Permit #2019050461

Permit Details

Status: COED

Parcel Id: 06-12-31-5825-00000-0220
Total Square Footage: 3564 sqft
Block: 00000
Subdivision: 2304 - CENTRAL LANDINGS APARTMENTS AT TOWN CENTER
Location Address: 8000 COASTAL TRCE BLDG 11
Type: BM - BUILDING MULTI - APARTMENT
Issue Date: 08/20/2019
NOC: RECORDED
Applicant name: WILLIAM SCOTT CULP
Owner: CENTRAL LANDINGS PARTNERS LTD & CENTRAL LANDINGS 8

Address

335 N KNOWLES AVE STE 101

WINTER PARK, FL 32789

Lot: 0220
Contracted Stated Job Value: ¤210,276.00
Job Description: BLDG #11- 2 UNIT MULTIFAMILY APARTMENT - CENTRAL LANDINGS
Type: CN

Contractor

WPGC CONSTRUCTIONI, LLC
Status Location Address Mailing Address State License Number
CANCEL

200 EAST CANTON AVE

,

STE 102

WINTER PARK, FL 32789

CGC1524369 (Exp: 08/31/2022)

Sub Contractors

RANCE F BORDERICK
Status Location Address State License Number Phone Fax
ACTIVE

430 WEST DRIVE

ALTAMONTE SPRINGS, FL 32714

EC0000981 (Exp: 08/31/2026) (407)788-3500 407-788-2007
DAVID A CROSON
Status Location Address State License Number Phone
CANCEL

31550 COUNTY ROAD 437

SORRENTO, FL 32776

CFC1426109 (Exp: 08/31/2022) 352-729-7100
JOHN MAXEN BARTKOVICH
Status Location Address State License Number Phone
ACTIVE

818 SHADOWMOSS DR

WINTERGARDEN, FL 32787

CAC1815793 (Exp: 08/31/2026) 407-886-3729
JACK DOUGLAS LANIER
Status Location Address State License Number Phone Fax
ACTIVE

485 COMMERCE WAY

LONGWOOD , FL 32750

CCC058022 (Exp: 08/31/2026) (321)441-2300 (321)441-2313

Inspection History

Type Request Date Result Inspector
FIRE FINAL 04/07/2020 APPROVED WMILLER
EXTERIOR ARCHITECTURAL FEATURES 04/07/2020 APPROVED MBACON
U - UTILITY COMMERCIAL FINAL 04/07/2020 APPROVED AHALL
Note: BLDG 11 as part of stage 2
BUILDING FINAL 04/06/2020 Approval - Private Provider PPROVIDER
Note: Building 11 - Building final passed
ELECTRIC FINAL 03/30/2020 Disapproved- Private Provider PPROVIDER
ELECTRIC FINAL 03/30/2020 Approval - Private Provider PPROVIDER
HVAC FINAL 03/26/2020 Approval - Private Provider PPROVIDER
PLUMBING FINAL 03/26/2020 Approval - Private Provider PPROVIDER
ELECTRIC FINAL 03/26/2020 Disapproved- Private Provider PPROVIDER
FOUNDATION SURVEY - OFFICE USE ONLY 03/13/2020 APPROVED - AS NOTED CMORALES
ELECTRIC - EARLY POWER 03/10/2020 Approval - Private Provider PPROVIDER
ELECTRIC TEMP POLE 02/10/2020 Approval - Private Provider PPROVIDER
FIREWALL FINAL 02/10/2020 Approval - Private Provider PPROVIDER
SHEARWALL 02/10/2020 Approval - Private Provider PPROVIDER
SHEARWALL 02/10/2020 Approval - Private Provider PPROVIDER
INSULATION 02/10/2020 Approval - Private Provider PPROVIDER
ELECTRIC 2ND ROUGH 02/05/2020 Approval - Private Provider PPROVIDER
BLD - SEWER TIE IN 02/03/2020 Approval - Private Provider PPROVIDER
PLUMBING 2ND ROUGH 02/03/2020 Approval - Private Provider PPROVIDER
HVAC ROUGH 02/03/2020 Approval - Private Provider PPROVIDER
HVAC ROUGH 02/03/2020 Approval - Private Provider PPROVIDER
ABOVE CEILING 02/03/2020 Approval - Private Provider PPROVIDER
Note: plumbing and mechanical 2nd rough, framing and above ceiling
GRAVITY SEWER 01/30/2020 APPROVED JGIBSON
BLD - SEWER TIE IN 01/30/2020 APPROVED JGIBSON
HVAC ROUGH 01/24/2020 Approval - Private Provider JMONTARULI
SHEARWALL 01/24/2020 Approval - Private Provider JMONTARULI
FRAMING 01/24/2020 Approval - Private Provider JMONTARULI
FRAMING 01/16/2020 Approval - Private Provider PPROVIDER
FRAMING 01/08/2020 Approval - Private Provider PPROVIDER
EXTERIOR STRAP/CLIP 01/08/2020 Approval - Private Provider PPROVIDER
EXTERIOR WALL SHEATHING / SHEARWALL 12/31/2019 Approval - Private Provider PPROVIDER
ROOF SHEATHING / BRACE / TIE DOWN 12/31/2019 Approval - Private Provider PPROVIDER
SECOND FLOOR SLAB 12/02/2019 Approval - Private Provider PPROVIDER
ELECTRIC 1ST ROUGH 11/13/2019 Approval - Private Provider PPROVIDER
MONOLITHIC SLAB 11/13/2019 Approval - Private Provider PPROVIDER
PLUMBING 1ST ROUGH 10/23/2019 Approval - Private Provider PPROVIDER
Note: Building 11

Review History

Department Status Date In Date Out
BLD COMPLETE 04/07/2020 04/09/2020
Note: Released By: PBUCKLEY
ENGIN1 COMPLETE 04/07/2020 04/09/2020
Note: Released By: DLEAP
ENGIN1 COMPLETE 02/28/2020 03/13/2020
Note: Released By: CMORALES Foundation Survey Foundation Survey approval was based on site visit and conversation with Surveyor. Final Survey needs to differentiate between FFE and Garage Floor Elevation.
BLD COMPLETE 08/01/2019 08/02/2019
Note: Released By: JHINDMAN
DSD COMPLETE 07/15/2019 07/15/2019
Note: Released By: JGONZALEZ
ARCHR COMPLETE 07/15/2019 07/15/2019
Note: Released By: BDAWSON
BLD HOLD 07/15/2019 07/29/2019
Note: Held By: JHINDMAN On page S5.1 Identify the anchorage for the truss to wall connectors as plans do not specify the uplift at the truss locations per 6th ed. FBC 2303.4.4. 2. page 3/s8.2 identify the truss to header anchor.
MECH COMPLETE 07/15/2019 07/23/2019
Note: Released By: MGARRETT
ARCHR HOLD 05/09/2019 05/13/2019
Note: Held By: BDAWSON Provide exterior elevations with colors called out.
BLD HOLD 05/09/2019 05/23/2019
Note: Held By: JHINDMAN On page S5.1 Identify the anchorage for the truss to wall connectors as plans do not specify the uplift at the truss locations per 6th ed. FBC 2303.4.4. 2. page 3/s8.2 identify the truss to header anchor.
DSD HOLD 05/09/2019 05/10/2019
Note: Held By: DRAMIREZ 1. Development Order for the site must be issued prior to issuance of permit. 2. Addresses must be established and all permits must reflect the new address prior to issuance of permit. 3. Amendment to the Innovation District incentives must be approved so they can be applied to the permit prior to issuance. 4. Site Development permit must be ready for issuance prior to issuance of the Commercial Building permit.
ELEC COMPLETE 05/09/2019 05/23/2019
Note: Released By: JHINDMAN
FI1 COMPLETE 05/09/2019 05/23/2019
Note: Released By: JHINDMAN
MECH HOLD 05/09/2019 05/23/2019
Note: Held By: RLEE Provide rated dampers at exhaust duct exterior rated wall penetrations
PLUM COMPLETE 05/09/2019 05/23/2019
Note: Released By: RLEE
UD1 COMPLETE 05/09/2019 05/10/2019
Note: Released By: CJOHNSON

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
CONTRACTOR CHANGE ¤40.00 02/05/2020
CONTRACTOR CHANGE ¤40.00 02/05/2020
3% FIRE IMPACT FEE CREDIT (¤13.40) 08/20/2019
IMPACT FEE FIRE ¤446.76 08/20/2019
IMPACT FEE PARKS ¤1,698.48 08/20/2019
IMPACT FEE SCHOOL ¤1,862.00 08/20/2019
IMPACT FEE TRANSPORTATION ¤3,436.00 08/20/2019
3% PARKS IMPACT FEE CREDIT (¤50.95) 08/20/2019
PLAN CHECK FEE ¤241.82 08/20/2019
SURCHARGE FS 533.721 ¤17.75 08/20/2019
SURCHARGE - FS 468.631 ¤26.63 08/20/2019
3% TRANS IMPACT FEE CREDIT (¤103.08) 08/20/2019
ADMIN COMMERCIAL ¤60.00 08/20/2019
Fees Total Due: ¤0.00 Total Paid: ¤7,702.01