I want to search for...
Permit #2019020835
Permit Details
Status: COED
| Parcel Id: 07-11-31-7035-00670-0120 |
| CONDITIONED SPACE: 2919 sqft |
| GARAGE: 716 sqft |
| OPENED PORCH (WITH ROOF) : 57 sqft |
| OPENED PORCH (WITH ROOF) : 250 sqft |
| Total Square Footage: 3942 sqft |
| Block: 00670 |
| Subdivision: 2172 - SECTION 35-BELLE TERRE |
| Job Phone: 386-627-8993 |
| Location Address: 34 BURBANK DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 04/02/2019 |
| NOC: RECORDED |
| Applicant name: WILLIAM PIERCE STOUGHTON |
| Owner: RICE ANDREW EVERETT |
|
Address 31 BARKWOOD LANE PALM COAST, FL 32137 |
| Lot: 0120 |
| Contracted Stated Job Value: ¤250,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
STOUGHTON & DURAN CUSTOM HOMES LLC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 1478 BUNNELL, FL 32110 |
CGC047560 (Exp: 08/31/2026) | 386-627-8993 | 866-576-9888 |
Sub Contractors
PETER JOSEPH LYDEN
| Status | Location Address | State License Number | Phone |
| CANCEL |
17 UNIMAY CT BUNNELL, FL 32110 |
EC0002436 (Exp: 08/31/2022) | 386-931-2568 |
RICHARD LEE VONBROCKEN
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
1738 STATE AVE HOLLY HILL, FL 32117 |
CAC035516 (Exp: 08/31/2026) | (386)672-1950 | (386)672-1952 |
HEATH EDWARD SANFORD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
126 EAST END RD SAN MATEO, FL 32187 |
CFC1429896 (Exp: 08/31/2026) | 386-871-8823 |
BRIAN CHRISTOPHER MULLEN
| Status | Location Address | State License Number | Phone |
| INACTIVE |
PO BOX 351158 PALM COAST, FL 0 |
CCC1330417 (Exp: 08/31/2026) | 386-385-8504 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 12/03/2020 | FINAL APPROVED | MMESSER |
| Note: THIS IS A REINSPECTION ADDRESS NUMBERS, SITE ADDRESS NUMBERS FBC R319.1 4 INCH MINIMUM WITH .5 INCH STROKE WIDTH WINDOW SILLS IN 2 FRONT BEDROOMS MISSING. PROOF OF TERMITE INSPECTION NEEDS TO BE POSTED ON ELECTRICAL PANEL. INSULATION CALCULATION MISSING. INSPECTION STOPPED! | |||
| BLD - BUILDING FINAL | 11/30/2020 | Disapproved -FEE REQUIRED | FWILLIS |
| Note: ADDRESS NUMBERS, SITE ADDRESS NUMBERS FBC R319.1 4 INCH MINIMUM WITH .5 INCH STROKE WIDTH WINDOW SILLS IN 2 FRONT BEDROOMS MISSING. PROOF OF TERMITE INSPECTION NEEDS TO BE POSTED ON ELECTRICAL PANEL. INSULATION CALCULATION MISSING. INSPECTION STOPPED! | |||
| BLD - BUILDING FINAL | 11/19/2020 | CANCELLED BY APPLICANT | WEB |
| U -UTILITY RESIDENTIAL FINAL | 11/16/2020 | FINAL APPROVED | DHANEY |
| Note: THIS IS A REINSPECTION | |||
| ROW - STORMWATER FINAL | 11/12/2020 | APPROVED | RGROSS |
| U -UTILITY RESIDENTIAL FINAL | 11/12/2020 | CANCELLED BY APPLICANT | JHARDING |
| ROW - FINAL APRON (AFTER POUR) | 11/12/2020 | APPROVED | RGROSS |
| ELECTRIC - EARLY POWER | 11/12/2020 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED POWER 9:00 | |||
| FINAL SURVEY (OFFICE USE ONLY) | 09/14/2020 | APPROVED | RGROSS |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 09/14/2020 | APPROVED | RGROSS |
| ALL ROUGH | 08/04/2020 | APPROVED | JCOLASANTI |
| Note: Schedule rough inspection for studio. | |||
| FRAMING | 06/25/2020 | APPROVED | JCOLASANTI |
| INSULATION | 05/27/2020 | APPROVED | JCOLASANTI |
| Note: insulation for sound room | |||
| U - SEWER TIE IN | 05/22/2020 | APPROVED | JGIBSON |
| ROW- PRE-APRON (PRE-POUR) | 05/22/2020 | APPROVED | RGROSS |
| Note: READY FOR PAVERS | |||
| GRAVITY SEWER TEST | 05/22/2020 | APPROVED | JGIBSON |
| PROJECT STATUS (OFFICE USE) | 05/21/2020 | APPROVED | JCOLASANTI |
| Note: will need insulation, framing and all rough inspection for sond room | |||
| ROW- PAVER RESTRAINTS | 05/13/2020 | APPROVED | RGROSS |
| ROW- PRE-APRON (PRE-POUR) | 05/13/2020 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION ADDED ON 3/19/2020 3:35:24 PM NOT FORMED CORRECTLY IN THE ROW. SEE CITY WEB SITE SEARCH "RESIDENTIAL CULVERT DETAIL" PDF FOR CITY CODE FOR DRIVEWAY CULVERTS. APPROVED FOR THE APRON AND PAVER RESTRAINTS ONLY. UPPER PAVER DRIVEWAY BASE STILL NEEDS CHECKED ON THE 2ND PART OF THE PRE POUR. ON SITE WITH SUPER. | |||
| ROW- PRE-APRON (PRE-POUR) | 03/23/2020 | Disapproved - NO FEE | RGROSS |
| Note: THIS IS A REINSPECTION ADDED ON 3/19/2020 3:35:24 PM NOT FORMED CORRECTLY IN THE ROW. SEE CITY WEB SITE SEARCH "RESIDENTIAL CULVERT DETAIL" PDF FOR CITY CODE FOR DRIVEWAY CULVERTS. PHOTO'S ATTACHED. | |||
| ROW- PRE-APRON (PRE-POUR) | 03/20/2020 | CANCELLED BY APPLICANT | JMONTARULI |
| ROW- PROJECT STATUS | 03/12/2020 | Disapproved - NO FEE | CTROHA |
| Note: A resident reported the builder had removed vegetation and trees from city property along the canal at this location. After and inspection of the property I found evidence of the removal and sent this to code enforcement. | |||
| PEP TANK INSTALLATION REQUEST | 03/09/2020 | APPROVED | CSTONE |
| ELECTRIC-TUG | 01/22/2020 | APPROVED - AS NOTED | RMARTIN |
| Note: NEED REVISION IF NOT ON PLAN OF SUB PANEL IN GARAGE BY FINAL, NEED APPROVED PLANS ON SITE FOR INSPECTIONS, EMAILED FPL RELEASED TUG 1:50 | |||
| INSULATION | 12/16/2019 | APPROVED | JDELBONIS |
| ALL ROUGH | 12/09/2019 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| ALL ROUGH | 10/25/2019 | Disapproved -FEE REQUIRED | WMILLER |
| Note: THIS IS A REINSPECTION 1. need revision for changes in electric thoughout (not as proposed) 2. need revision for ductwork (not as proposed) 3. 5ft HEAD OF WATER, 6TH EDITION FBC CHAPTER 25 SECTION P2503.5.1 (1) 4. NAIL PLATES ON ELECTRIC FBC E3802.1 (table), AND 3802.3.2 OR NEC 334.15 b. (RESPECTIVELY) protection from physical damage. (top of panel and at bottom plate in kitchen pantry) 5. double walls not installed at studio 6. electric out of wall at kitchen pantry bottom plate 6. exhaust ducts within 3 feet of windows 7. Need to complete work and obtain revision for studio | |||
| ALL ROUGH | 09/30/2019 | Disapproved - NO FEE | JCOLASANTI |
| Note: need revision for sub panel in garage.....need to attach duct to ceiling and run electrical per plan in sound room | |||
| LATH/BRICK/ WATER BARRIER | 09/30/2019 | APPROVED | JCOLASANTI |
| ROOF VALLEY & METAL | 08/01/2019 | APPROVED - AS NOTED | JCOLASANTI |
| Note: need revision for garage door into sound room by all rough inspection | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 07/26/2019 | APPROVED - AS NOTED | JCOLASANTI |
| Note: THIS IS A REINSPECTION need to nail and add straps front entrance area check at all rough Elizabeth called to schedule this inspection | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 07/24/2019 | CANCELLED BY APPLICANT | JDELBONIS |
| TIE BEAM / LINTEL | 06/12/2019 | APPROVED | JCOLASANTI |
| FOUND SURVEY APPROVED (OFFICE) | 06/12/2019 | APPROVED | STHOMAS |
| MONOLITHIC SLAB | 05/15/2019 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION per contractor | |||
| MONOLITHIC SLAB | 05/13/2019 | CANCELLED BY APPLICANT | WMILLER |
| Note: per contractor cancelled per contractor due to weather | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 05/07/2019 | APPROVED | JGIBSON |
Review History
| Department | Status | Date In | Date Out |
| ZON | COMPLETE | 04/30/2020 | 04/30/2020 |
| Note: Released By: ELENS | |||
| ZON | HOLD | 04/13/2020 | 04/14/2020 |
| Note: Held By: ELENS Revised landscape plan does not contain a legend showing the types and sizes of plantings. The proposed plan does not show required number and placement of foundation plantings, and trees. | |||
| MECH | COMPLETE | 12/02/2019 | 12/03/2019 |
| Note: Released By: CPISCITELLI | |||
| ELEC | COMPLETE | 12/02/2019 | 12/02/2019 |
| Note: Released By: JMUNSON | |||
| MECH | COMPLETE | 09/19/2019 | 09/26/2019 |
| Note: Released By: MGARRETT | |||
| BLD | COMPLETE | 09/13/2019 | 09/20/2019 |
| Note: Released By: MGARRETT | |||
| MECH | HOLD | 07/08/2019 | 07/09/2019 |
| Note: Held By: JHINDMAN 1. Revised energy calculations are not signed by the contractor on page 1 and the EPL card. | |||
| SW1 | COMPLETE | 06/11/2019 | 06/11/2019 |
| Note: Released By: JMUNSON | |||
| SW1 | HOLD | 05/06/2019 | 05/07/2019 |
| Note: Held By: JHINDMAN foundation survey is for wrong address | |||
| ZON | COMPLETE | 03/26/2019 | 03/27/2019 |
| Note: Released By: AMOBLEY | |||
| UD1 | COMPLETE | 03/26/2019 | 03/29/2019 |
| Note: Released By: AHALL PEP Tank areas new home This is a PEP Tank area. The Pep Panel will be placed 5 feet from the front corner of the building on the same side of the building as the PEP tank that is marked on the Utility marked Site plan. Make sure the electrician places the PEP power wire between 3 feet and 5 feet from the ground. The plumber should exit the slab with the sewer pipe on the side of the building the tank will be on and matching the utility marked site plan, this will reduce any piping under driveways or sidewalks and minimize the fall required. The sewer tie-in inspection must be called in the day before the tie-in. The morning of the tie-in the inspector should be contacted to coordinate the time of the tie-in visual inspection so he can witness the tie-in. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap | |||
| MECH | COMPLETE | 03/26/2019 | 04/01/2019 |
| Note: Released By: JHINDMAN | |||
| PLUM | COMPLETE | 03/26/2019 | 04/01/2019 |
| Note: Released By: JHINDMAN | |||
| ELEC | COMPLETE | 03/26/2019 | 04/01/2019 |
| Note: Released By: JHINDMAN | |||
| SWALE | COMPLETE | 02/25/2019 | 03/01/2019 |
| Note: Released By: TBAKER | |||
| BLD | COMPLETE | 02/25/2019 | 03/04/2019 |
| Note: Released By: JHINDMAN | |||
| ELEC | HOLD | 02/25/2019 | 03/04/2019 |
| Note: Held By: JHINDMAN 1. Provide electrical load calculations signed by the electrical contractor with their license number 2014 necart.220. | |||
| ENGIN1 | COMPLETE | 02/25/2019 | 02/25/2019 |
| Note: Released By: TBAKER | |||
| MECH | HOLD | 02/25/2019 | 03/04/2019 |
| Note: Held By: JHINDMAN 1. Provide contractors signature on energy calculation page r405 and epl card. | |||
| PLUM | HOLD | 02/25/2019 | 03/04/2019 |
| Note: Held By: JHINDMAN 1. Provide a signed and sealed plumbing riser diagram or a riser signed by the plumbing contractor with their license number 6th ed. FBC 107. | |||
| SW1 | COMPLETE | 02/25/2019 | 03/04/2019 |
| Note: Released By: JHINDMAN | |||
| UD1 | HOLD | 02/25/2019 | 02/26/2019 |
| Note: Held By: LFITZGERALD PEP Panel not shown on electrical plans (Builder Electrical Plan PEP Panel is not shown in the electrical plan. Submit a new electrical plan showing PEP Panel on the building on the same side of the building as indicated in the Utility marked site plan | |||
| ZON | HOLD | 02/25/2019 | 02/25/2019 |
| Note: Held By: AMOBLEY Please provide name of the sherwin williams body color with the LRV Please specify the gallon size of all shrubs on landscape plan (Shrubs around AC Pad must be 7 gallon) |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 12/11/2020 |
| REINSPECTION FEE | ¤40.00 | 12/11/2020 |
| NEW RESIDENTIAL INSPECTIONS | ¤730.00 | 04/02/2019 |
| SITE PLAN 20 | ¤20.00 | 04/02/2019 |
| SURCHARGE FS 533.721 | ¤17.53 | 04/02/2019 |
| SURCHARGE - FS 468.631 | ¤26.30 | 04/02/2019 |
| STORM WATER PERMIT FEES | ¤80.00 | 04/02/2019 |
| 3% TRANS IMPACT FEE CREDIT | (¤48.96) | 04/02/2019 |
| ADMIN FEE | ¤20.00 | 04/02/2019 |
| ELECTRIC FEE | ¤279.00 | 04/02/2019 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 04/02/2019 |
| IMPACT FEE FIRE | ¤223.38 | 04/02/2019 |
| IMPACT FEE PARKS | ¤849.24 | 04/02/2019 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 04/02/2019 |
| IMPACT FEE TRANSPORTATION | ¤1,632.00 | 04/02/2019 |
| MECHANICAL FEE | ¤279.00 | 04/02/2019 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 04/02/2019 |
| PLAN CHECK FEE | ¤146.00 | 04/02/2019 |
| PLUMBING FEE | ¤279.00 | 04/02/2019 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤8,180.31 |