Permit #2019040588
Permit Details
Status: CANCEL
| Parcel Id: 07-11-31-7009-00110-0180 |
| Block: 00110 |
| Subdivision: 2208 - SECTION 9-FLORIDA PARK |
| Job Phone: 386-931-1725 |
| Location Address: 56 FARMSWORTH DR |
| Type: DR - DRIVEWAY |
| Issue Date: 05/06/2019 |
| NOC: Unknown |
| Applicant name: JOSEPH ALEIXO PORTAL |
| Owner: TRAULSEN ERIK O & INGRID H H&W & ANN M TRAULSEN JT |
|
Address UNIT B PALM COAST, FL 32137 |
|
Address 56 FARMSWORTH DRIVE PALM COAST, FL 32137 |
| Lot: 0180 |
| Contracted Stated Job Value: ¤2,500.00 |
| Job Description: WIDEN EXISTING CONCRETE DRIVEWAYS |
| Type: CN |
Contractor
SWEETWATER CUSTOM HOMES INC.
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
1105 LAMBERT AVENUE FLAGLER BEACH, FL 32136 |
CBC1252965 (Exp: 08/31/2024) | 386-931-1725 | 386-439-4676 |
Inspection History
| Type | Request Date | Result | Inspector |
| ROW- PRE-APRON (PRE-POUR) | 05/08/2019 | APPROVED - AS NOTED | RGROSS |
| Note: CONTRACTOR TO MAKE A SMALL ADJUSTMENT TO THE MITERED FORM. AFTER THAT, READY TO POUR. | |||
| ROW - FINAL APRON (AFTER POUR) | |||
| ROW - FINAL INSPECTION | |||
| U -UTILITY RESIDENTIAL FINAL |
Review History
| Department | Status | Date In | Date Out |
| ZON | COMPLETE | 05/01/2019 | 05/01/2019 |
| Note: Released By: TDOAK | |||
| ENGIN1 | COMPLETE | 05/01/2019 | 05/03/2019 |
| Note: Released By: TBAKER | |||
| SW1 | COMPLETE | 05/01/2019 | 05/01/2019 |
| Note: Released By: JHINDMAN | |||
| UD1 | COMPLETE | 05/01/2019 | 05/06/2019 |
| Note: Released By: AHALL | |||
| ENGIN1 | COMPLETE | 04/12/2019 | 04/16/2019 |
| Note: Released By: TBAKER | |||
| SW1 | COMPLETE | 04/12/2019 | 04/12/2019 |
| Note: Released By: JHINDMAN | |||
| UD1 | COMPLETE | 04/12/2019 | 04/24/2019 |
| Note: Released By: AHALL All Concrete, Driveways, Pavers, Pools / Sidewalks ETC. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap. The NFPA Clear Zone distance there can be no obstacles in front of the Hydrant and 7.5’ on the sides or 4’ behind. | |||
| ZON | HOLD | 04/12/2019 | 04/12/2019 |
| Note: Held By: TDOAK 1. Site plan must depict material to be used to repair/widen driveway. 2. There is conflicting information of the site plan regarding the dimensions. One area says that the left driveway will be widened 4' on the right side but then there is a note on the bottom that says the driveway will be widened to 21.5'. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADMIN FEE | ¤20.00 | 05/06/2019 |
| SITE PLAN 20 | ¤20.00 | 05/06/2019 |
| SURCHARGE FS 533.721 | ¤2.00 | 05/06/2019 |
| SURCHARGE - FS 468.631 | ¤2.00 | 05/06/2019 |
| STORM WATER PERMIT FEES | ¤40.00 | 05/06/2019 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤84.00 |