Permit #2018070770

Permit Details

Status: COED

Parcel Id: 07-11-31-7031-00060-0310
CONDITIONED SPACE: 1333 sqft
GARAGE: 406 sqft
OPENED PORCH (WITH ROOF) : 44 sqft
Total Square Footage: 1783 sqft
Block: 00060
Subdivision: 2166 - SECTION 31-ROYAL PALMS
Job Phone: (386) 246-6123
Location Address: 16 RIPPLING BROOK DR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 07/24/2018
NOC: RECORDED
Applicant name: BRIAN ANDREW GAZZOLI
Owner: TORRES-PAGAN HAYDEE URB. SIERRA BAYAMON

Address

25 B 11 CALLE 25 A

BAYAMON, PR 00961

Lot: 0310
Contracted Stated Job Value: ¤155,319.00
Job Description: SINGLE FAMILY RESIDENTIAL
Type: CN

Contractor

SEAGATE HOMES, LLC
Status Location Address Mailing Address State License Number Phone
ACTIVE

185 CYPRESS POINT PARKWAY

Palm Coast, FL 32137

SUITE 7

Palm Coast, FL 32137

CGC1518372 (Exp: 08/31/2026) 386-246-6132

Sub Contractors

RICHARD H SIMMONS JR
Status Location Address State License Number Phone Fax
ACTIVE

PO BOX 1963

BUNNELL, FL 32110

ES12001217 (Exp: 08/31/2026) 386-437-0607 386-437-1847
MICHAEL FRANK MORELLO
Status Location Address State License Number Phone Fax
ACTIVE

2 HARGROVE GRADE

PALM COAST, FL 32164

CAC052446 (Exp: 08/31/2026) 386-445-5023 386-446-4614
DENNIS GENE GAINEY
Status Location Address State License Number Phone Fax
INACTIVE

P.O. BOX 1203

Bunnell, FL 32110

CFC046004 (Exp: 08/31/2026) (386) 437-5637 386-437-3012
CHAD DAVID GRESSANI
Status Location Address State License Number Phone Fax
ACTIVE

2640 BROOKSHIRE CIRCLE

MELBOURNE, FL 32904

CCC1327235 (Exp: 08/31/2026) 321-288-6415 321-729-8997

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 02/06/2019 FINAL APPROVED DROCKWELL
ROW - FINAL APRON (AFTER POUR) 02/06/2019 FINAL APPROVED KHOWELL
ROW - FINAL INSPECTION 02/01/2019 APPROVED - AS NOTED KHOWELL
Note: THIS WILL BE REINSPECTED AFTER THE AFTER-POUR ISSUES HAVE BEEN REPAIRED
ROW - FINAL APRON (AFTER POUR) 02/01/2019 Disapproved -FEE REQUIRED KHOWELL
Note: 1. REMOVE ALL CONCRETE FROM THE CULVERT PIPE 2. THE FOOTER ON THE LEFT SIDE IS HIGHER THEN THE CULVERT INVERT
FINAL SURVEY (OFFICE USE ONLY) 01/28/2019 APPROVED JHINDMAN
U -UTILITY RESIDENTIAL FINAL 01/18/2019 FINAL APPROVED LFITZGERALD
ROW- PRE-APRON (PRE-POUR) 01/09/2019 APPROVED - AS NOTED KHOWELL
Note: ADJUST THE BOTTOM MITERED END FORM BOARDS SO THEY ARE BOTH 9" OFF THE EDGE OF PIPE NOT 12" ON ONE SIDE AND 9" ON THE OTHER SIDE. It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist READY TO POUR upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete.
ELECTRIC - EARLY POWER 12/27/2018 APPROVED JHINDMAN
GRAVITY SEWER TEST 12/13/2018 APPROVED JGIBSON
U - SEWER TIE IN 12/13/2018 APPROVED JGIBSON
LATH/BRICK/ WATER BARRIER 11/15/2018 APPROVED DROCKWELL
INSULATION 11/13/2018 APPROVED DROCKWELL
ALL ROUGH 11/08/2018 APPROVED DROCKWELL
ROOF VALLEY & METAL 10/31/2018 APPROVED DROCKWELL
ROOF SHEATHING / BRACES/TIES/DOWN CELL 10/26/2018 APPROVED DROCKWELL
TIE BEAM / LINTEL 10/17/2018 APPROVED DROCKWELL
FOUND SURVEY APPROVED (OFFICE) 10/12/2018 APPROVED DREWIS
MONOLITHIC SLAB 09/26/2018 APPROVED DROCKWELL
MONOLITHIC SLAB 09/25/2018 Disapproved -FEE REQUIRED DROCKWELL
Note: Add forms accross front and left side garage as so concrete will be contained in place
PLUMBING 1ST ROUGH UNDERGROUND 09/18/2018 APPROVED JGIBSON

Review History

Department Status Date In Date Out
SW1 COMPLETE 01/23/2019 01/28/2019
Note: Released By: JHINDMAN
SW1 COMPLETE 10/10/2018 10/12/2018
Note: Released By: DREWIS
BLD COMPLETE 07/19/2018 07/20/2018
Note: Released By: JHINDMAN
ELEC COMPLETE 07/19/2018 07/23/2018
Note: Released By: DREWIS
ENGIN1 COMPLETE 07/19/2018 07/19/2018
Note: Released By: JHOWARD
MECH COMPLETE 07/19/2018 07/24/2018
Note: Released By: FREODICA
PLUM COMPLETE 07/19/2018 07/24/2018
Note: Released By: FREODICA
SW1 COMPLETE 07/19/2018 07/23/2018
Note: Released By: DREWIS
UD1 COMPLETE 07/19/2018 07/24/2018
Note: Released By: LFITZGERALD PEP Tank areas new home This is a PEP Tank area. The Pep Panel will be placed 5 feet from the front corner of the building on the same side of the building as the PEP tank that is marked on the Utility marked Site plan. Make sure the electrician places the PEP power wire between 3 feet and 5 feet from the ground. The plumber should exit the slab with the sewer pipe on the side of the building the tank will be on and matching the utility marked site plan, this will reduce any piping under driveways or sidewalks and minimize the fall required. The sewer tie-in inspection must be called in the day before the tie-in. The morning of the tie-in the inspector should be contacted to coordinate the time of the tie-in visual inspection so he can witness the tie-in. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap. The NFPA Clear Zone distance there can be no obstacles in front of the Hydrant and 7.5’ on the sides or 4’ behind.
ZON COMPLETE 07/19/2018 07/20/2018
Note: Released By: AMOBLEY
SWALE COMPLETE 07/19/2018 09/10/2018
Note: Released By: TBAKER

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 02/06/2019
REINSPECTION FEE ¤40.00 02/06/2019
NEW RESIDENTIAL INSPECTIONS ¤332.00 07/24/2018
SITE PLAN 20 ¤20.00 07/24/2018
SURCHARGE FS 533.721 ¤9.17 07/24/2018
SURCHARGE - FS 468.631 ¤13.76 07/24/2018
STORM WATER PERMIT FEES ¤80.00 07/24/2018
3% TRANS IMPACT FEE CREDIT (¤48.96) 07/24/2018
ADMIN FEE ¤20.00 07/24/2018
ELECTRIC FEE ¤159.60 07/24/2018
3% FIRE IMPACT FEE CREDIT (¤6.56) 07/24/2018
IMPACT FEE FIRE ¤218.79 07/24/2018
IMPACT FEE PARKS ¤849.24 07/24/2018
IMPACT FEE SCHOOL ¤3,600.00 07/24/2018
IMPACT FEE TRANSPORTATION ¤1,632.00 07/24/2018
MECHANICAL FEE ¤159.60 07/24/2018
3% PARKS IMPACT FEE CREDIT (¤25.48) 07/24/2018
PLAN CHECK FEE ¤66.40 07/24/2018
PLUMBING FEE ¤159.60 07/24/2018
Fees Total Due: ¤0.00 Total Paid: ¤7,319.16