I want to search for...
Permit #2019050451
Permit Details
Status: COED
| Parcel Id: 06-12-31-5825-00000-0220 |
| Total Square Footage: 48425 sqft |
| Block: 00000 |
| Subdivision: 2304 - CENTRAL LANDINGS APARTMENTS AT TOWN CENTER |
| Location Address: 3000 COASTAL TRCE BLDG 3 |
| Type: BM - BUILDING MULTI - APARTMENT |
| Issue Date: 08/20/2019 |
| NOC: RECORDED |
| Applicant name: WILLIAM SCOTT CULP |
| Owner: CENTRAL LANDINGS PARTNERS LTD & CENTRAL LANDINGS 8 |
|
Address 335 N KNOWLES AVE STE 101 WINTER PARK, FL 32789 |
| Lot: 0220 |
| Contracted Stated Job Value: ¤2,857,075.00 |
| Job Description: BLDG #3 - 39 UNIT MULTIFAMILY APARTMENT - CENTRAL LANDINGS |
| Type: CN |
Contractor
WPGC CONSTRUCTIONI, LLC
| Status | Location Address | Mailing Address | State License Number |
| CANCEL |
200 EAST CANTON AVE , |
STE 102 WINTER PARK, FL 32789 |
CGC1524369 (Exp: 08/31/2022) |
Sub Contractors
RANCE F BORDERICK
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
430 WEST DRIVE ALTAMONTE SPRINGS, FL 32714 |
EC0000981 (Exp: 08/31/2026) | (407)788-3500 | 407-788-2007 |
DAVID A CROSON
| Status | Location Address | State License Number | Phone |
| CANCEL |
31550 COUNTY ROAD 437 SORRENTO, FL 32776 |
CFC1426109 (Exp: 08/31/2022) | 352-729-7100 |
JOHN MAXEN BARTKOVICH
| Status | Location Address | State License Number | Phone |
| ACTIVE |
818 SHADOWMOSS DR WINTERGARDEN, FL 32787 |
CAC1815793 (Exp: 08/31/2026) | 407-886-3729 |
JACK DOUGLAS LANIER
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
485 COMMERCE WAY LONGWOOD , FL 32750 |
CCC058022 (Exp: 08/31/2026) | (321)441-2300 | (321)441-2313 |
Inspection History
| Type | Request Date | Result | Inspector |
| BUILDING FINAL | 05/18/2020 | Approval - Private Provider | PPROVIDER |
| FIRE FINAL | 05/14/2020 | APPROVED | WMILLER |
| U - UTILITY COMMERCIAL FINAL | 05/14/2020 | APPROVED | MBACON |
| GRAVITY SEWER | 05/14/2020 | APPROVED | JGIBSON |
| BLD - SEWER TIE IN | 05/14/2020 | APPROVED | JGIBSON |
| ELECTRIC FINAL | 05/14/2020 | Approval - Private Provider | PPROVIDER |
| ELECTRIC FINAL | 05/11/2020 | Approval - Private Provider | BBEMBRY |
| HVAC FINAL | 05/11/2020 | Approval - Private Provider | PPROVIDER |
| PLUMBING FINAL | 05/11/2020 | Approval - Private Provider | PPROVIDER |
| ROOF FINAL | 05/06/2020 | Approval - Private Provider | PPROVIDER |
| ELECTRIC - EARLY POWER | 04/27/2020 | Approval - Private Provider | PPROVIDER |
| Note: Building 3 pre power inspection passed. Please issue release of power for the following units: 3101 3201 3301 3102 3202 3302 3103 3203 3303 3104 3204 3304 3105 3205 3305 3106 3206 3306 3107 3207 3307 3108 3208 3308 3109 3209 3309 3110 3210 3310 3111 3211 3311 3112 3212 3312 3113 3213 3313 | |||
| FRAMING | 04/06/2020 | Approval - Private Provider | PPROVIDER |
| FLOOR/WALL PENETRATION | 04/06/2020 | Approval - Private Provider | PPROVIDER |
| INSULATION | 04/06/2020 | Approval - Private Provider | PPROVIDER |
| INSULATION | 04/01/2020 | Approval - Private Provider | PPROVIDER |
| INSULATION | 04/01/2020 | Approval - Private Provider | PPROVIDER |
| FLOOR/WALL PENETRATION | 04/01/2020 | Approval - Private Provider | PPROVIDER |
| FRAMING | 04/01/2020 | Approval - Private Provider | PPROVIDER |
| FRAMING | 04/01/2020 | Approval - Private Provider | PPROVIDER |
| Note: Building 3 - 2nd floor RC and insulation | |||
| FRAMING | 04/01/2020 | Approval - Private Provider | PPROVIDER |
| FRAMING | 03/30/2020 | Approval - Private Provider | PPROVIDER |
| FLOOR/WALL PENETRATION | 03/25/2020 | Approval - Private Provider | PPROVIDER |
| ABOVE CEILING | 03/23/2020 | Approval - Private Provider | PPROVIDER |
| FRAMING | 03/23/2020 | Approval - Private Provider | PPROVIDER |
| ELECTRIC 2ND ROUGH | 03/23/2020 | Approval - Private Provider | PPROVIDER |
| ELECTRIC 1ST ROUGH | 03/23/2020 | Approval - Private Provider | PPROVIDER |
| PLUMBING 2ND ROUGH | 03/23/2020 | Approval - Private Provider | PPROVIDER |
| HVAC ROUGH | 03/23/2020 | Approval - Private Provider | PPROVIDER |
| ELECTRIC 1ST ROUGH | 03/19/2020 | Approval - Private Provider | PPROVIDER |
| FRAMING | 03/19/2020 | Approval - Private Provider | PPROVIDER |
| INSULATION | 03/19/2020 | Approval - Private Provider | PPROVIDER |
| FIREWALL | 03/18/2020 | Approval - Private Provider | PPROVIDER |
| FLOOR/WALL PENETRATION | 03/18/2020 | Approval - Private Provider | PPROVIDER |
| ABOVE CEILING | 03/16/2020 | Approval - Private Provider | PPROVIDER |
| FRAMING | 03/16/2020 | Approval - Private Provider | PPROVIDER |
| Note: building 3 - 2nd floor mechanical, plumbing 2nd rough , framing and above ceiling | |||
| FRAMING | 03/16/2020 | Approval - Private Provider | PPROVIDER |
| Note: building 3 - 3rd floor aHU lids, dampers, insulation and RC , AC closets | |||
| ELECTRIC 1ST ROUGH | 03/16/2020 | Approval - Private Provider | PPROVIDER |
| Note: 2nd floor elec rough | |||
| ELECTRIC 2ND ROUGH | 03/16/2020 | Approval - Private Provider | PPROVIDER |
| Note: building 3 - 2nd floor | |||
| HVAC ROUGH | 03/16/2020 | Approval - Private Provider | PPROVIDER |
| Note: building 3 - 2nd floor mechanical, plumbing 2nd rough , framing and above ceiling | |||
| HVAC ROUGH | 03/16/2020 | Approval - Private Provider | PPROVIDER |
| Note: building 3 - 3rd floor aHU lids, dampers, insulation and RC , AC closets | |||
| PLUMBING 2ND ROUGH | 03/16/2020 | Approval - Private Provider | PPROVIDER |
| Note: building 3 - 2nd floor mechanical, plumbing 2nd rough , framing and above ceiling | |||
| INSULATION | 03/16/2020 | Approval - Private Provider | PPROVIDER |
| Note: building 3 - 3rd floor aHU lids, dampers, insulation and RC , AC closets | |||
| PLUMBING 2ND ROUGH | 03/13/2020 | Approval - Private Provider | PPROVIDER |
| HVAC OTHER | 03/13/2020 | Approval - Private Provider | PPROVIDER |
| FRAMING | 03/13/2020 | Approval - Private Provider | PPROVIDER |
| ABOVE CEILING | 03/13/2020 | Approval - Private Provider | PPROVIDER |
| FLOOR/WALL PENETRATION | 03/13/2020 | Approval - Private Provider | PPROVIDER |
| HVAC ROUGH | 03/11/2020 | Approval - Private Provider | PPROVIDER |
| PLUMBING 1ST ROUGH | 03/11/2020 | Approval - Private Provider | PPROVIDER |
| FLOOR/WALL PENETRATION | 03/09/2020 | Approval - Private Provider | NDIMATTINA |
| FLOOR/WALL PENETRATION | 03/05/2020 | Approval - Private Provider | PPROVIDER |
| FRAMING | 03/05/2020 | APPROVED | PPROVIDER |
| INSULATION | 03/05/2020 | Approval - Private Provider | PPROVIDER |
| INSULATION | 02/27/2020 | Approval - Private Provider | PPROVIDER |
| Note: building 2 - 2nd floor RC and insulation | |||
| FRAMING | 02/27/2020 | Approval - Private Provider | PPROVIDER |
| Note: 2nd floor RC and insulation | |||
| ELECTRIC 2ND ROUGH | 02/26/2020 | Approval - Private Provider | PPROVIDER |
| ELECTRIC 2ND ROUGH | 02/24/2020 | Approval - Private Provider | PPROVIDER |
| Note: THIS IS A REINSPECTION | |||
| ELECTRIC 2ND ROUGH | 02/20/2020 | Disapproved- Private Provider | PPROVIDER |
| Note: Building 2, 3rd floor 2nd rough electrical failed inspection. | |||
| PLUMBING 2ND ROUGH | 02/20/2020 | Approval - Private Provider | PPROVIDER |
| HVAC ROUGH | 02/20/2020 | Approval - Private Provider | PPROVIDER |
| FRAMING | 02/20/2020 | Approval - Private Provider | PPROVIDER |
| ABOVE CEILING | 02/20/2020 | Approval - Private Provider | PPROVIDER |
| SHEARWALL | 02/20/2020 | Approval - Private Provider | PPROVIDER |
| EXTERIOR WALL SHEATHING / SHEARWALL | 02/14/2020 | Approval - Private Provider | PPROVIDER |
| BLD - SEWER TIE IN | 02/12/2020 | Approval - Private Provider | PPROVIDER |
| INSULATION | 02/03/2020 | Approval - Private Provider | PPROVIDER |
| FRAMING | 01/29/2020 | Approval - Private Provider | PPROVIDER |
| FRAMING | 01/24/2020 | Approval - Private Provider | JMONTARULI |
| SHEARWALL | 01/24/2020 | Approval - Private Provider | JMONTARULI |
| ROOF SHEATHING / BRACE / TIE DOWN | 01/20/2020 | Approval - Private Provider | PPROVIDER |
| EXTERIOR WALL SHEATHING / SHEARWALL | 01/20/2020 | Approval - Private Provider | PPROVIDER |
| EXTERIOR STRAP/CLIP | 01/16/2020 | Approval - Private Provider | PPROVIDER |
| FRAMING | 01/16/2020 | Approval - Private Provider | PPROVIDER |
| ROOF SHEATHING / BRACE / TIE DOWN | 01/15/2020 | Approval - Private Provider | PPROVIDER |
| MONOLITHIC SLAB | 11/06/2019 | Approval - Private Provider | PPROVIDER |
| ELECTRIC 1ST ROUGH | 11/06/2019 | Approval - Private Provider | PPROVIDER |
| FOUNDATION SURVEY - OFFICE USE ONLY | 11/06/2019 | APPROVED | JMUNSON |
| PLUMBING 1ST ROUGH | 10/28/2019 | Approval - Private Provider | PPROVIDER |
| ELECTRIC TEMP POLE | 08/29/2019 | Approval - Private Provider | PPROVIDER |
| Note: Barbie called FPL - Susan 2:45pm |
Review History
| Department | Status | Date In | Date Out |
| SW1 | COMPLETE | 11/04/2019 | 11/06/2019 |
| Note: Released By: JMUNSON | |||
| BLD | COMPLETE | 08/01/2019 | 08/02/2019 |
| Note: Released By: JHINDMAN | |||
| DSD | COMPLETE | 07/16/2019 | 07/16/2019 |
| Note: Released By: DRAMIREZ | |||
| ARCHR | COMPLETE | 07/16/2019 | 07/22/2019 |
| Note: Released By: BDAWSON | |||
| UD1 | COMPLETE | 07/16/2019 | 07/17/2019 |
| Note: Released By: CJOHNSON | |||
| BLD | HOLD | 07/16/2019 | 07/29/2019 |
| Note: Held By: JHINDMAN On page S5.1 Identify the anchorage for the truss to wall connectors as plans do not specify the uplift at the truss locations per 6th ed. FBC 2303.4.4. 2. page 3/s8.2 identify the truss to header anchor. | |||
| PLUM | COMPLETE | 07/16/2019 | 07/30/2019 |
| Note: Released By: MGARRETT | |||
| MECH | COMPLETE | 07/16/2019 | 07/23/2019 |
| Note: Released By: MGARRETT | |||
| ARCHR | HOLD | 05/09/2019 | 05/13/2019 |
| Note: Held By: BDAWSON Provide exterior elevations with colors called out | |||
| BLD | HOLD | 05/09/2019 | 05/23/2019 |
| Note: Held By: JHINDMAN On page S5.1 Identify the anchorage for the truss to wall connectors as plans do not specify the uplift at the truss locations per 6th ed. FBC 2303.4.4. 2. page 3/s8.2 identify the truss to header anchor. | |||
| DSD | HOLD | 05/09/2019 | 05/10/2019 |
| Note: Held By: DRAMIREZ 1. Development Order for the site must be issued prior to issuance of permit. 2. Addresses must be established and all permits must reflect the new address prior to issuance of permit. 3. Amendment to the Innovation District incentives must be approved so they can be applied to the permit prior to issuance. 4. Site Development permit must be ready for issuance prior to issuance of the Commercial Building permit. | |||
| ELEC | COMPLETE | 05/09/2019 | 05/23/2019 |
| Note: Released By: JHINDMAN | |||
| FI1 | COMPLETE | 05/09/2019 | 05/23/2019 |
| Note: Released By: JHINDMAN | |||
| MECH | HOLD | 05/09/2019 | 05/23/2019 |
| Note: Held By: RLEE Provide rated dampers at exhaust duct exterior rated wall penetrations | |||
| PLUM | HOLD | 05/09/2019 | 05/23/2019 |
| Note: Held By: RLEE Provide complete plumbing riser for all of building floors | |||
| UD1 | HOLD | 05/09/2019 | 05/22/2019 |
| Note: Held By: CJOHNSON Show dimensions on the meter room. Show room dimensions, height the meters will be off floor, spacing between meters. Refer to City of Palm Coast meter room detail W-15A for required items to include. Installation will require external antenna. Sensus may be able to help with required accessories. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| CONTRACTOR CHANGE | ¤40.00 | 02/05/2020 |
| CONTRACTOR CHANGE | ¤40.00 | 02/05/2020 |
| 3% FIRE IMPACT FEE CREDIT | (¤261.35) | 08/20/2019 |
| IMPACT FEE FIRE | ¤8,711.82 | 08/20/2019 |
| IMPACT FEE PARKS | ¤33,120.36 | 08/20/2019 |
| IMPACT FEE SCHOOL | ¤36,309.00 | 08/20/2019 |
| IMPACT FEE TRANSPORTATION | ¤67,002.00 | 08/20/2019 |
| 3% PARKS IMPACT FEE CREDIT | (¤993.61) | 08/20/2019 |
| PLAN CHECK FEE | ¤3,285.64 | 08/20/2019 |
| SURCHARGE FS 533.721 | ¤210.97 | 08/20/2019 |
| SURCHARGE - FS 468.631 | ¤316.45 | 08/20/2019 |
| 3% TRANS IMPACT FEE CREDIT | (¤2,010.06) | 08/20/2019 |
| ADMIN COMMERCIAL | ¤60.00 | 08/20/2019 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤145,831.22 |