I want to search for...

Permit #2019040941

Permit Details

Status: COED

Parcel Id: 07-11-31-7057-00450-0010
CONDITIONED SPACE: 1502 sqft
GARAGE: 500 sqft
OPENED PORCH (WITH ROOF) : 70 sqft
OPENED PORCH (WITH ROOF) : 234 sqft
Total Square Footage: 2306 sqft
Block: 00450
Subdivision: 2123 - SECTION 57-ULYSSES TREES
Job Phone: 386-447-4151
Location Address: 18 UNIQUE CT
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 04/26/2019
NOC: RECORDED
Applicant name: GENE WARREN SLONE
Owner: ROBERTS DENNIS & SHARON ROBERTS H&W

Address

4313 CANAL AVE

BUNNELL, FL 32110

Lot: 0010
Contracted Stated Job Value: ¤200,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

FLORIDA GREEN CONSTRUCTION INC.
Status Location Address State License Number Phone
INACTIVE

870 E RETTA STREET

DELEON SPRINGS, FL 32130

CBC1260957 (Exp: 08/31/2026) 407-580-2657

Sub Contractors

JONATHAN M PEARSON
Status Location Address State License Number Phone Fax
ACTIVE

209 N FORSYTH ST

BUNNELL, FL 32110

CFC1425941 (Exp: 08/31/2026) 386-597-0944 386-437-4996
GREGG A MCANALLY
Status Location Address State License Number Phone
INACTIVE

3370 AGRICULTURAL CENTER DRIVE

PALM COAST, FL 32092

CAC1815760 (Exp: 08/31/2022) 904-829-8898
OLEG BELINSKIY
Status Location Address State License Number Phone
ACTIVE

19 PINE CIRCLE DRIVE19

PALM COAST, FL 32167

CCC1325974 (Exp: 08/31/2026) 386-263-7906
JOHN EDWARD GAMBONE
Status Location Address Mailing Address State License Number Phone
ACTIVE

15 HARGROVE LN

PALM COAST, FL 32137

1G

PALM COAST, FL 32137

EC13006037 (Exp: 08/31/2026) 386-586-9144

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 02/07/2020 FINAL APPROVED FWILLIS
Note: THIS IS A REINSPECTION
BLD - BUILDING FINAL 02/06/2020 Disapproved - NO FEE FWILLIS
Note: House has furniture, boxes and personal items throughout. CAN NOT MOVE IN UNTIL FINAL IS APPROVED. Could not test some of the Outlets in garage. Tom much Clutter. GFCI in bathroom not working. Can not reset. Need Insulation Calc, normally posted on Truss in attic. INSPECTION STOPPED.
ELECTRIC - EARLY POWER 01/24/2020 APPROVED - AS NOTED RMARTIN
Note: EMAILED FPL RELEASED POWER 10:40
ELECTRIC - EARLY POWER 01/22/2020 Disapproved -FEE REQUIRED RMARTIN
Note: FIXTURE BRACKET NOT GROUNDED.... PER MANUFACTURE SPEC AND NEC 410.40 AND 110.3B CONTRACTOR NEEDS TO MEET ON SITE TO CHECK ALL FIXTURES ON RE-INSPECTION
ROW - FINAL APRON (AFTER POUR) 01/22/2020 APPROVED MMAJEWSKI
ROW - STORMWATER FINAL 01/22/2020 APPROVED MMAJEWSKI
U -UTILITY RESIDENTIAL FINAL 01/22/2020 APPROVED AHALL
ROW FIELD SURVEY /GRADING CERTIFICATION 01/16/2020 APPROVED MMAJEWSKI
FINAL SURVEY (OFFICE USE ONLY) 01/16/2020 APPROVED MMAJEWSKI
ROW- PRE-APRON (PRE-POUR) 12/03/2019 APPROVED - AS NOTED KHOWELL
Note: THIS IS A REINSPECTION It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist READY TO POUR upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete.
ROW- PRE-APRON (PRE-POUR) 11/19/2019 Disapproved - NO FEE KHOWELL
Note: SLOPE ON APRON IS MORE THEN MAXIMUM ALLOWED OF 8%
INSULATION 10/15/2019 APPROVED FWILLIS
LATH/BRICK/ WATER BARRIER 10/07/2019 APPROVED JDELBONIS
ALL ROUGH 10/01/2019 APPROVED - AS NOTED JDELBONIS
Note: dryer vent is outside of wall studsand celing in closet needs to be reworked or wall needs to be fered out
GRAVITY SEWER TEST 09/20/2019 APPROVED JGIBSON
U - SEWER TIE IN 09/20/2019 APPROVED JGIBSON
ROOF VALLEY & METAL 07/19/2019 APPROVED DROCKWELL
ROOF SHEATHING / BRACES/TIES/DOWN CELL 07/15/2019 APPROVED DROCKWELL
TIE BEAM / LINTEL 06/20/2019 APPROVED - AS NOTED DROCKWELL
Note: Corrections were made during inspection
FOUND SURVEY APPROVED (OFFICE) 06/18/2019 APPROVED JMUNSON
MONOLITHIC SLAB 06/03/2019 APPROVED DROCKWELL
PLUMBING 1ST ROUGH UNDERGROUND 05/30/2019 APPROVED JGIBSON
ELECTRIC TEMP POLE 05/10/2019 APPROVED - AS NOTED RMARTIN
Note: SPOKE TO SUSAN FPL RELEASED POWER 10:30

Review History

Department Status Date In Date Out
SW1 COMPLETE 06/17/2019 06/18/2019
Note: Released By: JMUNSON foundation s
BLD COMPLETE 04/22/2019 04/26/2019
Note: Released By: JHINDMAN
ELEC COMPLETE 04/22/2019 04/26/2019
Note: Released By: JHINDMAN
ENGIN1 COMPLETE 04/22/2019 04/22/2019
Note: Released By: TBAKER
LOCATE COMPLETE 04/22/2019 04/24/2019
Note: Released By: CSTONE
MECH COMPLETE 04/22/2019 04/26/2019
Note: Released By: JHINDMAN
PLUM COMPLETE 04/22/2019 04/26/2019
Note: Released By: JHINDMAN
SW1 COMPLETE 04/22/2019 04/25/2019
Note: Released By: RLEE
UD1 COMPLETE 04/22/2019 04/26/2019
Note: Released By: AHALL Gravity Sewer new homes This is a Gravity sewer, the Sewer Tie-in Inspection is a visual inspection it must be called in the day before the tie-in is to be made. The morning of the tie-in the inspector should be contacted to coordinate the time of the tie-in so he can witness the tie-in and help prevent failed inspections due to cave in or mud/water preventing the visual inspection. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap. The NFPA Clear Zone distance there can be no obstacles in front of the Hydrant and 3.0’ on both sides and 4’ behind.
ZON COMPLETE 04/22/2019 04/24/2019
Note: Released By: AMOBLEY
SWALE COMPLETE 04/22/2019 05/02/2019
Note: Released By: TBAKER

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 02/06/2020
NEW RESIDENTIAL INSPECTIONS ¤400.00 04/26/2019
SITE PLAN 20 ¤20.00 04/26/2019
SURCHARGE FS 533.721 ¤10.60 04/26/2019
SURCHARGE - FS 468.631 ¤15.90 04/26/2019
STORM WATER PERMIT FEES ¤80.00 04/26/2019
3% TRANS IMPACT FEE CREDIT (¤48.96) 04/26/2019
ADMIN FEE ¤20.00 04/26/2019
ELECTRIC FEE ¤180.00 04/26/2019
3% FIRE IMPACT FEE CREDIT (¤6.70) 04/26/2019
IMPACT FEE FIRE ¤223.38 04/26/2019
IMPACT FEE PARKS ¤849.24 04/26/2019
IMPACT FEE SCHOOL ¤3,600.00 04/26/2019
IMPACT FEE TRANSPORTATION ¤1,632.00 04/26/2019
MECHANICAL FEE ¤180.00 04/26/2019
3% PARKS IMPACT FEE CREDIT (¤25.48) 04/26/2019
PLAN CHECK FEE ¤80.00 04/26/2019
PLUMBING FEE ¤180.00 04/26/2019
Fees Total Due: ¤0.00 Total Paid: ¤7,429.98