Permit #2018110059
Permit Details
Status: COED
| Parcel Id: 33-11-31-3061-00050-0050 |
| CONDITIONED SPACE: 2632 sqft |
| GARAGE: 705 sqft |
| OPENED PORCH (WITH ROOF) : 72 sqft |
| OPENED PORCH (WITH ROOF) : 331 sqft |
| Total Square Footage: 3740 sqft |
| Block: 00050 |
| Subdivision: 2108 - HIDDEN LAKES PHASE II - TOSCANA |
| Job Phone: 863-420-2100 |
| Location Address: 14 NEW LEATHERWOOD DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 03/27/2019 |
| NOC: RECORDED |
| Applicant name: YUVAL BOTANSKY |
| Owner: APPLIED BUILDING DEVELOPMENT OF ORLANDO - PC INC |
|
Address 131 CHADWICK DRIVE DAVENPORT, FL 33837 |
| Lot: 0050 |
| Contracted Stated Job Value: ¤250,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
APPLIED BUILDING DEVELOPMENT COMPANY - OAKHILLS IN
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
131 CHADWICK DRIVE DAVENPORT, FL 33837 |
CRC1330762 (Exp: 08/31/2026) | 863-420-2100 | 386-517-6865 |
Sub Contractors
JOSEPH H STRADA JR
| Status | Location Address | State License Number | Phone |
| CANCEL |
3400 ST JOHNS PKWY SANFORD, FL 32771 |
EC13003715 (Exp: 08/31/2022) | 877-906-1113 |
SANTOS L HERNANDEZ
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
946 SHADDICK DRIVE ORANGE CITY, FL 32763 |
CCC1328011 (Exp: 08/31/2026) | 386-218-4942 | 386-218-4937 |
TERRY HILE BURD
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
PO Box 180308 CASSELBERRY, FL 32707 |
CAC1814423 (Exp: 08/31/2024) | (407) 831-3600 | (407)831-2893 |
DAVID MILLER
| Status | Location Address | State License Number | Phone |
| CANCEL |
2659 MERCY DRIVE ORLANDO, FL 32808 |
06157 (Exp: 08/31/2024) | 407-466-6514 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 05/06/2020 | FINAL APPROVED | JDELBONIS |
| U-CROSS CONNECTION | 05/06/2020 | APPROVED | LFITZGERALD |
| ROW - FINAL APRON (AFTER POUR) | 05/06/2020 | APPROVED | MMAJEWSKI |
| ROW - STORMWATER FINAL | 05/06/2020 | APPROVED | MMAJEWSKI |
| U -UTILITY RESIDENTIAL FINAL | 05/06/2020 | FINAL APPROVED | LFITZGERALD |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 05/05/2020 | APPROVED | MMAJEWSKI |
| FINAL SURVEY (OFFICE USE ONLY) | 05/05/2020 | APPROVED | MMAJEWSKI |
| ELECTRIC - EARLY POWER | 05/01/2020 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED POWER 2:15 | |||
| ROOF VALLEY & METAL | 04/27/2020 | APPROVED | JDELBONIS |
| ROW- PRE-APRON (PRE-POUR) | 04/23/2020 | APPROVED | MMAJEWSKI |
| ROW- PRE-APRON (PRE-POUR) | 04/17/2020 | APPROVED | MMAJEWSKI |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION | |||
| ROW- PRE-APRON (PRE-POUR) | 04/16/2020 | Disapproved - NO FEE | MMAJEWSKI |
| Note: THIS IS A REINSPECTION PAVER RESTRAINT ALONG PROPERTY LINE NEEDS TO BE DUG OUT MORE | |||
| ROW- PRE-APRON (PRE-POUR) | 04/14/2020 | Disapproved - NO FEE | MMAJEWSKI |
| Note: SIDEWALK FORM BOARDS NEED TO BE FIXED | |||
| U - SEWER TIE IN | 03/20/2020 | APPROVED | JGIBSON |
| GRAVITY SEWER TEST | 03/20/2020 | APPROVED | JGIBSON |
| LATH/BRICK/ WATER BARRIER | 03/04/2020 | APPROVED | JDELBONIS |
| INSULATION | 02/25/2020 | APPROVED | JDELBONIS |
| ALL ROUGH | 02/20/2020 | APPROVED | JDELBONIS |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 02/20/2020 | APPROVED | JDELBONIS |
| ROOF VALLEY & METAL | 02/18/2020 | CANCELLED BY APPLICANT | WEB |
| ROOF VALLEY & METAL | 02/06/2020 | APPROVED | JDELBONIS |
| ROOF SHEATHING | 01/23/2020 | APPROVED - AS NOTED | JDELBONIS |
| Note: roof sheating only | |||
| ELECTRIC-TUG | 01/14/2020 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED POWER 2:30 | |||
| TIE BEAM / LINTEL | 01/08/2020 | APPROVED | JDELBONIS |
| FOUND SURVEY APPROVED (OFFICE) | 04/30/2019 | APPROVED | JHINDMAN |
| MONOLITHIC SLAB | 04/24/2019 | APPROVED | MWILLIAMS |
| PLUMBING 1ST ROUGH UNDERGROUND | 04/23/2019 | APPROVED | JGIBSON |
| FOOTER | 04/08/2019 | APPROVED | MWILLIAMS |
Review History
| Department | Status | Date In | Date Out |
| SW1 | COMPLETE | 04/29/2019 | 04/30/2019 |
| Note: Released By: JHINDMAN | |||
| URB | COMPLETE | 11/05/2018 | 11/13/2018 |
| Note: Released By: JBEAUDET | |||
| BLD | COMPLETE | 11/02/2018 | 11/09/2018 |
| Note: Released By: RLEE | |||
| ELEC | COMPLETE | 11/02/2018 | 11/06/2018 |
| Note: Released By: DREWIS | |||
| ENGIN1 | COMPLETE | 11/02/2018 | 11/07/2018 |
| Note: Released By: TBAKER | |||
| MECH | COMPLETE | 11/02/2018 | 11/09/2018 |
| Note: Released By: RLEE | |||
| PLUM | COMPLETE | 11/02/2018 | 11/09/2018 |
| Note: Released By: RLEE | |||
| SW1 | COMPLETE | 11/02/2018 | 11/06/2018 |
| Note: Released By: DREWIS | |||
| UD1 | COMPLETE | 11/02/2018 | 11/05/2018 |
| Note: Released By: LFITZGERALD Gravity Sewer new homes This is a Gravity sewer, the Sewer Tie-in Inspection is a visual inspection it must be called in the day before the tie-in is to be made. The morning of the tie-in the inspector should be contacted to coordinate the time of the tie-in so he can witness the tie-in and help prevent failed inspections due to cave in or mud/water preventing the visual inspection. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap. The NFPA Clear Zone distance there can be no obstacles in front of the Hydrant and 7.5’ on the sides or 4’ behind. | |||
| ZON | COMPLETE | 11/02/2018 | 11/05/2018 |
| Note: Released By: AMOBLEY |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| EXTENSION | ¤40.00 | 05/04/2020 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 03/27/2019 |
| IMPACT FEE FIRE | ¤223.38 | 03/27/2019 |
| IMPACT FEE PARKS | ¤849.24 | 03/27/2019 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 03/27/2019 |
| IMPACT FEE TRANSPORTATION | ¤2,981.00 | 03/27/2019 |
| MECHANICAL FEE | ¤262.20 | 03/27/2019 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 03/27/2019 |
| PLAN CHECK FEE | ¤134.80 | 03/27/2019 |
| PLUMBING FEE | ¤262.20 | 03/27/2019 |
| NEW RESIDENTIAL INSPECTIONS | ¤674.00 | 03/27/2019 |
| SITE PLAN 20 | ¤20.00 | 03/27/2019 |
| SURCHARGE FS 533.721 | ¤16.35 | 03/27/2019 |
| SURCHARGE - FS 468.631 | ¤24.53 | 03/27/2019 |
| STORM WATER PERMIT FEES | ¤80.00 | 03/27/2019 |
| 3% TRANS IMPACT FEE CREDIT | (¤89.43) | 03/27/2019 |
| ADMIN FEE | ¤20.00 | 03/27/2019 |
| ELECTRIC FEE | ¤262.20 | 03/27/2019 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤9,328.29 |