHNSON | |||
| BLD | COMPLETE | 04/03/2018 | 04/05/2018 |
| Note: Released By: JHINDMAN | |||
| DSD | COMPLETE | 04/03/2018 | 04/05/2018 |
| Note: Released By: DRAMIREZ | |||
| ENGIN1 | CANCEL | 04/03/2018 | 04/19/2018 |
| PLLA | COMPLETE | 04/03/2018 | 04/04/2018 |
| Note: Released By: WBUTLER | |||
| UD1 | HOLD | 04/03/2018 | 04/06/2018 |
| Note: Held By: CJOHNSON FDEP sewer permit shall be complete prior to issuance of the site development permit |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 07/27/2020 |
| SITE PLAN 20 | ¤20.00 | 04/20/2018 |
| INSPECTION 40 | ¤1,480.00 | 04/20/2018 |
| PERMIT FEE | ¤125.00 | 04/20/2018 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤1,665.00 |