Permit #2018050028

Permit Details

Status: FINAL

Parcel Id: 07-11-31-7024-00200-0010
Block: 00200
Subdivision: -
Job Phone: 386-274-3120
Location Address: 10000 GREEN CIR
Type: SDD - SUBDIVISION SITE DEVELOPMENT
Issue Date: 07/05/2018
NOC: Unknown
Applicant name: RICKY JOE ABERCROMBIE
Owner: HAMMOCK REAL ESTATE DEVELOPMENT LLC

Address

200 OCEAN CREST DRIVE #1111

PALM COAST, FL 32137

Lot: 0010
Job Description: AMERICAN VILLAGE (SUBDIVISION SITE DEVELOPMENT)
Type: CN

Contractor

TOMOKA CONSTRUCTION SERVICES, INC
Status Location Address State License Number Phone Fax
INACTIVE

810 FENTRESS CT

DAYTONA BEACH, FL 32117

CUC1224170 (Exp: 08/31/2022) 386-274-3120 386-274-3170

Inspection History

Type Request Date Result Inspector
LDSC- LANDSCAPE / IRRIGATION AS-BUILT 08/25/2021 APPROVED DRAMIREZ
Note: THIS IS A REINSPECTION UNDER APPLICATION #3959
LDSC- LANDSCAPE FINAL 08/25/2021 FINAL APPROVED LFITZGERALD
Note: As-builts have been submitted and approved.
UC-FINAL SITE INSPECTION 08/25/2021 APPROVED LFITZGERALD
Note: Per Larry this final inspection was done. He requested I close this permit.
LDSC-SITE LIGHT STAKE LOCATE 01/13/2020 CANCELLED BY INSPECTOR BDAWSON
LDSC- SUBSTANTIAL COMPLETE (OFFICE USE) 01/13/2020 APPROVED - AS NOTED BDAWSON
Note: THIS IS A REINSPECTION LANDSCAPE - ALL TREE MULCH RINGS NEED TO BE REESTABLISHED. - WEED ALL LANDSCAPE BEDS/ MULCH RINGS. - UPDATE AS-BUILTS WITH MISSING PALM TREE ON LS2 WEST ENTRANCE. - REPLACE (1) PODO ON RIGHT SIDE OF WEST ENTRANCE - REPLANTED (1) PODO FALLEN OVEN ON LEFT SIDE OF WEST ENTRANCE. - MULCH ALL BARE AREAS AND WASHED OUT AREAS. - BRING UP GRADE AT RIGHT SIDE OF WEST ENTRANCE WHERE THERE IS A DROP OFF FROM THE SIDEWALK. IRRIGATION - PROVIDE ROCK IN IRRIGATION BOXES. - ADD HEAD IN EAST ENTRANCE REAR MEDIAN TO COVER DRY SPOT. - SHOW MISSING BUBBLER FOR MISSING PALM IN AS-BUILTS OF WEST ENTRANCE.
LDSC-PRE-PLANTING TREE QUALITY 01/13/2020 APPROVED BDAWSON
Note: THIS IS A REINSPECTION
U - UTILITY COMMERCIAL FINAL 07/01/2019 FINAL APPROVED MBACON
Note: Approved as noted per Larry Fitzgerald must meet conditions as explained before house C.O. can be given.
UC-FINAL SITE INSPECTION 06/28/2019 FINAL APPROVED LFITZGERALD
UC-FINAL SITE INSPECTION 06/26/2019 CANCELLED BY APPLICANT WEB
UROW-RETENT/DETENT STABILI 06/26/2019 APPROVED - AS NOTED LFITZGERALD
Note: THIS IS A REINSPECTION-city staff agreeed for a temp. fence since NWL proposed has not yet been achieved with certain conditions noted on permit 2019051149-Please see permit number 2019051149 on CD Plus. The conditioned statement is as follows: Per the Stormwater & Engineering Department: The proposed fence shall need to be installed along the top of bank elevation. Furthermore, the fence will need to remain installed for as long as the pond remains uncompliant with the SJRWMD permit conditions. Should the pond be brought up to compliance, the City of Palm Coast Stormwater Department shall be contacted to schedule an inspection. The fence may be removed and/or replaced as per the Land Development Code fence standards following a successful inspection Per Ray Tyner Planning Manager a temporary fence permit 2019051149 for galvanized chain link fence can remain until the earlier of: C.O. of the first condo building or until June 1, 2021 (two years). Fence must be replaced with the agreed upon fence type of Black Chain Link or Alumnimum rod iron look fence. A CO hold will be placed on the addresses and permits associated with condo's,etc. until all requirements are fufilled.
UC - PROJECT STATUS 06/26/2019 APPROVED - AS NOTED LFITZGERALD
Note: THIS IS A REINSPECTION-a temp. fence has now been installed around entire top of pond thus helping to prevent potential hazard from steeep slopes due to NWL not being achieved. Please see fence and pond conditions noted on permit 2019051149
LDSC-LOCATE BACKFLOW PREVENTOR OR PAD/ ELEC TRANS 06/18/2019 CANCELLED BY INSPECTOR BDAWSON
LDSC-TREE BARRICADE 06/18/2019 CANCELLED BY INSPECTOR BDAWSON
LDSC-PRE-PLANTING TREE QUALITY 06/18/2019 Disapproved - NO FEE BDAWSON
Note: Replace two magnolias at Green Circle East Entry - not Florida No 1 or better.
LDSC- LANDSCAPE / IRRIGATION AS-BUILT 06/18/2019 CANCELLED BY APPLICANT BDAWSON
LDSC- SUBSTANTIAL COMPLETE (OFFICE USE) 06/18/2019 PARTIALLY APPROVED BDAWSON
Note: - Provide staking on trees and palms. - Reestablish all tree watering wells. - Straighten up all leaning trees. - 2 oaks and 1 magnolia planted low - raise trees (refer to drawing emailed to landscape installer) - Please note when as-built is submitted update location of shifted palm trees.
PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY 06/17/2019 APPROVED LFITZGERALD
Note: As-builts were conditionally approved under application # 3959 CMorales Approved as conditioned below (see Fence Permit No. 2019051149 for reference): A proposed fence shall need to be installed along the top of bank elevation. Furthermore, the fence will need to remain installed for as long as the pond remains uncompliant with the SJRWMD permit conditions. Should the pond be brought up to compliance, the City of Palm Coast Stormwater Department shall be contacted to schedule an inspection. The fence may be removed and/or replaced as per the Land Development Code fence standards following a successful inspection.
MAINT BOND ACCEPTANCE (OFFICE) 05/31/2019 APPROVED DRAMIREZ
Note: Maintenance Bond approved under application 3943 for the amount of $67,232.00.
UROW - FINAL DRAINAGE 05/22/2019 APPROVED LFITZGERALD
ROW - FINAL INSPECTION 05/22/2019 APPROVED LFITZGERALD
UROW-RETENT/DETENT STABILI 04/26/2019 Disapproved - NO FEE LFITZGERALD
Note: THIS IS A REINSPECTION-update:water level still lower than proposed NWL 23.80, erosions at some of the mitered end sections despite placing Coquina rip rap , and the unstabilized 2;1 is erodingat misc. areas. This pond still a potential hazard to human life. No C.O. for this site or the proposed houses being built until this situation is correctted.
UC-SUBSTANTIAL WALK-THRU 04/26/2019 APPROVED LFITZGERALD
UC- PRELIMINARY AS-BUILTS 04/26/2019 APPROVED LFITZGERALD
ROW - EROSION CONTROL / INLET PROTE/SILT FENCE 04/24/2019 APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION
UROW -FINAL GRADE PRIOR SOD 04/24/2019 APPROVED LFITZGERALD
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 04/24/2019 APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-dog park sidewalk now reconstructed with propoer ADA specifications
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 04/10/2019 Disapproved - NO FEE LFITZGERALD
Note: part of the sidewalk for the dog park does not meet the ADA standard for no greater than 5% profile(longitudial) slope. Kyle with Tomoka informed once this was inspected.
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 04/08/2019 APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-dog park, associated island to Mail area and misc. along multi-family now poured
UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) 04/08/2019 APPROVED LFITZGERALD
Note: Better Barricades placing thermo and related stop signs
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 04/05/2019 PARTIALLY APPROVED LFITZGERALD
Note: dog park and other misc. sidewalk excavated out but not yet formed
UROW- CURBING & GUTTER 04/05/2019 APPROVED LFITZGERALD
Note: remainding curb-D- for entrance islands poured
UC-MOT MAINTENANCE OF TRAFFIC 03/29/2019 APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-advance warning signs and flaggers were utilized by Tomoka Cstr. at both intersections as operations moved from one intersection to the next.
UC-ASPHALT PRE PLACEMENT 03/29/2019 APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-areas from yesterday approved again today for asphalt palcement. Weather conditions very favorablle and base was in excellent condition. P&S had their quality control rep. on site
UC-ASPHALT PRE PLACEMENT 03/28/2019 PARTIALLY APPROVED LFITZGERALD
Note: Base for President entrance , remaining of Presidential now ready along with milling the existing patch's at Pritchard /Presidential
UC - PROJECT STATUS 03/28/2019 Disapproved - NO FEE LFITZGERALD
Note: THIS IS A REINSPECTION-Detention pond Normal Water Level has not been met as proposed approved plan, the 2:1 slope which is above the eisting water level presently is eroding as well as at the mitered end sections wherer rip rap has ben added and falling away. As discussed at the TRX and informed to the owner and EOR , this storm water detention system is safty hazard and requires to be adressed before this cite can be CO and the spec. homes occupied.(see photo attached)
UC-DRAINAGE STRUCT PLACMNT 03/18/2019 APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-remaining mitered end sections now poured with concrete
UROW- CURBING & GUTTER 03/18/2019 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-remaining F and miami curb now installed at President emtrance
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 03/18/2019 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-misc. pieces of sidewalk now being installed
UROW -FINAL GRADE PRIOR SOD 03/18/2019 APPROVED LFITZGERALD
ROW - EROSION CONTROL / INLET PROTE/SILT FENCE 03/18/2019 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-rip rap now installed at all mitered end sections where erosions were occuring
PROJECT CLOSE OUT MEETING (386-986-3750) 03/04/2019 APPROVED LFITZGERALD
UC-DRAINAGE STRUCT PLACMNT 03/01/2019 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-Pond Mitered end sections now being formed and placed with concrete
UC - PROJECT STATUS 03/01/2019 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-this is to note the discrepency with the NWE(natural water elevations) proposed/designed and the actual that exist currently. All parties , city, developer, engineer and contractor made aware.
U-GRAVITY SEWER INSTALL/TESTING 03/01/2019 APPROVED LFITZGERALD
Note: ALL gravity sewer installations and testing now complete.
UC-ASPHALT PRE PLACEMENT 02/28/2019 PARTIALLY APPROVED LFITZGERALD
Note: All but the patch on Presidential/Pritchard at the existing manhle area and the President entrance(FPL Pole in conflict-scheduled to be moved) satisfactory to be paved.
UC-ASPHALT PRE PLACEMENT 02/26/2019 CANCELLED BY APPLICANT WEB
UC-CONSTRUCTION ENTRANCE 02/20/2019 APPROVED - AS NOTED LFITZGERALD
Note: THIS IS A REINSPECTION-BOTH ENTRANCES NOW BUILT WITH BASE
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 02/20/2019 APPROVED - AS NOTED LFITZGERALD
Note: THIS IS A REINSPECTION-all on site inspections completed, now waiting for DEP approval. Note-water not allowed to enter city supply until DEP clearence, can be used ,if necessary on site with a construction meter with on site containment.
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 02/20/2019 PARTIALLY APPROVED LFITZGERALD
Note: placing concrete sidewalk with machine
ROW - EROSION CONTROL / INLET PROTE/SILT FENCE 02/20/2019 Disapproved - NO FEE LFITZGERALD
Note: THIS IS A REINSPECTION-MES 4 EROSION-PHOTO INCLUDED
UROW-RETENT/DETENT STABILI 02/20/2019 Disapproved - NO FEE LFITZGERALD
Note: Retention pond as is, (since per the engineer/plan states on plans that the NWL is where the pond sould be), half way up the 4:1, the remainding pond slopes are presently not stabilized and is not in a safe condition where people are concerned. The contractor and the city engineer and other city staff have been informed. Photo included
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 02/19/2019 CANCELLED BY APPLICANT LFITZGERALD
Note: Due to expected rains, concrete pushed off
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 02/14/2019 PARTIALLY APPROVED LFITZGERALD
Note: wire tone test for water main satisfactory
U-GRAVITY SEWER INSTALL/TESTING 02/14/2019 PARTIALLY APPROVED LFITZGERALD
Note: Gravity sewer TV video/mandrel performed, COPC inspector to review once DVD/written report received
UC-DRAINAGE STRUCT PLACMNT 02/13/2019 PARTIALLY APPROVED LFITZGERALD
Note: MES's starting to be formed amd placed with concrete(Greco Concrete)
U-GRAVITY SEWER INSTALL/TESTING 02/13/2019 PARTIALLY APPROVED LFITZGERALD
Note: Air test performed for the gravity sewer-satisfactory
UC-ASPHALT PRE PLACEMENT 02/12/2019 PARTIALLY APPROVED LFITZGERALD
Note: limerock base now placedon proposed roadway except at President entrance which is forth coming
UROW- CURBING & GUTTER 02/12/2019 PARTIALLY APPROVED LFITZGERALD
Note: Misc. F curbs pieces now being constructed
UROW- CURBING & GUTTER 02/07/2019 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-F CURBING now mostly installed
UC-DRAINAGE PIPE PLACEMENT/LAMPING 02/07/2019 APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-all pipe now installed; MES'S only to be contructed
U-WATER MAIN DISINFECTION SAMPLING 02/05/2019 APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-2nd round of BAC-T samples taken
U-WATER MAIN DISINFECTION 02/04/2019 APPROVED LFITZGERALD
U-WATER MAIN DISINFECTION SAMPLING 02/04/2019 PARTIALLY APPROVED LFITZGERALD
Note: Bac-t sampling for day 1 completed today.
UC-ASPHALT PRE PLACEMENT 01/25/2019 PARTIALLY APPROVED LFITZGERALD
Note: stabilized sub-grade now in and 12inches verified. Limerock base to follow soon.
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 01/22/2019 PARTIALLY APPROVED LFITZGERALD
Note: the hydrstatic pressure test for the water main was conducted and passed the requirements
UROW- CURBING & GUTTER 01/18/2019 PARTIALLY APPROVED LFITZGERALD
Note: Greco concrete now on site starting with miami curbing install
UROW- CURBING & GUTTER 01/16/2019 CANCELLED BY APPLICANT LFITZGERALD
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 01/16/2019 PARTIALLY APPROVED LFITZGERALD
Note: the water main has now been flushed via pig method from POC at Presidential to POC at President
U-GRAVITY SEWER INSTALL/TESTING 01/15/2019 PARTIALLY APPROVED LFITZGERALD
Note: existing manhole that had a new gravity main installed through it, now has the new shelf/channel constructed with conseal applied.
UC-DRAINAGE PIPE PLACEMENT/LAMPING 01/15/2019 PARTIALLY APPROVED LFITZGERALD
Note: S 3 to MES 8 now being reinstalled per new elevations with concrete arch in the roadway section to be construced in due time. Other drainage strucures/pipe at Prseidential entrance also in process of being installed.
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 01/10/2019 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION- wet tap at President now installed
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 01/09/2019 PARTIALLY APPROVED LFITZGERALD
Note: the 8x8 2x8 wet taps were installed at Presindential, BUT unable to install the 8x8 wet tap at President due to a leaking gate valve at the bonnet. Rscheduled for tomorrow am.
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 01/08/2019 CANCELLED BY APPLICANT WEB
U-GRAVITY SEWER INSTALL/TESTING 01/08/2019 PARTIALLY APPROVED LFITZGERALD
Note: Existing manhole at Pritchard/Presidential now installed by coring a new invert with proposed gravity main; Drop manhole -MH1 also set
UC-ASPHALT PRE PLACEMENT 01/08/2019 PARTIALLY APPROVED LFITZGERALD
Note: roadway now being rouugh graded; one small area with stabilized subgrade
UC-MOT MAINTENANCE OF TRAFFIC 01/04/2019 PARTIALLY APPROVED LFITZGERALD
Note: The road closure at Pritchard/Presindential had the appropriate detour signage along with 2 Variable Electronic Message Boards on the outer limits of this closure.
UC-DRAINAGE PIPE PLACEMENT/LAMPING 01/03/2019 PARTIALLY APPROVED LFITZGERALD
Note: continuing to be installed
UC-DRAINAGE STRUCT PLACMNT 01/03/2019 PARTIALLY APPROVED LFITZGERALD
Note: continuing to be installed with the pipe associated with
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 01/03/2019 PARTIALLY APPROVED LFITZGERALD
Note: continuing to be installed
U-GRAVITY SEWER INSTALL/TESTING 12/18/2018 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-gravity main/manholes with service laterals installed now up to SSMH2
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 12/18/2018 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-water main now installed from SSMH 2 to SSMH8
UC - PROJECT STATUS 12/18/2018 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-December 12 neighborhood meeting took place with the mayjor citizen concerns were regarding to exiting to proposed sewer issues which occur during heavy rain events, which were addressed as best as possible by city staff.
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 12/07/2018 PARTIALLY APPROVED LFITZGERALD
Note: now starting to install water main just north of SSMH 2
U-GRAVITY SEWER INSTALL/TESTING 12/03/2018 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-remainig manholes now placed with the exception of SSMH-1(drop manhole)
UC - PROJECT STATUS 12/03/2018 PARTIALLY APPROVED LFITZGERALD
Note: overall construction note: with the dewatering sock system in place, all pipe/structures placements have been in mostly dry coditions. Bedding rock has been placed below all strucutures.
UC-DRAINAGE STRUCT PLACMNT 12/03/2018 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-structures continuing to be placed-13,14,,7,8 with their respective pipe runs
UC-DRAINAGE STRUCT PLACMNT 11/29/2018 PARTIALLY APPROVED LFITZGERALD
Note: started placement of storm with Curb 4 inlet to Mes run then to A4 inlet . mes 4 to be poured at later date
UC-DRAINAGE PIPE PLACEMENT/LAMPING 11/29/2018 PARTIALLY APPROVED LFITZGERALD
Note: ADS storm pipe now being placed from MES 4 to curb 4 to A4
U-GRAVITY SEWER INSTALL/TESTING 11/26/2018 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-SSMH 5,6,7 now have been set and the service laterals now being laid down to have proper planned fall to their respective property lines
UC-DRAINAGE PIPE PLACEMENT/LAMPING 11/19/2018 CANCELLED BY APPLICANT WEB
UC-DRAINAGE STRUCT PLACMNT 11/19/2018 CANCELLED BY APPLICANT WEB
U-GRAVITY SEWER INSTALL/TESTING 11/16/2018 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION GRAVITY SEWER MANHOLES 2,3,4 HAVE NOW BEEN SET
U-GRAVITY SEWER INSTALL/TESTING 11/13/2018 PARTIALLY APPROVED LFITZGERALD
Note: all manhole structures now painted grey on inside ,which arrrived onsite with black interiors. Mike with Tomoka now and possibly all day, constructing all the inverts (mudding in channels) to stucture bottoms that all came with none. Pipe is strung out to a few joints starting at MH-2. Reminded Mike of at least 12inches of rock under each strucure all the time and up to 12 -10 for the storm.
SILT FENCE 10/05/2018 CANCELLED BY INSPECTOR LFITZGERALD
Note: as discussed ,please use the 9000 codes for all SSD(site) permitted inspections
ROW - EROSION CONTROL / INLET PROTE/SILT FENCE 10/05/2018 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-outside perimeter with 20 foot buffer satisfactory
ROW - EROSION CONTROL / INLET PROTE/SILT FENCE 09/18/2018 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-modification for recreation tracts D and E approved and silt fence was wedged in and is functional and secures. Spoke with Kyle regarding trenching in for the futue silt fencing and as well as this when fill is addded when this fencing has to be raised.
SILT FENCE 09/18/2018 CANCELLED BY INSPECTOR LFITZGERALD
Note: please use the respective 9000 codes for all CSD permitted inspections, thank you
UC-MOT MAINTENANCE OF TRAFFIC 08/09/2018 PARTIALLY APPROVED LFITZGERALD
Note: Per my requst to help provide/prevent potential hazard from vehicles travelling around roadway bend along project limits, Kyle(Tomoka Construction) equally agrreed and placed Trunks Entering... Mot signs at outer areas of job boundries. It was observed while inspecting that cars are exceeeding posted speed limit and it is very dangerous entering/exiting and working along ROW for this project.
UC-CONSTRUCTION ENTRANCE 08/01/2018 PARTIALLY APPROVED LFITZGERALD
Note: 2 entrances now with rock-Spoke with Kyle-Tomoka Construction stating that in both these entrances in ROW-Swale as is now water in the swale is draining ,but , if water drainge flow stops/slowed down and water starts entering the paved roadway, a culvert pipe will be required as this is the standard; Also-relating to the rock, as long as it remains functional and/or proper maintanece keeps it funtining, then the current rock type is ok, but , if it can not be maintained properely, then the other rock will be required. This is an ongoing inspection and will be monitored.
ROW - EROSION CONTROL / INLET PROTE/SILT FENCE 08/01/2018 PARTIALLY APPROVED LFITZGERALD
Note: silt fence now installed per original plan, awaiting approved modification to silt fence around tracts D,E,F(Recreation areas). This will be an ongoing inspection to ensure this erosion control measure stays intact and funtional.
ROW - EROSION CONTROL / INLET PROTE/SILT FENCE 07/31/2018 CANCELLED BY APPLICANT WEB
PLAN - PRE-CON 386-986-3750 07/09/2018 APPROVED DRAMIREZ

Review History

Department Status Date In Date Out
UD1 COMPLETE 06/22/2018 06/22/2018
Note: Released By: CJOHNSON
DSD COMPLETE 05/10/2018 05/21/2018
Note: Released By: DRAMIREZ
UD1 HOLD 05/10/2018 05/18/2018
Note: Held By: CJOHNSON FDEP permits shall be complete prior to issuance of the Site Development permit
ENGIN1 COMPLETE 05/10/2018 06/22/2018
Note: Released By: MPEEL
PLLA COMPLETE 05/02/2018 05/02/2018
Note: Released By: WBUTLER

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADMIN COMMERCIAL ¤60.00 07/05/2018
INSPECTION 40 ¤1,040.00 07/05/2018
SITE PLAN 20 ¤20.00 07/05/2018
Fees Total Due: ¤0.00 Total Paid: ¤1,120.00