I want to search for...

Permit #2019050967

Permit Details

Status: COED

Parcel Id: 07-11-31-7059-00140-0090
CONDITIONED SPACE: 1983 sqft
GARAGE: 516 sqft
OPENED PORCH (WITH ROOF) : 48 sqft
OPENED PORCH (WITH ROOF) : 106 sqft
Total Square Footage: 2653 sqft
Block: 00140
Subdivision: -
Job Phone: 407-807-0656
Location Address: 19 SEA SERPENT TR E
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 09/09/2019
NOC: RECORDED
Applicant name: NAVIN SUGRIM
Owner: DLP BRITE HOMES LLC

Address

605 PALENCIA CLUB DRIVE

ST AUGUSTINE, FL 32095

Lot: 0090
Contracted Stated Job Value: ¤135,076.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

DLP BUILDERS LLC
Status Location Address State License Number Phone
CANCEL

7345 GREENBRIAR PKWY

ORLANDO, FL 32819

CBC1263567 (Exp: 08/31/2022) 407-807-0656

Sub Contractors

TERRY BRICE DICKERSON
Status Location Address State License Number Phone
ACTIVE

4300 ST JOHN'S PARKWAY

ALPHARETTA, GA 30009

CCC1326209 (Exp: 08/31/2026) 407-548-6733
JONATHAN M PEARSON
Status Location Address State License Number Phone Fax
ACTIVE

209 N FORSYTH ST

BUNNELL, FL 32110

CFC1425941 (Exp: 08/31/2026) 386-597-0944 386-437-4996
JOSEPH H STRADA JR
Status Location Address State License Number Phone
CANCEL

3400 ST JOHNS PKWY

SANFORD, FL 32771

EC13003715 (Exp: 08/31/2022) 877-906-1113
ROBERT G DELLO RUSSO
Status Location Address State License Number Phone Fax
DECEASED

531 CODISCO WAY

SANFORD, FL 32771

CAC032448 (Exp: 08/31/2022) (407)831-2665 (407)333-3853

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 04/29/2020 FINAL APPROVED FWILLIS
Note: THIS IS A REINSPECTION Outside Unit has a Max Breaker of 25. Inside the Breaker is 30. Exceeds Maximum. Hot water not working.
BLD - BUILDING FINAL 04/28/2020 Disapproved - NO FEE FWILLIS
Note: Outside Unit has a Max Breaker of 25. Inside the Breaker is 30. Exceeds Maximum. Hot water not working.
U -UTILITY RESIDENTIAL FINAL 04/27/2020 APPROVED AHALL
BLD - BUILDING FINAL 04/27/2020 CANCELLED BY APPLICANT WEB
FINAL SURVEY (OFFICE USE ONLY) 04/24/2020 APPROVED MMAJEWSKI
ROW FIELD SURVEY /GRADING CERTIFICATION 04/24/2020 APPROVED MMAJEWSKI
ROW - STORMWATER FINAL 04/24/2020 APPROVED MMAJEWSKI
ROW - FINAL APRON (AFTER POUR) 04/24/2020 APPROVED MMAJEWSKI
ELECTRIC - EARLY POWER 03/27/2020 APPROVED - AS NOTED RMARTIN
Note: EMAILED FPL RELEASED POWER 9:20
ELECTRIC - EARLY POWER 03/10/2020 Disapproved -FEE REQUIRED JMUNSON
Note: Not Ready.
ROW- PRE-APRON (PRE-POUR) 02/05/2020 APPROVED - AS NOTED MMAJEWSKI
Note: It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete.
U - SEWER TIE IN 01/27/2020 APPROVED JGIBSON
GRAVITY SEWER TEST 01/27/2020 APPROVED JGIBSON
PEP TANK INSTALLATION REQUEST 01/13/2020 APPROVED CSTONE
LATH/BRICK/ WATER BARRIER 01/09/2020 APPROVED FWILLIS
INSULATION 12/31/2019 APPROVED FWILLIS
ALL ROUGH 12/27/2019 APPROVED FWILLIS
ROOF VALLEY & METAL 12/16/2019 APPROVED WMILLER
ELECTRIC-TUG 12/16/2019 APPROVED - AS NOTED RMARTIN
Note: EMAILED FPL RELEASED POWER 9:00
ROOF SHEATHING / BRACES/TIES/DOWN CELL 12/12/2019 APPROVED FWILLIS
TIE BEAM / LINTEL 12/02/2019 APPROVED FWILLIS
FOUND SURVEY APPROVED (OFFICE) 11/27/2019 APPROVED TBAKER
MONOLITHIC SLAB 11/19/2019 APPROVED FWILLIS
PLUMBING 1ST ROUGH UNDERGROUND 11/15/2019 APPROVED FWILLIS
WATER METER INSTALLATION REQUEST 11/15/2019 APPROVED CSTONE

Review History

Department Status Date In Date Out
ENGIN1 COMPLETE 11/27/2019 11/27/2019
Note: Released By: TBAKER
BLD COMPLETE 09/20/2019 09/27/2019
Note: Released By: MGARRETT
ZON COMPLETE 08/28/2019 08/28/2019
Note: Released By: AMOBLEY
ZON HOLD 07/12/2019 07/12/2019
Note: Held By: TDOAK REPEAT COMMENT: Left side setback (FACING THE HOUSE FROM THE ROAD) must be from the CLOSEST point of the proposed home to the property line. The lot is not parallel.
UD1 COMPLETE 07/12/2019 07/17/2019
Note: Released By: AHALL
SW1 COMPLETE 07/12/2019 07/12/2019
Note: Released By: JMUNSON
ENGIN1 COMPLETE 07/12/2019 07/15/2019
Note: Released By: TBAKER
PLUM COMPLETE 06/18/2019 06/25/2019
Note: Released By: JHINDMAN
ZON HOLD 06/18/2019 06/18/2019
Note: Held By: TDOAK Left side setback must be from the closest point of the proposed home to the property line. The lot is not parallel.
SWALE COMPLETE 05/29/2019 06/13/2019
Note: Released By: TBAKER
BLD COMPLETE 05/22/2019 05/30/2019
Note: Released By: JHINDMAN
CUSVC COMPLETE 05/22/2019 05/22/2019
Note: Released By: AROSCOE
ELEC COMPLETE 05/22/2019 05/30/2019
Note: Released By: JHINDMAN
ENGIN1 COMPLETE 05/22/2019 05/29/2019
Note: Released By: TBAKER
LOCATE COMPLETE 05/22/2019 05/24/2019
Note: Released By: CSTONE
MECH COMPLETE 05/22/2019 05/30/2019
Note: Released By: JHINDMAN
PLUM HOLD 05/22/2019 05/30/2019
Note: Held By: JHINDMAN 1. Provide a plumbing riser signed by the plumbing contractor with their license number.
SW1 COMPLETE 05/22/2019 05/30/2019
Note: Released By: JHINDMAN
UD1 COMPLETE 05/22/2019 05/30/2019
Note: Released By: AHALL
ZON HOLD 05/22/2019 05/23/2019
Note: Held By: AMOBLEY Must have at least four shrubs along each side Must have 7 gallon shrubs screening ac pad Please specify material of driveway on site plan/survey

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
CONTRACTOR CHANGE ¤40.00 05/06/2020
REINSPECTION FEE ¤40.00 05/06/2020
NEW RESIDENTIAL INSPECTIONS ¤494.00 09/09/2019
SITE PLAN 20 ¤20.00 09/09/2019
SURCHARGE FS 533.721 ¤11.59 09/09/2019
SURCHARGE - FS 468.631 ¤17.38 09/09/2019
STORM WATER PERMIT FEES ¤80.00 09/09/2019
3% TRANS IMPACT FEE CREDIT (¤48.96) 09/09/2019
SEWER CREDIT (¤1,147.00) 09/09/2019
SEWER INSPECTION ¤25.00 09/09/2019
SEWER CAPITAL FACILITY ¤4,515.25 09/09/2019
WATER CAPITAL FACILITY FEE ¤3,314.84 09/09/2019
ELECTRIC FEE ¤208.20 09/09/2019
3% FIRE IMPACT FEE CREDIT (¤6.70) 09/09/2019
IMPACT FEE FIRE ¤223.38 09/09/2019
IMPACT FEE PARKS ¤849.24 09/09/2019
IMPACT FEE SCHOOL ¤3,600.00 09/09/2019
IMPACT FEE TRANSPORTATION ¤1,632.00 09/09/2019
MECHANICAL FEE ¤208.20 09/09/2019
WATER -IRRIGATION INSPECTION ¤25.00 09/09/2019
3% PARKS IMPACT FEE CREDIT (¤25.48) 09/09/2019
PLAN CHECK FEE ¤98.80 09/09/2019
PLUMBING FEE ¤208.20 09/09/2019
METER - DEPOSIT ¤60.00 09/09/2019
WATER- TURN ON ¤25.00 09/09/2019
ADMIN FEE ¤20.00 09/09/2019
CONNECTION FEES ¤985.25 09/09/2019
Fees Total Due: ¤0.00 Total Paid: ¤15,473.19