I want to search for...

Permit #2019031045

Permit Details

Status: CANCEL

Parcel Id: 07-11-31-0325-00000-0230
Block: 00000
Subdivision: 1014 - ARLINGTON SUBDIVISION
Job Phone: 386-547-6556
Location Address: 29 MOUNT VERNON LN
Type: DR - DRIVEWAY
Issue Date: 04/02/2019
NOC: RECORDED
Applicant name: RAY COPELAND
Owner: PRESTON, HOWARD L & CATHLEEN A

Address

29 MOUNT VERNON LANE

PALM COAST, FL 32164

Lot: 0230
Contracted Stated Job Value: ¤7,900.00
Job Description: REPLACE CONCRETE DRIVEWAY & WALKWAY WITH PAVERS
Type: CN

Contractor

ATLANTIC BRICK PAVERS INC
Status Location Address Phone
HOLD

8 SECRETARY TRAIL

PALM COAST, FL 32164

386-547-6556

Inspection History

Type Request Date Result Inspector
ROW- PRE-APRON (PRE-POUR) 04/11/2019 APPROVED - AS NOTED KHOWELL
Note: THIS IS A REINSPECTION THE SIDEWALK REPAIR ON THE LEFT SIDE IS NOT ACCEPTABLE, THE CITY DOES NOT ALLOW SMALL PATCHES THE WHOLE PANEL IS REQUIRED TO BE REPLACED
ROW- PRE-APRON (PRE-POUR) 04/05/2019 CANCELLED BY APPLICANT KHOWELL
ROW - FINAL APRON (AFTER POUR) 04/05/2019 CANCELLED BY APPLICANT KHOWELL
Note: INSPECTION IS AFTER PAVERS ARE INSTALLED AND EDGES BACKED AND SOD PLACED
ROW- PAVER RESTRAINTS 04/04/2019 APPROVED - AS NOTED KHOWELL
Note: I SUGGEST THAT THE SPRINKLER LINE 90 DEGREE BENDS GET MOVED OUT OF THE FOOTER, THAT IS YOUR CALL
ROW - FINAL APRON (AFTER POUR)
Note: THIS IS A REINSPECTION
ROW - FINAL INSPECTION
U -UTILITY RESIDENTIAL FINAL

Review History

Department Status Date In Date Out
ENGIN1 COMPLETE 03/27/2019 03/27/2019
Note: Released By: TBAKER
SW1 CANCEL 03/27/2019 03/28/2019
UD1 COMPLETE 03/27/2019 04/01/2019
Note: Released By: AHALL All Concrete, Driveways, Pavers, Pools / Sidewalks ETC. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap. The NFPA Clear Zone distance there can be no obstacles in front of the Hydrant and 7.5’ on the sides or 4’ behind.
ZON COMPLETE 03/27/2019 03/27/2019
Note: Released By: AMOBLEY

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADMIN FEE ¤20.00 04/02/2019
RECORDING FEE REIMBURSE DOC ¤44.00 04/02/2019
SITE PLAN 20 ¤20.00 04/02/2019
SURCHARGE FS 533.721 ¤2.00 04/02/2019
SURCHARGE - FS 468.631 ¤2.00 04/02/2019
STORM WATER PERMIT FEES ¤40.00 04/02/2019
Fees Total Due: ¤0.00 Total Paid: ¤128.00