Permit #2019030052

Permit Details

Status: COED

Parcel Id: 07-11-31-7026-00140-0140
CONDITIONED SPACE: 1448 sqft
GARAGE: 416 sqft
OPENED PORCH (WITH ROOF) : 60 sqft
OPENED PORCH (WITH ROOF) : 234 sqft
Total Square Footage: 2158 sqft
Block: 00140
Subdivision: 2153 - SECTION 26-PINE GROVE
Job Phone: 386-447-4151
Location Address: 53 PINELAND LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 03/18/2019
NOC: RECORDED
Applicant name: GENE WARREN SLONE
Owner: FLORIDA GREEN CONSTRUCTION, INC

Address

50 LEANNI WAY

PALM COAST, FL 32137

Address

UNIT C1

PALM COAST, FL 32137

Lot: 0140
Contracted Stated Job Value: ¤200,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

FLORIDA GREEN CONSTRUCTION INC.
Status Location Address State License Number Phone
INACTIVE

870 E RETTA STREET

DELEON SPRINGS, FL 32130

CBC1260957 (Exp: 08/31/2026) 407-580-2657

Sub Contractors

JONATHAN M PEARSON
Status Location Address State License Number Phone Fax
ACTIVE

209 N FORSYTH ST

BUNNELL, FL 32110

CFC1425941 (Exp: 08/31/2026) 386-597-0944 386-437-4996
OLEG BELINSKIY
Status Location Address State License Number Phone
ACTIVE

19 PINE CIRCLE DRIVE19

PALM COAST, FL 32167

CCC1325974 (Exp: 08/31/2026) 386-263-7906
GREGG A MCANALLY
Status Location Address State License Number Phone
INACTIVE

3370 AGRICULTURAL CENTER DRIVE

PALM COAST, FL 32092

CAC1815760 (Exp: 08/31/2022) 904-829-8898
JOHN EDWARD GAMBONE
Status Location Address Mailing Address State License Number Phone
ACTIVE

15 HARGROVE LN

PALM COAST, FL 32137

1G

PALM COAST, FL 32137

EC13006037 (Exp: 08/31/2026) 386-586-9144

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 10/23/2019 APPROVED JDELBONIS
ROW - FINAL APRON (AFTER POUR) 10/22/2019 APPROVED MMAJEWSKI
ROW - STORMWATER FINAL 10/22/2019 APPROVED MMAJEWSKI
U -UTILITY RESIDENTIAL FINAL 10/22/2019 FINAL APPROVED LFITZGERALD
ROW FIELD SURVEY /GRADING CERTIFICATION 10/21/2019 APPROVED MMAJEWSKI
FINAL SURVEY (OFFICE USE ONLY) 10/21/2019 APPROVED MMAJEWSKI
ROW- PRE-APRON (PRE-POUR) 09/18/2019 APPROVED - AS NOTED KHOWELL
Note: It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist READY TO POUR upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete.
U - SEWER TIE IN 09/09/2019 APPROVED JGIBSON
GRAVITY SEWER TEST 09/09/2019 APPROVED JGIBSON
ELECTRIC - EARLY POWER 09/06/2019 APPROVED - AS NOTED RMARTIN
Note: SPOKE TO SUSAN FPL RELEASED POWER 3:50
PEP TANK INSTALLATION REQUEST 08/20/2019 APPROVED CSTONE
Note: Once you request your pep tank we ask that you keep the site clear until the tank is in. You will have 72 hours after pep tank request has been approved to get the site ready. Site ready means area is clear without driveway, sod, paint, sidewalks, or irrigation in the way. If you have underground power where the pep tank will be located you will need to have that moved
LATH/BRICK/ WATER BARRIER 07/29/2019 APPROVED MWILLIAMS
ELECTRIC - EARLY POWER 07/23/2019 CANCELLED BY APPLICANT WEB
INSULATION 07/16/2019 APPROVED JDELBONIS
ALL ROUGH 07/03/2019 APPROVED MWILLIAMS
ROOF SHEATHING / BRACES/TIES/DOWN CELL 05/20/2019 APPROVED WMILLER
ROOF VALLEY & METAL 05/20/2019 APPROVED WMILLER
ROOF SHEATHING 05/16/2019 APPROVED - AS NOTED WMILLER
Note: (ROOF SHEATHING ONLY)
TIE BEAM / LINTEL 05/06/2019 APPROVED DROCKWELL
FOUND SURVEY APPROVED (OFFICE) 05/03/2019 APPROVED JHINDMAN
MONOLITHIC SLAB 04/16/2019 APPROVED MWILLIAMS
PLUMBING 1ST ROUGH UNDERGROUND 04/09/2019 APPROVED JGIBSON
ELECTRIC TEMP POLE 04/04/2019 APPROVED - AS NOTED RMARTIN
Note: SPOKE TO DELL FPL RELEASED POWER 3:30

Review History

Department Status Date In Date Out
SW1 COMPLETE 05/01/2019 05/03/2019
Note: Released By: JHINDMAN foundation
MECH COMPLETE 03/11/2019 03/18/2019
Note: Released By: JHINDMAN
SWALE COMPLETE 03/04/2019 03/07/2019
Note: Released By: TBAKER
BLD COMPLETE 03/01/2019 03/07/2019
Note: Released By: JHINDMAN
ELEC COMPLETE 03/01/2019 03/07/2019
Note: Released By: JHINDMAN
ENGIN1 COMPLETE 03/01/2019 03/04/2019
Note: Released By: TBAKER
MECH HOLD 03/01/2019 03/07/2019
Note: Held By: JHINDMAN 1. Provide a a/c unit that meets the minimum load for the heat required by the energy calculations Form R405.
PLUM COMPLETE 03/01/2019 03/07/2019
Note: Released By: JHINDMAN
SW1 COMPLETE 03/01/2019 03/07/2019
Note: Released By: JHINDMAN
UD1 COMPLETE 03/01/2019 03/05/2019
Note: Released By: LFITZGERALD PEP Tank areas new home This is a PEP Tank area. The Pep Panel will be placed 5 feet from the front corner of the building on the same side of the building as the PEP tank that is marked on the Utility marked Site plan. Make sure the electrician places the PEP power wire between 3 feet and 5 feet from the ground. The plumber should exit the slab with the sewer pipe on the side of the building the tank will be on and matching the utility marked site plan, this will reduce any piping under driveways or sidewalks and minimize the fall required. The sewer tie-in inspection must be called in the day before the tie-in. The morning of the tie-in the inspector should be contacted to coordinate the time of the tie-in visual inspection so he can witness the tie-in. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap
ZON COMPLETE 03/01/2019 03/04/2019
Note: Released By: AMOBLEY

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADMIN FEE ¤20.00 03/18/2019
ELECTRIC FEE ¤180.00 03/18/2019
3% FIRE IMPACT FEE CREDIT (¤6.70) 03/18/2019
IMPACT FEE FIRE ¤223.38 03/18/2019
IMPACT FEE PARKS ¤849.24 03/18/2019
IMPACT FEE SCHOOL ¤3,600.00 03/18/2019
IMPACT FEE TRANSPORTATION ¤1,632.00 03/18/2019
MECHANICAL FEE ¤180.00 03/18/2019
3% PARKS IMPACT FEE CREDIT (¤25.48) 03/18/2019
PLAN CHECK FEE ¤80.00 03/18/2019
PLUMBING FEE ¤180.00 03/18/2019
NEW RESIDENTIAL INSPECTIONS ¤400.00 03/18/2019
SITE PLAN 20 ¤20.00 03/18/2019
SURCHARGE FS 533.721 ¤10.60 03/18/2019
SURCHARGE - FS 468.631 ¤15.90 03/18/2019
STORM WATER PERMIT FEES ¤80.00 03/18/2019
3% TRANS IMPACT FEE CREDIT (¤48.96) 03/18/2019
Fees Total Due: ¤0.00 Total Paid: ¤7,389.98