I want to search for...

Permit #2018120148

Permit Details

Status: COED

Parcel Id: 07-11-31-7025-00140-0290
CONDITIONED SPACE: 1571 sqft
GARAGE: 443 sqft
OPENED PORCH (WITH ROOF) : 46 sqft
OPENED PORCH (WITH ROOF) : 201 sqft
Total Square Footage: 2261 sqft
Block: 00140
Subdivision: 2189 - SECTION 25-PINE GROVE
Job Phone: 407-307-4753
Location Address: 22 PERKINS LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 01/25/2019
NOC: RECORDED
Applicant name: SHAWN VIRAG
Owner: DLP BRITE HOMES LLC

Address

605 PALENCIA CLUB DRIVE

ST AUGUSTINE, FL 32095

Lot: 0290
Contracted Stated Job Value: ¤135,466.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

SHAWNTELLE CONSULTING AND DESIGN LLC
Status Location Address State License Number Phone
CANCEL

611 LARGOVISTA DR

OAKLAND, FL 34787

CBC1261160 (Exp: 08/31/2020) 407-307-4753

Sub Contractors

TERRY BRICE DICKERSON
Status Location Address State License Number Phone
ACTIVE

4300 ST JOHN'S PARKWAY

ALPHARETTA, GA 30009

CCC1326209 (Exp: 08/31/2026) 407-548-6733
JOSEPH H STRADA JR
Status Location Address State License Number Phone
CANCEL

3400 ST JOHNS PKWY

SANFORD, FL 32771

EC13003715 (Exp: 08/31/2022) 877-906-1113
RALPH RICHARD PARROTT
Status Location Address State License Number Phone
INACTIVE

7777 WICKHAM ROAD, SUITE 12507

MELBOURNE, FL 32940

CFC1429812 (Exp: 08/31/2026) 407-568-9202
ROBERT G DELLO RUSSO
Status Location Address State License Number Phone Fax
DECEASED

531 CODISCO WAY

SANFORD, FL 32771

CAC032448 (Exp: 08/31/2022) (407)831-2665 (407)333-3853
JONATHAN M PEARSON
Status Location Address State License Number Phone Fax
ACTIVE

209 N FORSYTH ST

BUNNELL, FL 32110

CFC1425941 (Exp: 08/31/2026) 386-597-0944 386-437-4996

Inspection History

Type Request Date Result Inspector
ROW - STORMWATER FINAL 01/15/2020 APPROVED MMAJEWSKI
Note: THIS IS A REINSPECTION
U -UTILITY RESIDENTIAL FINAL 10/31/2019 APPROVED - AS NOTED LFITZGERALD
Note: Sewer cap was cossed threaded-Tom informed and was directed to correct
ROW - STORMWATER FINAL 10/31/2019 Disapproved - NO FEE MMAJEWSKI
Note: PIECES OF CONCRETE AND GARBAGE AT FRONT LEFT SIDE OF PROPERTY NEED TO BE CLEANED UP.
ROW - FINAL APRON (AFTER POUR) 10/31/2019 APPROVED MMAJEWSKI
BLD - BUILDING FINAL 10/30/2019 FINAL APPROVED JCOLASANTI
BLD - BUILDING FINAL 08/29/2019 CANCELLED BY APPLICANT WEB
ROW FIELD SURVEY /GRADING CERTIFICATION 08/06/2019 Disapproved - NO FEE RGROSS
Note: THERE IS A LOW SPOT ON THE LEFT REAR CORNER OF THE HOUSE THAT IS SUPPOSED TO DRAIN FORWARD. SEE FIELD SURVEY MARKUP.
FINAL SURVEY (OFFICE USE ONLY) 08/06/2019 APPROVED RGROSS
ELECTRIC - EARLY POWER 07/16/2019 APPROVED - AS NOTED RMARTIN
Note: SPOKE TO SUSAN FPL RELEASED POWER 3:50
ROW- PRE-APRON (PRE-POUR) 07/10/2019 APPROVED - AS NOTED KHOWELL
Note: THE APPROVED SITE PLAN IS REQUIRED TO BE IN THE DOC BOX FOR THIS INSPECTION SO THE BENCH MARK CAN BE VERIFIED. It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist READY TO POUR upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete.
U - SEWER TIE IN 07/01/2019 APPROVED - AS NOTED JGIBSON
Note: VIDEO SENT BY PLUMBER FOR U-TIE IN
GRAVITY SEWER TEST 07/01/2019 APPROVED JGIBSON
LATH/BRICK/ WATER BARRIER 05/29/2019 APPROVED WMILLER
INSULATION 05/23/2019 APPROVED JCOLASANTI
ALL ROUGH 05/21/2019 APPROVED - AS NOTED JCOLASANTI
Note: THIS IS A REINSPECTION need to bond metal box in master bedroom
ALL ROUGH 05/20/2019 Disapproved -FEE REQUIRED JCOLASANTI
Note: THIS IS A REINSPECTION Add bolt at ledger board and tighten right side bolt....fix knockout in panel....bond metal boxes....fresh air duct needs to e extended to drop ceiling height at porch....need to completly mastic the dryer vent....BEARING WALLS DRILLING AND KNOTCHING-STUDS..FBC…602.1.4……. TOP PLATES.FBC.. .602.6.1 ( need correct plate and place 6" past the edge of holes at kitchen /bath vet pipe through barring wall)...
ALL ROUGH 05/17/2019 Disapproved -FEE REQUIRED JCOLASANTI
Note: Add bolt at ledger board and tighten right side bolt/Provide solid blocking between trusses top and bottom as so sheathing can be nailed per plan right of entry.Will check next inspection (not completed from roof sheathing inspection)
ROOF VALLEY & METAL 05/10/2019 APPROVED MWILLIAMS
ROOF SHEATHING / BRACES/TIES/DOWN CELL 05/09/2019 APPROVED - AS NOTED DROCKWELL
Note: Add bolt at ledger board and tighten right side bolt/Provide solid blocking between trusses top and bottom as so sheathing can be nailed per plan right of entry.Will check next inspection
TIE BEAM / LINTEL 04/24/2019 APPROVED WMILLER
Note: THIS IS A REINSPECTION DEFICIENCIES NOTED BY INSPECTOR JC PRIOR RESOLVED
ELECTRIC-TUG 04/24/2019 APPROVED - AS NOTED RMARTIN
Note: SPOKE TO DELL FPL RELEASED POWER 3:20
TIE BEAM / LINTEL 04/18/2019 Disapproved -FEE REQUIRED JCOLASANTI
Note: THIS IS A REINSPECTION etter needs to be approved by COPC and approved sheet must be on site at time of inspection...detail S11 shows steel in cells, no steel in cells on site. FBC 802
TIE BEAM / LINTEL 04/11/2019 Disapproved -FEE REQUIRED JCOLASANTI
Note: missing cell right side wall...need cell at header front entry per code marked on floor plan......need to tie in bock at raise section to house at entry FBC 802
FOUND SURVEY APPROVED (OFFICE) 04/10/2019 APPROVED JHINDMAN
MONOLITHIC SLAB 04/01/2019 APPROVED WMILLER
Note: THIS IS A REINSPECTION
MONOLITHIC SLAB 03/26/2019 Disapproved -FEE REQUIRED WMILLER
Note: THIS IS A REINSPECTION 12 inch MINIMUM DEPTH , UNDISTURBED GROUND SURFACE… (6TH EDITION) R403.1.3.4 and in accordance with R401.2, and R403.1 ALL FOOTINGS SHALL BE PLACED AT LEAST 12 in. BELOW THE UNDISTURBED GROUND SURFACE (NEED ADDITIONAL COMPACTION REPORT FOR AREAS OUTSIDE OF FOOTINGS AFTER ADDING REQUIRED MINIMUM DEPTH) soil removed from pad for footing and placed on outer side of form board does not meet undisturbed soil requirements. Compaction reports are required for that material. site plan and indication of areas tested for compaction will be required to count as compacted undisturbed soil.
MONOLITHIC SLAB 03/19/2019 Disapproved -FEE REQUIRED JCOLASANTI
Note: MINIMUM DEPTH ON FOOTERS 12" UNDISTURBED SOIL..FBC..403.1.4 MARKED ON PLANS
PLUMBING 1ST ROUGH UNDERGROUND 03/12/2019 APPROVED JGIBSON

Review History

Department Status Date In Date Out
SW1 COMPLETE 04/05/2019 04/10/2019
Note: Released By: JHINDMAN
BLD COMPLETE 03/11/2019 03/18/2019
Note: Released By: JHINDMAN
SWALE COMPLETE 01/17/2019 01/29/2019
Note: Released By: TBAKER
ZON COMPLETE 01/14/2019 01/14/2019
Note: Released By: AMOBLEY
ENGIN1 COMPLETE 01/14/2019 01/18/2019
Note: Released By: TBAKER
PLUM COMPLETE 01/14/2019 01/22/2019
Note: Released By: JHINDMAN
ZON HOLD 12/14/2018 12/14/2018
Note: Held By: AMOBLEY Repeat comment: Survey must have total lot square footage
ENGIN1 HOLD 12/14/2018 12/18/2018
Note: Held By: TBAKER Unaccepptable bench mark. See attached image of COPC requirements for site benchmarks.
SW1 COMPLETE 12/14/2018 12/18/2018
Note: Released By: DREWIS
ELEC COMPLETE 12/14/2018 12/18/2018
Note: Released By: DREWIS
UD1 COMPLETE 12/14/2018 12/20/2018
Note: Released By: LFITZGERALD Gravity Sewer new homes This is a Gravity sewer, the Sewer Tie-in Inspection is a visual inspection it must be called in the day before the tie-in is to be made. The morning of the tie-in the inspector should be contacted to coordinate the time of the tie-in so he can witness the tie-in and help prevent failed inspections due to cave in or mud/water preventing the visual inspection. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap. The NFPA Clear Zone distance there can be no obstacles in front of the Hydrant and 7.5’ on the sides or 4’ behind
PLUM HOLD 12/14/2018 12/26/2018
Note: Held By: JHINDMAN 1. Provide a master bath minimum sanitary drain size of 3" . 6th ed. FBC R Table 3005.4.1 J. hindman 986-3784. 2nd request
BLD COMPLETE 12/06/2018 12/13/2018
Note: Released By: JHINDMAN
ELEC HOLD 12/06/2018 12/10/2018
Note: Held By: DREWIS Per NEC 2014 210.52 Provide receptacles for both left side bedrooms at the switch wall. Additional GFCI in the laundry area. GFCI with weather proof cover(406.9) on the porch. Daniel Rewis 986-4736
ENGIN1 HOLD 12/06/2018 12/10/2018
Note: Held By: TBAKER No benchmark on survey
MECH COMPLETE 12/06/2018 12/13/2018
Note: Released By: JHINDMAN
PLUM HOLD 12/06/2018 12/13/2018
Note: Held By: JHINDMAN 1. Provide a master bath minimum sanitary drain size of 3" . 6th ed. FBC R Table 3005.4.1 J. hindman 986-3784.
SW1 HOLD 12/06/2018 12/10/2018
Note: Held By: DREWIS Provide a site plan depicting storm water flow elevations and grade at and away from the foundation wall of residence per Residential Florida Building Code R401.3 and City of Palm Coast Tech. Manual Sec. 5 Eng. Standard 300. Daniel Rewis 986-4736
UD1 HOLD 12/06/2018 12/12/2018
Note: Held By: MBACON Please remove septic tank and drainage field from survey. Gravity sewer is available.
ZON HOLD 12/06/2018 12/07/2018
Note: Held By: AMOBLEY Survey must have total lot square footage

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
CONTRACTOR CHANGE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
NEW RESIDENTIAL INSPECTIONS ¤406.00 01/25/2019
SITE PLAN 20 ¤20.00 01/25/2019
SURCHARGE FS 533.721 ¤10.73 01/25/2019
SURCHARGE - FS 468.631 ¤16.09 01/25/2019
STORM WATER PERMIT FEES ¤80.00 01/25/2019
3% TRANS IMPACT FEE CREDIT (¤48.96) 01/25/2019
ELECTRIC FEE ¤181.80 01/25/2019
3% FIRE IMPACT FEE CREDIT (¤6.70) 01/25/2019
IMPACT FEE FIRE ¤223.38 01/25/2019
IMPACT FEE PARKS ¤849.24 01/25/2019
IMPACT FEE SCHOOL ¤3,600.00 01/25/2019
IMPACT FEE TRANSPORTATION ¤1,632.00 01/25/2019
MECHANICAL FEE ¤181.80 01/25/2019
3% PARKS IMPACT FEE CREDIT (¤25.48) 01/25/2019
PLAN CHECK FEE ¤81.20 01/25/2019
PLUMBING FEE ¤181.80 01/25/2019
ADMIN FEE ¤20.00 01/25/2019
Fees Total Due: ¤0.00 Total Paid: ¤7,682.90