I want to search for...

Permit #2019040185

Permit Details

Status: COED

Parcel Id: 48-11-31-1710-00000-0620
CONDITIONED SPACE: 3289 sqft
GARAGE: 950 sqft
OPENED PORCH (WITH ROOF) : 672 sqft
OPENED PORCH (WITH ROOF) : 106 sqft
Total Square Footage: 5017 sqft
Block: 00000
Subdivision: 2087 - ESTATES AT GRAND HAVEN PHASE II
Job Phone: (386)445-2012
Location Address: 45 SCARLET OAK CIR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 04/19/2019
NOC: RECORDED
Applicant name: JOHN DONALD GORDON
Owner: SMITH DAVID H & SUSAN F H&W

Address

744 PONUS RIDGE RD

NEW CANAAN, CT 06840

Lot: 0620
Contracted Stated Job Value: ¤416,597.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

SKYWAY BUILDERS INC.
Status Location Address State License Number Phone Fax
INACTIVE

P. O. Box 354786

Palm Coast, FL 32137

CGC062646 (Exp: 08/31/2020) (386)445-2012 (386)446-7928

Sub Contractors

MARK JOHN LUTCZA
Status Location Address State License Number Phone
ACTIVE

26 ROYAL LEAF LANE

PALM COAST, FL 32164

EC13005145 (Exp: 08/31/2026) 386-586-0770
DANIEL DAVID RUTKOWSKI III
Status Location Address State License Number Phone Fax
ACTIVE

1687 STATE AVENUE

HOLLY HILL, FL 32117

CCC1328639 (Exp: 08/31/2026) 386-290-7490 386-256-0001
THOMAS WALTER ALBANO
Status Location Address State License Number Phone Fax
INACTIVE

P. O. BOX 352075

Palm Coast, FL 32135

CFC045991 (Exp: 08/31/2024) 386-437-2795 (386)437-2781
THOMAS A REGULA
Status Location Address State License Number Phone Fax
INACTIVE

11320 PHILLIPS PKWY DRIVE E

JACKSONVILLE, FL 32256

CMC1250075 (Exp: 08/31/2026) 904-278-0339 904-278-0366
GEORGE F AYLSWORTH JR
Status Location Address State License Number Phone Fax
DECEASED

2680 S US HIGHWAY 17

CRESCENT CITY, FL 32112

00714 (Exp: 08/31/2021) 386-698-1033 386-698-1077

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 02/26/2020 FINAL APPROVED JDELBONIS
Note: THIS IS A REINSPECTION
BLD - BUILDING FINAL 02/25/2020 Disapproved -FEE REQUIRED JDELBONIS
Note: THIS IS A REINSPECTION lock out braker on wall ovens GFCI braker in bathrooms 210.8 A
ROW - FINAL APRON (AFTER POUR) 02/24/2020 APPROVED RGROSS
BLD - BUILDING FINAL 02/24/2020 CANCELLED BY APPLICANT JDELBONIS
GAS ROUGH 02/24/2020 APPROVED JGIBSON
Note: THIS IS A REINSPECTION
GAS FINAL 02/24/2020 APPROVED JGIBSON
ROW - STORMWATER FINAL 02/24/2020 APPROVED RGROSS
U -UTILITY RESIDENTIAL FINAL 02/24/2020 FINAL APPROVED LFITZGERALD
FINAL SURVEY (OFFICE USE ONLY) 02/21/2020 Disapproved - NO FEE RGROSS
Note: THIS IS A REINSPECTION. SEE ATTACHMENT FIELD SURVEY MARK-UP. LANDSCAPING IN THE EASEMENT ON THE RIGHT SIDE PROPERTY LINE MUST BE REMOVED. ALSO GRADE ELEVATIONS NEEDED ALONG THE RIGHT SIDE 10 FT FROM OFF BUILDING FOUNDATION ELEVATIONS.
FINAL SURVEY (OFFICE USE ONLY) 02/21/2020 APPROVED - AS NOTED RGROSS
Note: THIS IS A REINSPECTION. FINAL SURVEY DID HAVE THE ELEVATIONS ALONG THE LEFT PROPERTY LINE, NOT ORIGINALLY SEEN BY INSPECTOR. THIS SUB-DIVISION DOES NOT HAVE AN EASEMENT PER SUB PLAT. NO LANDSCAPING NEEDS REMOVED. THUS APPROVED AS-NOTED.
ROW FIELD SURVEY /GRADING CERTIFICATION 02/21/2020 Disapproved - NO FEE RGROSS
Note: SEE FIELD SURVEY MARK-UP
ROW FIELD SURVEY /GRADING CERTIFICATION 02/21/2020 APPROVED - AS NOTED RGROSS
Note: THIS IS A REINSPECTION. INSPECTOR LOOKED AT THE WRONG SURVEY WITH MISSING GRADE ELEVATIONS. THIS SUB-DIVISION HAS NO EASEMENTS PER PLAT.
U-CROSS CONNECTION 02/20/2020 APPROVED LFITZGERALD
FINAL SURVEY (OFFICE USE ONLY) 02/19/2020 Disapproved - NO FEE MMAJEWSKI
Note: ELEVATIONS ALONG FOUNDATION NEED TO BE A MINIMUM OF 4 INCHES BELOW F/F
U-CROSS CONNECTION 02/06/2020 CANCELLED BY APPLICANT WEB
ROW- PRE-APRON (PRE-POUR) 01/09/2020 APPROVED - AS NOTED RGROSS
Note: SECOND PART OF A PRE POUR. PAVERS AND BASE ON SITE.
GAS ROUGH 01/09/2020 PARTIALLY APPROVED JGIBSON
Note: this was a partial inspection on gas line ran from tank to house, another gas rough and gas final can be scheduled at same time for next time
ROW- PRE-APRON (PRE-POUR) 01/08/2020 CANCELLED BY APPLICANT WEB
Note: THIS IS A REINSPECTION
GAS ROUGH 12/30/2019 Disapproved -FEE REQUIRED JGIBSON
Note: NO PLANS OR PAPER WORK POSTED AT TIME OF INSPECTION 1: 54, NO TEST ON GAS LINE.
ROW- PAVER RESTRAINTS 12/06/2019 APPROVED RGROSS
ROW- PRE-APRON (PRE-POUR) 12/06/2019 PARTIALLY APPROVED RGROSS
Note: APPROVED FOR CONCRETE APRON PLUS 30 FT. UPPER PART OF DRIVEWAY ARE PAVERS. PAVER RESTRAINTS APPROVED.
U - SEWER TIE IN 11/06/2019 APPROVED MWILLIAMS
GRAVITY SEWER TEST 11/06/2019 APPROVED MWILLIAMS
ELECTRIC - EARLY POWER 10/09/2019 APPROVED - AS NOTED RMARTIN
GAS ROUGH 09/11/2019 APPROVED JGIBSON
INSULATION 08/27/2019 APPROVED MWILLIAMS
LATH/BRICK/ WATER BARRIER 08/21/2019 APPROVED MWILLIAMS
ALL ROUGH 08/15/2019 APPROVED DROCKWELL
ROOF VALLEY & METAL 07/25/2019 APPROVED FWILLIS
ROOF SHEATHING / BRACES/TIES/DOWN CELL 07/18/2019 APPROVED - AS NOTED MWILLIAMS
Note: also checked sliding door for fastening at request of Builder.
WINDOW NAILING 07/17/2019 CANCELLED BY INSPECTOR MWILLIAMS
Note: This inspection not required . Windows installed in CMU walls Windows are inspected at the all rough
ELECTRIC-TUG 06/24/2019 APPROVED - AS NOTED RMARTIN
Note: spoke to susan fpl released power 3:40
TIE BEAM / LINTEL 06/07/2019 APPROVED WMILLER
FOUND SURVEY APPROVED (OFFICE) 06/04/2019 APPROVED JMUNSON
ELEV CERT-FOUNDATION APPROVAL 05/31/2019 APPROVED JMYERS
MONOLITHIC SLAB 05/17/2019 APPROVED WMILLER
PLUMBING 1ST ROUGH UNDERGROUND 05/15/2019 APPROVED JGIBSON

Review History

Department Status Date In Date Out
PLFM COMPLETE 02/20/2020 02/20/2020
Note: Released By: JMYERS Final elevation certificate has been accepted
PLFM COMPLETE 02/18/2020 02/18/2020
Note: Released By: JMYERS Final elevation certificate has been accepted
SW1 COMPLETE 05/31/2019 06/04/2019
Note: Released By: JMUNSON Foundation S
PLFM COMPLETE 05/31/2019 05/31/2019
Note: Released By: JMYERS The Building elevation certificate has been accepted. Please provide Final prior to receiving CO.
ZON COMPLETE 04/18/2019 04/18/2019
Note: Released By: AMOBLEY
PLFM COMPLETE 04/15/2019 04/15/2019
Note: Released By: JMYERS The Construction elevation certificate has been accepted, however future elevation certificates will need to be sealed with a Raised seal as well as signed and dated on top of the seal. Informational: the phone number listed on the elevation certificate is incorrect.
ZON HOLD 04/10/2019 04/10/2019
Note: Held By: AMOBLEY Flood number not filled in on survey Please correct survey not site plan
PLFM HOLD 04/10/2019 04/11/2019
Note: Held By: JMYERS Please turn a hard copy of the elevation certificate with the previous hold comments corrected.
MECH COMPLETE 04/10/2019 04/17/2019
Note: Released By: JHINDMAN
ELEC COMPLETE 04/10/2019 04/16/2019
Note: Released By: JHINDMAN
BLD COMPLETE 04/10/2019 04/16/2019
Note: Released By: JHINDMAN
PLFM HOLD 04/04/2019 04/04/2019
Note: Elevation certificates cannot be submitted electronically. A hard copy of the Construction, Building, and Final must be turned in. In Section A8. A, b, and c must have N/A you cannot leave them blank. A8. D must be check with yes or no. In Section A9. B and c must have N/A you cannot leave them blank or have a 0. B9 must read 8.0’ The hard copies must be signed and sealed with a raised seal.
BLD HOLD 04/03/2019 04/09/2019
Note: Held By: JHINDMAN 1. Identify the lintel sizes and types on the floorplan 6th ed. FBC 107.3.5.
ELEC HOLD 04/03/2019 04/09/2019
Note: Held By: JHINDMAN 1. provide electrical load calculationssigned by the electrical contractor with their license number. 6th ed. FBC 107.1.
ENGIN1 COMPLETE 04/03/2019 04/04/2019
Note: Released By: TBAKER
LOCATE COMPLETE 04/03/2019 04/03/2019
Note: Released By: CSTONE
MECH HOLD 04/03/2019 04/09/2019
Note: Held By: JHINDMAN 1. provide energy calculations per 6th ed. FBC EC R405. file marked energy has an elevation cert.
PLUM COMPLETE 04/03/2019 04/09/2019
Note: Released By: JHINDMAN
SW1 COMPLETE 04/03/2019 04/09/2019
Note: Released By: JHINDMAN
UD1 COMPLETE 04/03/2019 04/09/2019
Note: Released By: AHALL Gravity Sewer new homes This is a Gravity sewer, the Sewer Tie-in Inspection is a visual inspection it must be called in the day before the tie-in is to be made. The morning of the tie-in the inspector should be contacted to coordinate the time of the tie-in so he can witness the tie-in and help prevent failed inspections due to cave in or mud/water preventing the visual inspection. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap. The NFPA Clear Zone distance there can be no obstacles in front of the Hydrant and 3.0’ on both sides and 4’ behind.
ZON HOLD 04/03/2019 04/04/2019
Note: Held By: AMOBLEY Flood number not on survey Please correct survey

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 02/26/2020
REINSPECTION FEE ¤40.00 02/26/2020
NEW RESIDENTIAL INSPECTIONS ¤872.00 04/19/2019
SITE PLAN 20 ¤20.00 04/19/2019
SURCHARGE FS 533.721 ¤20.51 04/19/2019
SURCHARGE - FS 468.631 ¤30.77 04/19/2019
STORM WATER PERMIT FEES ¤80.00 04/19/2019
3% TRANS IMPACT FEE CREDIT (¤89.43) 04/19/2019
ADMIN FEE ¤20.00 04/19/2019
ELECTRIC FEE ¤321.60 04/19/2019
3% FIRE IMPACT FEE CREDIT (¤6.70) 04/19/2019
IMPACT FEE FIRE ¤223.38 04/19/2019
IMPACT FEE PARKS ¤849.24 04/19/2019
IMPACT FEE SCHOOL ¤3,600.00 04/19/2019
IMPACT FEE TRANSPORTATION ¤2,981.00 04/19/2019
MECHANICAL FEE ¤321.60 04/19/2019
3% PARKS IMPACT FEE CREDIT (¤25.48) 04/19/2019
PLAN CHECK FEE ¤174.40 04/19/2019
PLUMBING FEE ¤321.60 04/19/2019
Fees Total Due: ¤0.00 Total Paid: ¤9,794.49