Permit #2019030901
Permit Details
Status: COED
| Parcel Id: 07-11-31-7032-00390-0200 |
| CONDITIONED SPACE: 1683 sqft |
| GARAGE: 558 sqft |
| OPENED PORCH (WITH ROOF) : 40 sqft |
| OPENED PORCH (WITH ROOF) : 214 sqft |
| Total Square Footage: 2495 sqft |
| Block: 00390 |
| Subdivision: 2155 - SECTION 32-ROYAL PALMS |
| Job Phone: 407-307-4753 |
| Location Address: 19 RUSSMAN LN |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 06/06/2019 |
| NOC: RECORDED |
| Applicant name: SHAWN VIRAG |
| Owner: BRITE PROPERTIES OF FLORIDA LLC |
|
Address 619 EAST WASHINGTON STREET ORLANDO, FL 32802 |
| Lot: 0200 |
| Contracted Stated Job Value: ¤140,878.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
SHAWNTELLE CONSULTING AND DESIGN LLC
| Status | Location Address | State License Number | Phone |
| CANCEL |
611 LARGOVISTA DR OAKLAND, FL 34787 |
CBC1261160 (Exp: 08/31/2020) | 407-307-4753 |
Sub Contractors
TERRY BRICE DICKERSON
| Status | Location Address | State License Number | Phone |
| ACTIVE |
4300 ST JOHN'S PARKWAY ALPHARETTA, GA 30009 |
CCC1326209 (Exp: 08/31/2026) | 407-548-6733 |
JOSEPH H STRADA JR
| Status | Location Address | State License Number | Phone |
| CANCEL |
3400 ST JOHNS PKWY SANFORD, FL 32771 |
EC13003715 (Exp: 08/31/2022) | 877-906-1113 |
JONATHAN M PEARSON
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
209 N FORSYTH ST BUNNELL, FL 32110 |
CFC1425941 (Exp: 08/31/2026) | 386-597-0944 | 386-437-4996 |
ROBERT G DELLO RUSSO
| Status | Location Address | State License Number | Phone | Fax |
| DECEASED |
531 CODISCO WAY SANFORD, FL 32771 |
CAC032448 (Exp: 08/31/2022) | (407)831-2665 | (407)333-3853 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 02/26/2020 | FINAL APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION | |||
| BLD - BUILDING FINAL | 02/25/2020 | Disapproved -FEE REQUIRED | FWILLIS |
| Note: Smoke Alarm missing outside bedrooms 2 and 3. Outside unit not Fastened to slab with tapcons as required. (4) | |||
| ROW - FINAL APRON (AFTER POUR) | 02/25/2020 | APPROVED | MMAJEWSKI |
| ROW - STORMWATER FINAL | 02/25/2020 | APPROVED | MMAJEWSKI |
| U -UTILITY RESIDENTIAL FINAL | 02/25/2020 | FINAL APPROVED | LFITZGERALD |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 02/24/2020 | APPROVED | MMAJEWSKI |
| FINAL SURVEY (OFFICE USE ONLY) | 02/24/2020 | APPROVED | MMAJEWSKI |
| Note: THIS IS A REINSPECTION | |||
| FINAL SURVEY (OFFICE USE ONLY) | 02/18/2020 | Disapproved - NO FEE | KHOWELL |
| Note: SEE NOTES ON FINAL SURVEY MARK UP | |||
| GRAVITY SEWER TEST | 01/17/2020 | APPROVED - AS NOTED | JGIBSON |
| Note: THIS WAS DONE ON 1/16/20 AND NOTIFIED ROBERT MARTIN OF ELETRICAL UNDERGROUND SERVICE NEEDED REPAIRED. | |||
| U - SEWER TIE IN | 01/17/2020 | APPROVED | JGIBSON |
| ELECTRIC - EARLY POWER | 11/20/2019 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED POWER 3:20 | |||
| ROW- PRE-APRON (PRE-POUR) | 11/14/2019 | APPROVED - AS NOTED | KHOWELL |
| Note: THIS IS A REINSPECTION It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist READY TO POUR upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete. | |||
| ROW- PRE-APRON (PRE-POUR) | 11/13/2019 | Disapproved - NO FEE | KHOWELL |
| Note: CULVERT PIPE IS MORE THEN 8' OFF THE EDGE OF PAVEMENT, TOO WET IN CULVERT AREA TO POUR | |||
| LATH/BRICK/ WATER BARRIER | 10/11/2019 | APPROVED | JDELBONIS |
| INSULATION | 10/04/2019 | APPROVED | DROCKWELL |
| ALL ROUGH | 10/02/2019 | APPROVED | DROCKWELL |
| ROOF VALLEY & METAL | 09/20/2019 | APPROVED | JDELBONIS |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 09/19/2019 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 09/13/2019 | Disapproved -FEE REQUIRED | DROCKWELL |
| Note: THIS IS A REINSPECTION/Not all corrections made per last inspections..see list | |||
| ELECTRIC-TUG | 09/13/2019 | APPROVED | DROCKWELL |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 09/10/2019 | Disapproved -FEE REQUIRED | DROCKWELL |
| Note: Anchor all upper trusses to trusses below at each end/Provide solid blocking at all flat-top trusses..7/16 OSB cannot span more than 24in | |||
| TIE BEAM / LINTEL | 08/06/2019 | APPROVED | DROCKWELL |
| FOUND SURVEY APPROVED (OFFICE) | 08/05/2019 | APPROVED | JMUNSON |
| MONOLITHIC SLAB | 07/30/2019 | APPROVED | DROCKWELL |
| Note: THIS IS A REINSPECTION | |||
| MONOLITHIC SLAB | 07/29/2019 | Disapproved - NO FEE | FWILLIS |
| Note: Footer is caved in, in several areas. also remove any standing water as per plan. | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 07/26/2019 | CANCELLED BY INSPECTOR | JGIBSON |
| Note: THIS INSPECTION WAS ALREADY APPROVED SCHEDULED BY MISTAKE | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 07/23/2019 | APPROVED | JGIBSON |
| WATER METER INSTALLATION REQUEST | 07/12/2019 | CANCELLED BY INSPECTOR | CSTONE |
| Note: WATER METER WAS ALREADY REQUESTED AND APPROVED ON 7/3. | |||
| WATER METER INSTALLATION REQUEST | 07/03/2019 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| SW1 | COMPLETE | 08/02/2019 | 08/05/2019 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 05/06/2019 | 05/09/2019 |
| Note: Released By: TBAKER | |||
| ENGIN1 | HOLD | 04/08/2019 | 04/08/2019 |
| Note: Held By: TBAKER Survey has not been revised. See note from previous HOLD | |||
| BLD | COMPLETE | 04/08/2019 | 04/15/2019 |
| Note: Released By: JHINDMAN | |||
| PLUM | COMPLETE | 04/08/2019 | 04/15/2019 |
| Note: Released By: JHINDMAN | |||
| ENGIN1 | HOLD | 03/28/2019 | 03/28/2019 |
| Note: Held By: TBAKER Centerline of road elevations are off by .35' +/- according to benchmark. Also - the benchmark elevation written on the pole at the site does not agree with the elevation on the site plan. | |||
| BLD | HOLD | 03/25/2019 | 04/01/2019 |
| Note: Held By: JHINDMAN 1. Provide a digital signature with cwertification that can be validatedon the plan without going to a 3rd party website. Florida Aministrative Code 61g-15-23. J. Hindman 986-3784. | |||
| ELEC | COMPLETE | 03/25/2019 | 04/01/2019 |
| Note: Released By: JHINDMAN | |||
| ENGIN1 | COMPLETE | 03/25/2019 | 03/25/2019 |
| Note: Released By: TBAKER | |||
| MECH | COMPLETE | 03/25/2019 | 04/01/2019 |
| Note: Released By: JHINDMAN | |||
| PLUM | HOLD | 03/25/2019 | 04/01/2019 |
| Note: Held By: JHINDMAN 1. Provide a digital signature with cwertification that can be validatedon the plan without going to a 3rd party website. Florida Aministrative Code 61g-15-23. J. Hindman 986-3784. | |||
| SW1 | COMPLETE | 03/25/2019 | 04/01/2019 |
| Note: Released By: RLEE | |||
| UD1 | COMPLETE | 03/25/2019 | 03/27/2019 |
| Note: Released By: AHALL Gravity Sewer new homes This is a Gravity sewer, the Sewer Tie-in Inspection is a visual inspection it must be called in the day before the tie-in is to be made. The morning of the tie-in the inspector should be contacted to coordinate the time of the tie-in so he can witness the tie-in and help prevent failed inspections due to cave in or mud/water preventing the visual inspection. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap. The NFPA Clear Zone distance there can be no obstacles in front of the Hydrant and 3.0’ on both sides and 4’ behind. | |||
| ZON | COMPLETE | 03/25/2019 | 03/26/2019 |
| Note: Released By: AMOBLEY | |||
| SWALE | COMPLETE | 03/25/2019 | 05/15/2019 |
| Note: Released By: TBAKER |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 03/20/2020 |
| REINSPECTION FEE | ¤40.00 | 12/05/2019 |
| REINSPECTION FEE | ¤40.00 | 12/05/2019 |
| NEW RESIDENTIAL INSPECTIONS | ¤440.00 | 06/06/2019 |
| SITE PLAN 20 | ¤20.00 | 06/06/2019 |
| SURCHARGE FS 533.721 | ¤11.44 | 06/06/2019 |
| SURCHARGE - FS 468.631 | ¤17.16 | 06/06/2019 |
| STORM WATER PERMIT FEES | ¤80.00 | 06/06/2019 |
| 3% TRANS IMPACT FEE CREDIT | (¤48.96) | 06/06/2019 |
| ADMIN FEE | ¤20.00 | 06/06/2019 |
| ELECTRIC FEE | ¤192.00 | 06/06/2019 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 06/06/2019 |
| IMPACT FEE FIRE | ¤223.38 | 06/06/2019 |
| IMPACT FEE PARKS | ¤849.24 | 06/06/2019 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 06/06/2019 |
| IMPACT FEE TRANSPORTATION | ¤1,632.00 | 06/06/2019 |
| MECHANICAL FEE | ¤192.00 | 06/06/2019 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 06/06/2019 |
| PLAN CHECK FEE | ¤88.00 | 06/06/2019 |
| PLUMBING FEE | ¤192.00 | 06/06/2019 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤7,596.08 |