Permit #2018120149

Permit Details

Status: COED

Parcel Id: 07-11-31-7028-00410-0200
CONDITIONED SPACE: 1390 sqft
GARAGE: 445 sqft
OPENED PORCH (WITH ROOF) : 120 sqft
OPENED PORCH (WITH ROOF) : 52 sqft
Total Square Footage: 2007 sqft
Block: 00410
Subdivision: 2199 - SECTION 28-WYNNFIELD
Job Phone: 407-307-4753
Location Address: 113 POINT PLEASANT DR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 01/18/2019
NOC: RECORDED
Applicant name: SHAWN VIRAG
Owner: DLP BRITE HOMES LLC

Address

605 PALENCIA CLUB DRIVE

ST AUGUSTINE, FL 32095

Lot: 0200
Contracted Stated Job Value: ¤127,800.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

SHAWNTELLE CONSULTING AND DESIGN LLC
Status Location Address State License Number Phone
CANCEL

611 LARGOVISTA DR

OAKLAND, FL 34787

CBC1261160 (Exp: 08/31/2020) 407-307-4753

Sub Contractors

TERRY BRICE DICKERSON
Status Location Address State License Number Phone
ACTIVE

4300 ST JOHN'S PARKWAY

ALPHARETTA, GA 30009

CCC1326209 (Exp: 08/31/2026) 407-548-6733
JOSEPH H STRADA JR
Status Location Address State License Number Phone
CANCEL

3400 ST JOHNS PKWY

SANFORD, FL 32771

EC13003715 (Exp: 08/31/2022) 877-906-1113
ROBERT G DELLO RUSSO
Status Location Address State License Number Phone Fax
DECEASED

531 CODISCO WAY

SANFORD, FL 32771

CAC032448 (Exp: 08/31/2022) (407)831-2665 (407)333-3853
JONATHAN M PEARSON
Status Location Address State License Number Phone Fax
ACTIVE

209 N FORSYTH ST

BUNNELL, FL 32110

CFC1425941 (Exp: 08/31/2026) 386-597-0944 386-437-4996

Inspection History

Type Request Date Result Inspector
ROW - FINAL APRON (AFTER POUR) 01/24/2020 APPROVED MMAJEWSKI
ROW - STORMWATER FINAL 01/24/2020 APPROVED MMAJEWSKI
U -UTILITY RESIDENTIAL FINAL 01/24/2020 APPROVED - AS NOTED LFITZGERALD
Note: water meterpit is too high-spoke with Rich at Utilities and he will lower. Sewer pep tank located across from pep panel next to garage due to conflict with underground power lines.Utility pep crew ro arive monday and lower exposd effluent line from tank to street. Spoke with bldr. Tom who agreeed to place more sod around sewer c/o cap.
BLD - BUILDING FINAL 08/13/2019 FINAL APPROVED JCOLASANTI
Note: THIS IS A REINSPECTION
BLD - BUILDING FINAL 08/08/2019 Disapproved -FEE REQUIRED JCOLASANTI
Note: need to cover open conductor and secure outlet box outside by meter....need to repair stucco right side bottom corner
ROW FIELD SURVEY /GRADING CERTIFICATION 08/06/2019 APPROVED RGROSS
Note: SEE NOTES ON FINAL SURVEY APPROVED AS NOTED.
FINAL SURVEY (OFFICE USE ONLY) 08/06/2019 APPROVED - AS NOTED RGROSS
Note: GRADE ON THE RIGHT SIDE OF THE PROPERTY ARE SWALED ON THE INSIDE OF THE PROPERTY LINE AND DRAIN AROUND THE PEP TANK AND TELEPHONE POLE. GRADE ON THE LEFT SIDE ARE ALSO SWALED INSIDE THE PROPERTY LINE AND DRAIN AROUND AN EXISTING CYPRESS TREE. THEREFORE APPROVED AS NOTED.
ELECTRIC - EARLY POWER 07/22/2019 APPROVED - AS NOTED RMARTIN
Note: THIS INSPECTION WAS ALREADY DONE
ROW- PRE-APRON (PRE-POUR) 07/17/2019 APPROVED RGROSS
Note: THIS IS A REINSPECTION. READY TO POUR
ROW- PRE-APRON (PRE-POUR) 07/16/2019 Disapproved - NO FEE KHOWELL
Note: THIS IS A REINSPECTION THERE AREAS IN THE UPPER PART OF THE DRIVEWAY THAT DO NOT HAVE THE MIN. THICKNESS OF 4"
ROW- PRE-APRON (PRE-POUR) 07/15/2019 Disapproved -FEE REQUIRED KHOWELL
Note: THIS IS A REINSPECTION THE CULVERT PIPE IS OUT OF TOLERANCE,
ROW- PRE-APRON (PRE-POUR) 07/10/2019 Disapproved -FEE REQUIRED KHOWELL
Note: THIS IS A REINSPECTION THE CULVERT PIPE IS OUT OF TOLERANCE, THE ROAD FORM BOARD IS REQUIRED TO FOLLOW THE CURVE OF THE ROADWAY SO THE INSIDE LINES UP WITH THE EXISTING EDGE OF PAVEMENT. THERE AREAS IN THE UPPER PART OF THE DRIVEWAY THAT DO NOT HAVE THE MIN. THICKNESS OF 4".
ROW- PRE-APRON (PRE-POUR) 07/09/2019 Disapproved -FEE REQUIRED KHOWELL
Note: THIS IS A REINSPECTION NO REBAR FOR CULVERT FOOTER, 4" MINIMUM THICK CONCRETE REQUIRED ABOVE THE ROW
ROW- PRE-APRON (PRE-POUR) 07/08/2019 Disapproved - NO FEE RGROSS
Note: WASHOUTS FROM THE RAIN ON THE LEFT SIDE IN THE UPPER ROW. MISSING REBAR FOR CULVERT ENDS.
U - SEWER TIE IN 07/02/2019 APPROVED JGIBSON
GRAVITY SEWER TEST 07/02/2019 APPROVED JGIBSON
ELECTRIC - EARLY POWER 06/26/2019 APPROVED - AS NOTED RMARTIN
Note: SPOKE TO SUSAN FPL RELEASED POWER 3:15
LATH/BRICK/ WATER BARRIER 05/22/2019 APPROVED DROCKWELL
INSULATION 05/14/2019 APPROVED JCOLASANTI
ALL ROUGH 05/14/2019 APPROVED JCOLASANTI
Note: THIS IS A REINSPECTION
ALL ROUGH 05/09/2019 Disapproved -FEE REQUIRED DROCKWELL
Note: Strap valley rafter to truss below as requested last Inspector/4ply girder requires 1/2in bolts w/washers at bottom cord 4ft o/c..see truss engineering
ROOF VALLEY & METAL 04/25/2019 APPROVED JCOLASANTI
ROOF SHEATHING / BRACES/TIES/DOWN CELL 04/23/2019 APPROVED - AS NOTED JCOLASANTI
Note: loose sheathing right side garage....strap valley right rear (marked on roof plan) check at all rough FBC 802
TIE BEAM / LINTEL 04/11/2019 APPROVED WMILLER
Note: THIS IS A REINSPECTION
ELECTRIC-TUG 04/11/2019 APPROVED - AS NOTED RMARTIN
Note: SPOKE TO DELL FPL RELEASED POWER 3:20
TIE BEAM / LINTEL 04/10/2019 Disapproved -FEE REQUIRED JCOLASANTI
Note: missing cell left side by recess tub FBC 802
FOUND SURVEY APPROVED (OFFICE) 04/09/2019 APPROVED JHINDMAN
MONOLITHIC SLAB 04/01/2019 APPROVED WMILLER
Note: THIS IS A REINSPECTION
MONOLITHIC SLAB 03/26/2019 Disapproved -FEE REQUIRED WMILLER
Note: THIS IS A REINSPECTION 12 inch MINIMUM DEPTH , UNDISTURBED GROUND SURFACE… R403.1.3.4 and in accordance with R401.2, and R403.1 ALL FOOTINGS SHALL BE PLACED AT LEAST 12 in. BELOW THE UNDISTURBED GROUND SURFACE (NEED ADDITIONAL COMPACTION REPORT FOR AREAS OUTSIDE OF FOOTINGS AFTER ADDING REQUIRED MINIMUM DEPTH) soil removed from pad for footing and placed on outer side of form board does not meet undisturbed soil requirements. Compaction reports are required for that material. site map and indication of areas tested for compaction will be required to count as compacted undisturbed soil. (CORRECTIONS WERE NOT MADE IN ACCORDANCE WITH PRIVISIONS OF CODE AS DISCUSSED WITH CHIEF BUILDING OFFICIAL RICKIE LEE DURRING ON SITE MEETING)
MONOLITHIC SLAB 03/21/2019 Disapproved -FEE REQUIRED MWILLIAMS
Note: THIS IS A REINSPECTION 12 inch MINIMUM DEPTH , UNDISTURBED GROUND SURFACE… R403.1.3.4 and in accordance with R401.2, and R403.1 ALL FOOTINGS SHALL BE PLACED AT LEAST 12 in. BELOW THE UNDISTURBED GROUND SURFACE (NEED ADDITIONAL COMPACTION REPORT FOR AREAS OUTSIDE OF FOOTINGS AFTER ADDING REQUIRED MINIMUM DEPTH) soil removed from pad for footing and placed on outer side of form board does not meet undisturbed soil requirements. Compaction reports are required for that material. site map and indication of areas tested for compaction will be required to count as compacted undisturbed soil.
MONOLITHIC SLAB 03/19/2019 Disapproved -FEE REQUIRED WMILLER
Note: THIS IS A REINSPECTION CLEARANCE ON REBAR FROM EARTH 3” FBC R404.1.3.3.7.4 (caved in and chairs not supporting check all)
MONOLITHIC SLAB 03/04/2019 Disapproved - NO FEE WMILLER
Note: THIS IS A REINSPECTION still need(APPROVED) revision to show which detail to follow for footings (F1 or 15 on 6.1) also (STILL NEED REPORT) FOR 12 inch MINIMUM DEPTH , UNDISTURBED GROUND SURFACE… R403.1.3.4 and in accordance with R401.2, and R403.1 ALL FOOTINGS SHALL BE PLACED AT LEAST 12 in. BELOW THE UNDISTURBED GROUND SURFACE (NEED ADDITIONAL COMPACTION REPORT FOR AREAS OUTSIDE OF FOOTINGS AFTER ADDING REQUIRED MINIMUM DEPTH)
MONOLITHIC SLAB 02/27/2019 Disapproved -FEE REQUIRED WMILLER
Note: THIS IS A REINSPECTION still need revision to show which detail to follow for footings (F1 or 15 on 6.1) also 12 inch MINIMUM DEPTH , UNDISTURBED GROUND SURFACE… R403.1.3.4 and in accordance with R401.2, and R403.1 ALL FOOTINGS SHALL BE PLACED AT LEAST 12 in. BELOW THE UNDISTURBED GROUND SURFACE (NEED ADDITIONAL COMPACTION REPORT FOR AREAS OUTSIDE OF FOOTINGS AFTER ADDING REQUIRED MINIMUM DEPTH)
MONOLITHIC SLAB 02/25/2019 Disapproved - NO FEE JCOLASANTI
Note: need to verify which detail is to be used detail 6.1/15 calls for 20" deep footers....will check slab when verification is done
PLUMBING 1ST ROUGH UNDERGROUND 02/21/2019 APPROVED JGIBSON

Review History

Department Status Date In Date Out
SW1 COMPLETE 04/03/2019 04/09/2019
Note: Released By: JHINDMAN Foundation Survey
BLD COMPLETE 03/11/2019 03/18/2019
Note: Released By: JHINDMAN
ZON COMPLETE 01/14/2019 01/14/2019
Note: Released By: AMOBLEY
ZON HOLD 01/03/2019 01/03/2019
Note: Held By: AMOBLEY Foundation Plantings a. Residential homes shall provide foundation plantings consisting of sixteen (16) shrubs. On interior lots, eight (8) shrubs shall be planted in front of the home, and four (4) shrubs planted on each side of the home.
ENGIN1 COMPLETE 01/03/2019 01/03/2019
Note: Released By: TBAKER
SW1 COMPLETE 01/03/2019 01/10/2019
Note: Released By: RLEE
UD1 COMPLETE 01/03/2019 01/11/2019
Note: Released By: MBACON
SWALE COMPLETE 01/03/2019 01/16/2019
Note: Released By: TBAKER
BLD COMPLETE 12/06/2018 12/13/2018
Note: Released By: JHINDMAN
ELEC COMPLETE 12/06/2018 12/10/2018
Note: Released By: DREWIS
ENGIN1 HOLD 12/06/2018 12/10/2018
Note: Held By: TBAKER No benchmark on survey
MECH COMPLETE 12/06/2018 12/13/2018
Note: Released By: JHINDMAN
PLUM COMPLETE 12/06/2018 12/13/2018
Note: Released By: JHINDMAN
SW1 HOLD 12/06/2018 12/10/2018
Note: Held By: DREWIS Provide a site plan depicting storm water flow elevations and grade at and away from the foundation wall of residence per Residential Florida Building Code R401.3 and City of Palm Coast Tech. Manual Sec. 5 Eng. Standard 300. Daniel Rewis 986-4736
UD1 HOLD 12/06/2018 12/12/2018
Note: Held By: MBACON PEP Panel not shown on electrical plans PEP Panel is not shown in the electrical plan. Submit a new electrical plan showing PEP Panel on the building on the same side of the building as indicated in the Utility marked site plan. Also please remove septic and drainfiled from survey.
ZON HOLD 12/06/2018 12/06/2018
Note: Held By: AMOBLEY Survey should have total lot square footage Please provide rear setback on site plan Foundation Plantings a. Residential homes shall provide foundation plantings consisting of sixteen (16) shrubs. On interior lots, eight (8) shrubs shall be planted in front of the home, and four (4) shrubs planted on each side of the home. On corner lots, six (6) shrubs shall be planted on each side of the home facing a street, and (4) shrubs planted on the interior side of the home. When the rear yard of a home faces a saltwater canal, lake, or golf course, an additional four (4) shrubs shall be planted along the rear of the home. b. All of these required shrubs shall be planted between two and one-half (2 ½) and eight (8) feet of the home’s foundation. c. The corners of the house shall be wrapped with shrubbery or have an understory tree planted there. Shrubbery shall be selected using varying heights to accent and soften walls.

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
CONTRACTOR CHANGE ¤40.00 12/05/2019
REINSPECTION FEE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
REINSPECTION FEE ¤40.00 08/13/2019
NEW RESIDENTIAL INSPECTIONS ¤360.00 01/18/2019
SITE PLAN 20 ¤20.00 01/18/2019
SURCHARGE FS 533.721 ¤9.76 01/18/2019
SURCHARGE - FS 468.631 ¤14.64 01/18/2019
STORM WATER PERMIT FEES ¤80.00 01/18/2019
3% TRANS IMPACT FEE CREDIT (¤48.96) 01/18/2019
ELECTRIC FEE ¤168.00 01/18/2019
3% FIRE IMPACT FEE CREDIT (¤6.70) 01/18/2019
IMPACT FEE FIRE ¤223.38 01/18/2019
IMPACT FEE PARKS ¤849.24 01/18/2019
IMPACT FEE SCHOOL ¤3,600.00 01/18/2019
IMPACT FEE TRANSPORTATION ¤1,632.00 01/18/2019
MECHANICAL FEE ¤168.00 01/18/2019
3% PARKS IMPACT FEE CREDIT (¤25.48) 01/18/2019
PLAN CHECK FEE ¤72.00 01/18/2019
PLUMBING FEE ¤168.00 01/18/2019
ADMIN FEE ¤20.00 01/18/2019
Fees Total Due: ¤0.00 Total Paid: ¤7,743.88