I want to search for...
Permit #2019021051
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7015-00020-1140 |
| Block: 00020 |
| Subdivision: 2194 - SECTION 15-COUNTRY CLUB COVE |
| Job Phone: 386-313-1897 |
| Location Address: 19 CRAZY HORSE CT |
| Type: DR - DRIVEWAY |
| Issue Date: 05/16/2019 |
| NOC: RECORDED |
| Applicant name: ERIC KACHNYCZ |
| Owner: BENOIST ANDREW E & JILL A H&W |
|
Address 19 CRAZY HORSE COURT PALM COAST, FL 32137 |
| Lot: 1140 |
| Contracted Stated Job Value: ¤7,000.00 |
| Job Description: Installation of paver driveway (same size as existing) |
| Type: CN |
Contractor
DONE RIGHT SINCE 1985
| Status | Location Address | Phone |
| ACTIVE |
1405 KINGS ESTATE RD ST AUGUSTINE, FL 32086 |
(904) 533-6373 |
Inspection History
| Type | Request Date | Result | Inspector |
| ROW - FINAL INSPECTION | 06/10/2019 | APPROVED | RGROSS |
| ROW - FINAL APRON (AFTER POUR) | 06/07/2019 | APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION | |||
| ROW - FINAL APRON (AFTER POUR) | 05/24/2019 | Disapproved -FEE REQUIRED | KHOWELL |
| Note: REMOVE THE CONCRETE AND DIRT OUT OF CULVERT. AND REMOVE CONCRETE FROM THE SWALE AREA ON THE LEFT SIDE. REMOVE FORM BOARD ON THE RIGHT SIDE AND POUR THE FOOTER UNDER THE CULVERT ON THE RIGHT SIDE NEEDS TO BE DONE TO THE CITY STANDARD DRIVEWAY DETAIL. PAVERS ARE SEPARATING AND HAVE SOME DIPS IN THEM. SOD THE R.O.W. AND ALONG THE DRIVEWAY I.E. BARE AREAS | |||
| U -UTILITY RESIDENTIAL FINAL | 05/24/2019 | FINAL APPROVED | JNICHOLS |
| ROW- PRE-APRON (PRE-POUR) | 04/25/2019 | APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION. READY FOR PAVERS | |||
| ROW- PRE-APRON (PRE-POUR) | 04/22/2019 | PARTIALLY APPROVED | RGROSS |
| Note: APPROVED FOR CONCRETE OVER THE CULVERT ONLY. PAVER DRIVEWAY |
Review History
| Department | Status | Date In | Date Out |
| ZON | COMPLETE | 03/21/2019 | 03/21/2019 |
| Note: Released By: AMOBLEY | |||
| ZON | HOLD | 03/18/2019 | 03/19/2019 |
| Note: Held By: AMOBLEY Please turn in Original copy of right of way agreement so it can be sent for recording | |||
| ENGIN1 | COMPLETE | 02/28/2019 | 03/07/2019 |
| Note: Released By: TBAKER | |||
| SW1 | COMPLETE | 02/28/2019 | 03/04/2019 |
| Note: Released By: JHINDMAN | |||
| UD1 | COMPLETE | 02/28/2019 | 03/06/2019 |
| Note: Released By: LFITZGERALD All Concrete, Driveways, Pavers, Pools / Sidewalks ETC. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap. The NFPA Clear Zone distance there can be no obstacles in front of the Hydrant and 7.5’ on the sides or 4’ behind. NOTE-existing older water meter was observed to be 8 inches from edge of driveway upon site visit. I had utility rep .inspect and there was no room to move so i was told to release. | |||
| ZON | HOLD | 02/28/2019 | 03/01/2019 |
| Note: Held By: AMOBLEY Right of way agreement must be signed by all owners on the deed and all signatures must be notarized. Original needs to be turned in to us so it can be sent for recording |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 06/06/2019 |
| SITE PLAN 20 | ¤20.00 | 05/16/2019 |
| ADMIN FEE | ¤20.00 | 05/16/2019 |
| RECORDING FEE REIMBURSE DOC | ¤44.00 | 05/16/2019 |
| SURCHARGE FS 533.721 | ¤2.00 | 05/16/2019 |
| SURCHARGE - FS 468.631 | ¤2.00 | 05/16/2019 |
| STORM WATER PERMIT FEES | ¤40.00 | 05/16/2019 |
| STORM WATER PERMIT FEES | ¤40.00 | 04/15/2019 |
| STORM WATER PERMIT FEES | (¤40.00) | 04/15/2019 |
| SURCHARGE FS 533.721 | ¤2.00 | 04/15/2019 |
| SURCHARGE - FS 468.631 | ¤2.00 | 04/15/2019 |
| SURCHARGE - FS 468.631 | (¤2.00) | 04/15/2019 |
| RECORDING FEE REIMBURSE DOC | ¤44.00 | 04/15/2019 |
| ADMIN FEE | ¤20.00 | 04/15/2019 |
| RECORDING FEE REIMBURSE DOC | (¤44.00) | 04/15/2019 |
| SURCHARGE FS 533.721 | (¤2.00) | 04/15/2019 |
| SITE PLAN 20 | ¤20.00 | 04/15/2019 |
| SITE PLAN 20 | (¤20.00) | 04/15/2019 |
| ADMIN FEE | (¤20.00) | 04/15/2019 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤168.00 |