Permit #2019050452

Permit Details

Status: COED

Parcel Id: 06-12-31-5825-00000-0220
Total Square Footage: 28825 sqft
Block: 00000
Subdivision: 2304 - CENTRAL LANDINGS APARTMENTS AT TOWN CENTER
Location Address: 6000 SUNSET BLVD BLDG 4
Type: BM - BUILDING MULTI - APARTMENT
Issue Date: 08/20/2019
NOC: RECORDED
Applicant name: WILLIAM SCOTT CULP
Owner: CENTRAL LANDINGS PARTNERS LTD & CENTRAL LANDINGS 8

Address

335 N KNOWLES AVE STE 101

WINTER PARK, FL 32789

Lot: 0220
Contracted Stated Job Value: ¤1,700,675.00
Job Description: BLDG #4 - 30 UNIT MULTIFAMILY APARTMENT - CENTRAL LANDINGS
Type: CN

Contractor

WPGC CONSTRUCTIONI, LLC
Status Location Address Mailing Address State License Number
CANCEL

200 EAST CANTON AVE

,

STE 102

WINTER PARK, FL 32789

CGC1524369 (Exp: 08/31/2022)

Sub Contractors

RANCE F BORDERICK
Status Location Address State License Number Phone Fax
ACTIVE

430 WEST DRIVE

ALTAMONTE SPRINGS, FL 32714

EC0000981 (Exp: 08/31/2026) (407)788-3500 407-788-2007
DAVID A CROSON
Status Location Address State License Number Phone
CANCEL

31550 COUNTY ROAD 437

SORRENTO, FL 32776

CFC1426109 (Exp: 08/31/2022) 352-729-7100
JOHN MAXEN BARTKOVICH
Status Location Address State License Number Phone
ACTIVE

818 SHADOWMOSS DR

WINTERGARDEN, FL 32787

CAC1815793 (Exp: 08/31/2026) 407-886-3729
JACK DOUGLAS LANIER
Status Location Address State License Number Phone Fax
ACTIVE

485 COMMERCE WAY

LONGWOOD , FL 32750

CCC058022 (Exp: 08/31/2026) (321)441-2300 (321)441-2313

Inspection History

Type Request Date Result Inspector
FIRE FINAL 05/21/2020 APPROVED WMILLER
Note: THIS IS A REINSPECTION CONTRACTOR SPOKE TO LEE MILLER AND WILL RESCHEDULE AT LATER DATE
BUILDING FINAL 05/20/2020 Approval - Private Provider PPROVIDER
FIRE FINAL 05/20/2020 CANCELLED BY APPLICANT RMARTIN
Note: CONTRACTOR SPOKE TO LEE MILLER AND WILL RESCHEDULE AT LATER DATE
ELECTRIC FINAL 05/20/2020 Approval - Private Provider PPROVIDER
PLUMBING FINAL 05/18/2020 Approval - Private Provider PPROVIDER
HVAC FINAL 05/18/2020 Approval - Private Provider PPROVIDER
U - UTILITY COMMERCIAL FINAL 05/18/2020 APPROVED AHALL
ROOF FINAL 05/06/2020 Approval - Private Provider PPROVIDER
ELECTRIC - EARLY POWER 04/29/2020 Approval - Private Provider PPROVIDER
FIREWALL FINAL 04/06/2020 Approval - Private Provider PPROVIDER
FLOOR/WALL PENETRATION 04/06/2020 Approval - Private Provider PPROVIDER
FLOOR/WALL PENETRATION 04/01/2020 Approval - Private Provider PPROVIDER
Note: building 4 - 3rd floor drywall screw (firewall) and 1st and 2nd floor RC and insulation
FRAMING 04/01/2020 Approval - Private Provider PPROVIDER
Note: building 4 - 3rd floor drywall screw (firewall) and 1st and 2nd floor RC and insulation
FIREWALL FINAL 04/01/2020 Approval - Private Provider PPROVIDER
FIREWALL FINAL 04/01/2020 Approval - Private Provider PPROVIDER
INSULATION 04/01/2020 Approval - Private Provider PPROVIDER
Note: building 4 - 3rd floor drywall screw (firewall) and 1st and 2nd floor RC and insulation
ABOVE CEILING 03/30/2020 Approval - Private Provider PPROVIDER
ABOVE CEILING 03/30/2020 Approval - Private Provider PPROVIDER
FIREWALL FINAL 03/30/2020 Approval - Private Provider PPROVIDER
FRAMING 03/30/2020 Approval - Private Provider PPROVIDER
FRAMING 03/30/2020 Approval - Private Provider PPROVIDER
HVAC ROUGH 03/30/2020 Approval - Private Provider PPROVIDER
HVAC ROUGH 03/30/2020 Approval - Private Provider PPROVIDER
PLUMBING 2ND ROUGH 03/30/2020 Approval - Private Provider PPROVIDER
PLUMBING 2ND ROUGH 03/30/2020 Approval - Private Provider PPROVIDER
FRAMING 03/26/2020 Approval - Private Provider PPROVIDER
INSULATION 03/26/2020 Approval - Private Provider PPROVIDER
GRAVITY SEWER 03/20/2020 APPROVED JGIBSON
PLUMBING 2ND ROUGH 03/19/2020 Approval - Private Provider PPROVIDER
HVAC OTHER 03/19/2020 Approval - Private Provider PPROVIDER
FRAMING 03/19/2020 Approval - Private Provider PPROVIDER
ELECTRIC 2ND ROUGH 03/19/2020 Approval - Private Provider PPROVIDER
ABOVE CEILING 03/19/2020 Approval - Private Provider PPROVIDER
INSULATION 03/16/2020 Approval - Private Provider PPROVIDER
INSULATION 03/16/2020 Approval - Private Provider PPROVIDER
Note: building 4 - ahu lids, dampers and rc channel inspection
ELECTRIC 2ND ROUGH 03/16/2020 Approval - Private Provider PPROVIDER
Note: building 4 - 3rd floor 2nd rough elec
FRAMING 03/16/2020 Approval - Private Provider PPROVIDER
FRAMING 03/16/2020 Approval - Private Provider PPROVIDER
Note: building 4 - ahu lids, dampers and rc channel inspection
HVAC ROUGH 03/16/2020 Approval - Private Provider PPROVIDER
HVAC ROUGH 03/16/2020 Approval - Private Provider PPROVIDER
HVAC ROUGH 03/16/2020 Approval - Private Provider PPROVIDER
Note: building 4 - ahu lids, dampers and rc channel inspection
HVAC ROUGH 03/13/2020 Approval - Private Provider PPROVIDER
HVAC ROUGH 03/13/2020 Approval - Private Provider PPROVIDER
PLUMBING 2ND ROUGH 03/13/2020 Approval - Private Provider PPROVIDER
FOUNDATION SURVEY - OFFICE USE ONLY 03/13/2020 APPROVED - AS NOTED CMORALES
FRAMING 03/13/2020 Approval - Private Provider PPROVIDER
FRAMING 03/13/2020 Approval - Private Provider PPROVIDER
SHEARWALL 02/27/2020 Approval - Private Provider PPROVIDER
Note: building 4 pre-rock screw
INSULATION 02/17/2020 Approval - Private Provider PPROVIDER
BLD - SEWER TIE IN 02/14/2020 Approval - Private Provider PPROVIDER
FRAMING 02/10/2020 Approval - Private Provider PPROVIDER
FRAMING 02/03/2020 Approval - Private Provider PPROVIDER
Note: Building 4 - rod location inspection
SHEARWALL 01/29/2020 Approval - Private Provider PPROVIDER
EXTERIOR STRAP/CLIP 01/20/2020 Approval - Private Provider PPROVIDER
FRAMING 01/20/2020 Approval - Private Provider PPROVIDER
EXTERIOR WALL SHEATHING / SHEARWALL 01/16/2020 Approval - Private Provider PPROVIDER
ROOF SHEATHING / BRACE / TIE DOWN 01/15/2020 Approval - Private Provider PPROVIDER
MONOLITHIC SLAB 11/13/2019 Approval - Private Provider PPROVIDER
ELECTRIC 1ST ROUGH 11/13/2019 Approval - Private Provider PPROVIDER
PLUMBING 1ST ROUGH 10/30/2019 Approval - Private Provider PPROVIDER

Review History

Department Status Date In Date Out
ENGIN1 COMPLETE 02/28/2020 03/13/2020
Note: Released By: CMORALES Foundation Survey. Foundation Survey approval was based on site visit and conversation with Surveyor. Final Survey needs to differentiate between FFE and Garage Floor Elevation.
BLD COMPLETE 08/01/2019 08/02/2019
Note: Released By: JHINDMAN
DSD COMPLETE 07/16/2019 07/16/2019
Note: Released By: DRAMIREZ
ARCHR COMPLETE 07/16/2019 07/22/2019
Note: Released By: BDAWSON
UD1 COMPLETE 07/16/2019 07/17/2019
Note: Released By: CJOHNSON
BLD HOLD 07/16/2019 07/29/2019
Note: Held By: JHINDMAN On page S5.1 Identify the anchorage for the truss to wall connectors as plans do not specify the uplift at the truss locations per 6th ed. FBC 2303.4.4. 2. page 3/s8.2 identify the truss to header anchor.
PLUM COMPLETE 07/16/2019 07/30/2019
Note: Released By: MGARRETT
MECH COMPLETE 07/16/2019 07/23/2019
Note: Released By: MGARRETT
ARCHR HOLD 05/09/2019 05/13/2019
Note: Held By: BDAWSON Provide exterior elevations with colors called out.
BLD HOLD 05/09/2019 05/23/2019
Note: Held By: JHINDMAN On page S5.1 Identify the anchorage for the truss to wall connectors as plans do not specify the uplift at the truss locations per 6th ed. FBC 2303.4.4. 2. page 3/s8.2 identify the truss to header anchor.
DSD HOLD 05/09/2019 05/10/2019
Note: Held By: DRAMIREZ 1. Development Order for the site must be issued prior to issuance of permit. 2. Addresses must be established and all permits must reflect the new address prior to issuance of permit. 3. Amendment to the Innovation District incentives must be approved so they can be applied to the permit prior to issuance. 4. Site Development permit must be ready for issuance prior to issuance of the Commercial Building permit.
ELEC COMPLETE 05/09/2019 05/23/2019
Note: Released By: JHINDMAN
FI1 COMPLETE 05/09/2019 05/23/2019
Note: Released By: JHINDMAN
MECH HOLD 05/09/2019 05/23/2019
Note: Held By: RLEE Provide rated dampers at exhaust duct exterior rated wall penetrations
PLUM HOLD 05/09/2019 05/23/2019
Note: Held By: RLEE Provide complete plumbing riser for all of building floors
UD1 HOLD 05/09/2019 05/22/2019
Note: Held By: CJOHNSON Show dimensions on the meter room. Show room dimensions, height the meters will be off floor, spacing between meters. Refer to City of Palm Coast meter room detail W-15A for required items to include. Installation will require external antenna. Sensus may be able to help with required accessories.

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
CONTRACTOR CHANGE ¤40.00 02/05/2020
CONTRACTOR CHANGE ¤40.00 02/05/2020
3% FIRE IMPACT FEE CREDIT (¤201.04) 08/20/2019
IMPACT FEE FIRE ¤6,701.40 08/20/2019
IMPACT FEE PARKS ¤25,477.20 08/20/2019
IMPACT FEE SCHOOL ¤27,930.00 08/20/2019
IMPACT FEE TRANSPORTATION ¤51,540.00 08/20/2019
3% PARKS IMPACT FEE CREDIT (¤764.32) 08/20/2019
PLAN CHECK FEE ¤1,955.78 08/20/2019
SURCHARGE FS 533.721 ¤126.55 08/20/2019
SURCHARGE - FS 468.631 ¤189.83 08/20/2019
3% TRANS IMPACT FEE CREDIT (¤1,546.20) 08/20/2019
ADMIN COMMERCIAL ¤60.00 08/20/2019
Fees Total Due: ¤0.00 Total Paid: ¤111,549.20